1 / 7

Lukasz Zwalinski, Michal Zimny, Piotr Gach, Michal Zabek

ATLAS IBL CO2 cooling Vacuum system commissioning status. Lukasz Zwalinski, Michal Zimny, Piotr Gach, Michal Zabek. IBL CO 2 cooling progress meeting 10.04.2014. IBL Vacuum commissioning status. Hardware: Vacuum control cabinet installed in USA15

nerys
Télécharger la présentation

Lukasz Zwalinski, Michal Zimny, Piotr Gach, Michal Zabek

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS IBL CO2 cooling Vacuum system commissioning status Lukasz Zwalinski,Michal Zimny, Piotr Gach, Michal Zabek IBL CO2 cooling progress meeting 10.04.2014

  2. IBL Vacuum commissioning status Hardware: • Vacuum control cabinet installed in USA15 • Temporary power supply cable for normal and UPS power connected • Final power supply connection – waiting for EN/EL • All necessary electrical modification already corrected (Electrical diagrams updated) All documentation available in EDMS https://edms.cern.ch/cedar/plsql/project.info?cookie=13329359&proj_id=1748151522&p_tab=TAB3 Vacuum control cabinet FCTIR-00096 IBL CO2 cooling progress meeting 10.04.2014

  3. IBL Vacuum commissioning status Vacuum gauges Hardware: I/O check finished !!! but … • All actuators checked • Sensors connection verified • Vacuum gauges still need some calibration Vacuum box FCTIR - 00099 Electrical valves Hardware in UX15 level 6 LAr area IBL CO2 cooling progress meeting 10.04.2014

  4. IBL Vacuum control status Hardware: • Problem with an oil for diffusion and backing pumps • Finally successfully ordered – waiting for the delivery • O-rings replacement - completed Backing pumps O-rings Diffusion pumps IBL CO2 cooling progress meeting 10.04.2014

  5. IBL Vacuum commissioning status Software tools: • WinCC OA user interfaces- completed • All accessible from the level of one application • Recipes - completed • LHC logging and LASER – to be done once system fully operational PLC modification: • Swap procedure upgraded • Scaling for all PT sensor – has to be changed IBL CO2 cooling progress meeting 10.04.2014

  6. IBL Vacuum commissioning status We have no delay at this moment ! Once TPG calibrated and diffusion and backing pumps filled with oil we can start final functional tests for both systems. IBL CO2 cooling progress meeting 10.04.2014

  7. Thank you for your attention IBL CO2 cooling progress meeting 10.04.2014

More Related