1 / 14

BIM: BEYOND CLASH DETECTION A Jobsite Level Perspective

BIM: BEYOND CLASH DETECTION A Jobsite Level Perspective. THE BIG PICTURE. DESIGN & DETAILING. INSTALLATION PLANNING . TRACKING. WHAT IS BIM?. Quality Control. xD. Scheduling (4D). 3D Coordination. Estimating (5D). RFI/Submittal Tracking. Material Tracking. Facilities Management.

olinda
Télécharger la présentation

BIM: BEYOND CLASH DETECTION A Jobsite Level Perspective

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BIM: BEYOND CLASH DETECTION A Jobsite Level Perspective THE BIG PICTURE DESIGN & DETAILING INSTALLATION PLANNING TRACKING

  2. WHAT IS BIM? Quality Control xD Scheduling (4D) 3D Coordination Estimating (5D) RFI/Submittal Tracking Material Tracking Facilities Management Turnover/ Closeout

  3. THE BIG PICTURE OLD ISSUE TRACKING NEW ISSUE TRACKING Field Notes BIM Phone Calls How much is there to build? Email Are we ready to build it? Meetings & Conversations When we will build it? Independent Lists What could prevent us from building it?

  4. NEED FOR CHANGE Basic Sequence Design - Project Fabricate - Project Build - Project Advanced Sequence Design - Steel Fab - Steel Build - Steel Design - Interiors Fab - Interiors Build - Interiors Ideal Sequence GREATER COMPLEXITY REQUIRES TIGHTER CONTROL AND BETTER ISSUE MANAGEMENT Design – Steel 1 Fab – Steel 1 Build – Steel 1 Design – Steel 1 Fab – Steel 1 Build – Steel 1 Design – Steel 1 Fab – Steel 1 Build – Steel 1

  5. DESIGN ISSUES • Communicate requests for information through the model • Provide transparency & consensus • Avoid issue stagnation

  6. SUBMITTAL PROGRESS • Input submittal status into model during review • Clearly identify pieces to be resubmitted • Avoid fabrication delays

  7. FABRICATION STATUS Started Fab • Communicate “how its coming along” Inspected Courtesy of Schuff Steel

  8. OVERALL PLANNING Sequence 3 Sequence 2 Sequence 1 • Show the overall plan • Helpful, but there’s more…

  9. DETAIL PLANNING TWO WEEKS OUT NEXT WEEK THIS WEEK • Communicates the exact items in each schedule task • Utilized at weekly onsite meetings • Ensures all items needed for the successor are completed • Helpful, but there’s still more…

  10. DETAIL PLANNING • Analyze quantities • Validate resources needed • Instill greater accuracy into schedules

  11. CHANGES 1. Steel Added 3. Other Pieces Placed on Hold Courtesy Schuff Steel • Extract change quantities from model • Agree on pieces to be placed on hold until change is fully designed 2. Quantified

  12. MATERIAL TRACKING 2. Logged 3. Model Updated 1. Material Rec. • Understand what’s onsite and what’s not 4. “I NEED THIS PIECE, NOW!”

  13. LESSONS LEARNED Project specific problems dictate BIM use and value. PROJECT A: Quality Control xD Scheduling (4D) Quality Control 3D Coordination 3D Coordination Estimating (5D) Material Tracking RFI/Submittal Tracking Scheduling (4D) Material Tracking PROJECT B: Facilities Management Turnover/ Closeout Facilities Management 3D Coordination Turnover/ Closeout RFI/Submittal Tracking

  14. LESSONS LEARNED Partners using BIM efficiently are absolutely necessary. • Integrate BIM with Other Processes • Utilize BIM for Drawing Creation Submittal Review Thanks to Schuff Steel, Goody Clancy Architects, Weldon Steel, Walter P. Moore Engineers, & Shockey Precast for the models in this presentation. Shop Fabrication

More Related