1 / 42

Final Thesis – Nathan Braskey Construction Option Craig Dubler

Final Thesis – Nathan Braskey Construction Option Craig Dubler. Sunnyvale plaza. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations. Project Overview. Size: 752,000 Gross Sq. Ft.

nijole
Télécharger la présentation

Final Thesis – Nathan Braskey Construction Option Craig Dubler

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Final Thesis – Nathan BraskeyConstruction OptionCraig Dubler Sunnyvale plaza

  2. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Project Overview Size: 752,000 Gross Sq. Ft. Stories: 15 Above Grade, 7 Below Grade Location:Mid-Atlantic Prime Cost: $500 million Contract: Guaranteed Maximum Price Delivery Method: Design-Build Completion: May 2014 Architect: Cooper Carry, TVS Gen. Contractor: Hensel Phelps Structural: GEI Consultants, Inc. MEP: GHT Limited Electrical: Truland Systems

  3. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Analysis Overview Analysis #1: Implementation of A Stormwater Harvesting System Analysis #2: Analysis of Excavation Method Analysis #3: Façade Retention Method Analysis #4: Profitability of Early Scheduled Opening

  4. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Analysis #1:Implementation of A Stormwater Harvesting SystemBreadth 1: Plumbing

  5. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Average Water Usage

  6. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Roof Area Consideration

  7. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Roof Area Consideration

  8. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Water Utility Fee Analysis

  9. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Water Utility Fee Analysis

  10. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Results

  11. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Results

  12. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Analysis #2:Analysis of Excavation Method

  13. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Background Information / Research

  14. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Background Information / Research

  15. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Background Information / Research

  16. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Analysis #3:Façade Retention Method Breadth 2: Structural

  17. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Background Information

  18. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Retaining Structure Analysis

  19. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Retaining Structure Analysis

  20. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Retaining Structure Analysis

  21. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Cost Analysis

  22. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Cost Analysis

  23. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Cost Analysis

  24. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Schedule Analysis

  25. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Schedule Analysis

  26. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Schedule Analysis

  27. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Analysis #4:Profitability of Early Scheduled Opening

  28. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Background Information March 20 – April 13: Cherry Blossom Festival

  29. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Financial Analysis

  30. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Financial Analysis

  31. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Financial Analysis

  32. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations General Conditions

  33. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Results

  34. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Conclusion Analysis 1: • Annual savings of $27,800 • Payback period of 2.5 years Analysis 3: • Decrease schedule by 30 days • Cost savings of $832,700 Analysis 4: • Added revenue of $14,500,000 • Profitability of $2,140,000 Summary: • Decrease schedule by 30 days • Total Profit of $3 million • Annual Savings of $27,800

  35. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Acknowledgements Academic: Dr. Craig Dubler - Construction Advisor Penn State AE Faculty Special Thanks: Chris Mihalick Keith Bush David Webb Jeff Overmiller PACE Industry Members Family and Friends

  36. Project Overview Analysis Overview Analysis 1 Analysis 2 Analysis 3 Analysis 4 Conclusions & Recommendations Sunnyvale Plaza

  37. Analysis #1: Zone Rainwater Collection

  38. Analysis #1: Total Rainwater Collection

  39. Analysis #3: New Construction Costs

  40. Analysis #3: Renovation Costs

  41. Analysis #3: New Construction Durations

  42. Analysis #4: Hotel Rate Data

More Related