Innovative Energy Solutions in Lyon: A Focus on Reducing Consumption and Increasing Renewables

The Lyon Confluence project, led by Project Manager Maxime Valentin, aims to significantly reduce energy consumption by 40% and increase reliance on renewable energy sources to 80%. This ambitious project encompasses three key blocks—A (19,401 m²), B (33,071 m²), and C (28,220 m²)—totaling over 80,000 m² of development. Detailed scheduling and phases from earthwork to finishing work are set for 2007-2009. For inquiries, contact ENERTECH WP leader Pierre Joutard at SEM Lyon Confluence.

neorah
Télécharger la présentation

Innovative Energy Solutions in Lyon: A Focus on Reducing Consumption and Increasing Renewables

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RENAISSANCE LYON WP3 DEMONSTRATION Maxime VALENTIN Project Manager & Lyon confluence

  2. CONCERTO • 1/Reducing energy consumption • - 40% • 2/ Renewable energies • 80%

  3. Block A

  4. Block A – 19 401 m²

  5. Block a Schedule 2007 2008 2009 June Sept Dec Mar June Sept Dec Mar June Sept Dec Earthwork and Infrastructure Superstructure Finishing Work Ending

  6. BLOCK B

  7. Bock B – 33 071 m²

  8. Block b Schedule 2007 2008 2009 June Sept Dec Mar June Sept Dec Mar June Sept Dec Mar Earthwork and Infrastructure Superstructure Finishing Work Ending

  9. BLOCK C

  10. Block C – 28 220 m²

  11. Block c Schedule 2007 2008 2009 June Sept Dec Mar June Sept Dec Mar June Sept Dec Mar Earthwork and Infrastructure Superstructure Finishing Work Ending

  12. Blocks A,B and C – 80 357 m²

  13. Conclusions ENERTECH WP leader contact Pierre Joutard, Directeur adjoint SEM Lyon Confluence Tel: +33.(0)4.78.38.74.00 pjoutard@lyon-confluence.fr