January 2011 Permit Processing Times: Insights on Repair and Development Permits

In January 2011, a total of 1,707 repair permits were issued, with an average time of less than one day for 439 permits at the counter. For small to medium projects, 821 permits were processed, with times to appointment, review, and customer interaction averaging 6, 16, and 35 days respectively, totaling 57 days. Medium to large projects saw only 14 permits issued, taking an average of 82 days in total. The green permit process issued 6 permits, with a total processing time of 36 days, underscoring the varied timelines of permit processing across different categories.

nelia
Télécharger la présentation

January 2011 Permit Processing Times: Insights on Repair and Development Permits

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. January, 2011 Time to Permit Repair Permits (EPP)* Average for January (1707 permits Issued) 8 Calendar Days with repair permits (at counter 439) taking less than 1 day. * Replacement of plumbing fixtures, electrical lights, tuck pointing, etc. Small to Medium (SPR)* Average for January (821 Permits Issued)* Time to appointment 6 Calendar Days Time to review 16 Calendar Days Time with customer 35 Calendar Days Total Time 57 Calendar Days * Single family dwelling, strip centers, interior buildouts. Medium to Large Projects (Developer Services) Average for January (14 Permits Issued) Time to appointment 9 Calendar Days Time to review 10 Calendar Days Time with customer 65 Calendar Days Total Time 82 Calendar Days * Big box stores, Hospitals, Schools, High-rises. Green Permit Process * Average for January (6 Permits issued) Time to appointment 4 Calendar Days Time to review 9 Calendar Days Time with customer 23 Calendar Days Total Time 36 Calendar Days *LEED certified projects, Chicago Green Homes and Green Elements

More Related