1 / 16

Final Presentation

Final Presentation. Mark Dubosky Eyob Kidanmariam Rashmi Nagaraja Challa Bonja Hakan Ordek Amara Kaba. General Project Information. External Deliverables Produced Project Management Tool Project Management Plan Weekly Activity and Status Report Internal Deliverables Produced

oded
Télécharger la présentation

Final Presentation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Final Presentation Mark Dubosky Eyob Kidanmariam Rashmi Nagaraja Challa Bonja Hakan Ordek Amara Kaba

  2. General Project Information • External Deliverables Produced • Project Management Tool • Project Management Plan • Weekly Activity and Status Report • Internal Deliverables Produced • Software Design Document • Test Cases Document • Test Execution Document • User Manual Document

  3. Project Information • Used MS Project to manage schedule • Created and used yahoo group page for communication and file management. • Regular weekly meeting to report status on individual assignment.

  4. Product Information • Used Visual Studio .NET (C#) • Used MS Access for Database. • Total LOC Count ~1.5KLOC • Assuming the project to be ‘Organic’ and Using the default ‘Nominal’ value for all cost drivers • The amount effort needed is 4.9 PM • The actual effort expended is 2.2 PM

  5. Our Initial Goals

  6. Planned Vs Actual Effort

  7. Planned Vs Actual (Schedule) 10/14 10/25 10/30 11/28 11/29 10/11 3 days (50%) Late Requirement 11/25 5 days (33%) Late 3 days (7.5%) Early Design Coding On Time Testing Plan Actual 10/13 11/23 10/6 10/18 11/20 10/11

  8. Plan Evaluation • Our initial plan shows much higher effort. • Our initial schedule assumed much higher resource (in persons month) than actually available. • Created some challenge and room for adjustment.

  9. Actual Outcome Evaluation • Used much less effort in all activities but finished late in earlier activities such as requirement analysis and design. • Adjustment was made to make sure all committed requirements can be completed and tested in time.

  10. Adjustment on Schedule • New deadline was drafted by the team just for coding to ensure in time completion. • Team members put efforts needed within the scheduled timeframe; thus, deadline was met with no hindrance.

  11. Testing • Definitions for Severity Level • Very High : system crashes; or there is a major function working incorrectly; or the data in the database is corrupted and the system can not be used. • High: there is a major function working incorrectly but there is a work around; or the query results are not correctly formatted or sized but the data is accurate; or the message or documentation is incorrect • Medium: there is a minor functional problem and there is a work around; the user interface has wrong terminology or confusing message. • Low: minor cosmetic looks problem; or functionally inconvenient but not incorrect.

  12. Planning • Strength – Having enough buffer time and effort to compensate shortfalls. • Problem - Our initial plan with regard to effort estimation and scheduling was not realistic. • Cause - Resource, especially skill and time, was not delivered as promised. • Action – Re-draft a schedule to ensure in time completion of the most critical activity. • Lesson Learned – Must come up with the mechanism to assure the promised effort is really available.

  13. Organizing • Strength – Used skill matrix to establish task assignment among team members. • Problem – Team members unable to complete assigned tasks in time. • Cause - Assignments given to individual members in earlier phases were too broad. • Action – We started to assign specific tasks with deadlines to individual members. • Lesson Learned – Task assigned to individual should always be specific and should include due date.

  14. Monitoring • Strength – Tracking project progress through weekly status meeting. • Problem – Lack of accountability in terms of meeting a deadline for a specific assignment. • Cause – Assigned tasks were too broad and not be able to be tracked easily in weekly bases in early stages. • Action – Enforced specific tasks to be completed in time.

  15. Adjusting • Adjusting the schedule to successfully complete activities on time. • Test case design started earlier than scheduled. • Coding schedule re-planned to ensure in time completion. • Adjusting the task assignment to be specific enough for monitoring.

More Related