1 / 29

Chapter 5 Project Planning

Chapter 5 Project Planning. “ If you don’t plan for the project, you are planning for failure” “ Plans act as a road map of complicated process to manage project”. 6 Stages of Project Planning. Preliminary coordination with various parties(client,developer,govt. agency…)

omer
Télécharger la présentation

Chapter 5 Project Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 5 Project Planning “ If you don’t plan for the project, you are planning for failure” “ Plans act as a road map of complicated process to manage project” Chapter 5 Planning

  2. 6 Stages of Project Planning • Preliminary coordination with various parties(client,developer,govt. agency…) • Provide detail description of various tasks involved. • Deriving project budget. • Work on schedule. • Project status report. • Project termination. Chapter 5 Planning

  3. Focus of this chapter • Discuss the first two stages of project planning. • Develop tools and techniques for the planning process. Chapter 5 Planning

  4. Why initial project coordination with various parties crucial? • Define objectives & scopes of the project. • Technical objectives are established. • Basic areas of performance responsibilities delegated. • Tentative schedules and budgets are worked out. Chapter 5 Planning

  5. What is project’s deliverables? • Involving client in early part of planning process. • Determine client’s needs and expectations • Some project starts with front ends – bidding all the way to commissioning and delivery • Others may be construction on product development Chapter 5 Planning

  6. 9 Key Elements of Project Plan • Overview • Short summary of the objectives and scope of the project. • Objectives • Detailed statement of the goals (profit, etc ….) • General Approach • Describes both the managerial and the technical approaches. • Contractual Aspects • A complete list and description of all reporting requirement. Chapter 5 Planning

  7. Elements of Project Plan (cont.) • Schedules • Various schedule and lists of all milestone. • Resources • Budget. • Cost monitoring and control. • Personnel • Personnel requirements (subcontracting) • Evaluation Methods • Be evaluated against the standard. • Potential Problems • Anticipate potential difficulties. Chapter 5 Planning

  8. Chapter 5 Planning

  9. Chapter 5 Planning

  10. Role of System Integration in Project Management • Integrating the technical disciplines (science or art) of the project to achieve the customer’s objectives. • Who is the customer? Chapter 5 Planning

  11. 3 Major Objectives of System Integration • Performance • System design, reliability, quality, maintainability, etc. • Effectiveness • Design system to achieve performance in an optimal manner. • Cost • Value engineering examines all cost trade off. Chapter 5 Planning

  12. Hierarchical Planning System • Goals must be specified. • Identifying the set of required activities to achieve the goals. • Each activities and events can be decomposed into sub-activities and sub-events. Chapter 5 Planning

  13. Planning Process Tools • Gozinto Chart. • Work Breakdown Structure (WBS). • Linear Responsibility Chart. • TREND • Plan to include design, fabrication/construction(prototype), mass production • R & D is also a project - > uncertainties Chapter 5 Planning

  14. Gozinto Chart • Named after famous Italian mathematician, Prof. Zepartzat Gozinto. • Similar set-up with Bill of Materials. • A Tree-Diagram. Chapter 5 Planning

  15. Chapter 5 Planning

  16. Work Breakdown Structure (WBS) • Project sub-divided into hierarchical units of tasks, work packages, and work units. • Each part of unit tasks, work packages and work units is budget able, in terms of money, labor hours, and other requisite resources. Chapter 5 Planning

  17. Work Breakdown Structure (WBS) • Project is breakdown into a group of activities. • Each activity is breakdown into a task list. • This task list is put into a calendar. • Then, assign people, time, money and other resources. Chapter 5 Planning

  18. Activity Calendar Work Breakdown Structure (WBS) • Schedule Task list into calendar. • Assigning people, time, money to each activity. • Make themselves competent. • Managing “intelligent” people. Chapter 5 Planning

  19. Activities: Work Breakdown Structure • Breakdown task into activities • Top-down refinement possible • List activities which form a single operation or function which you know is achievable • Work breakdown structure • (Product breakdown structure) Chapter 5 Planning

  20. Chapter 5 Planning

  21. Example of WBS: “Holiday” holiday travel documents booking household passport tickets choose resort confirm cat! brochures insurance Chapter 5 Planning

  22. List of activities • Booking: • get brochures • choose resort • make booking • confirm booking • Travel documents: • check passport • book tickets • get insurance • Household: • feeding the cat! • This is a simple • example: • inoculations • visas • travel money • etc. Chapter 5 Planning

  23. Time Management • When activities happen: • Start and finish • How long they take: • Estimates vs. actual? • Relationship between activities: • Dependencies • Parallel activities Chapter 5 Planning

  24. Gantt chart Chapter 5 Planning

  25. People • Task assignment • Responsibility for task completion: • Task management • Liaison with other tasks • Meetings Chapter 5 Planning

  26. Linear Responsibility Matrix • Show the relationship of personnel (who is responsible for what) and to identify where special coordination is necessary. Chapter 5 Planning

  27. Linear Responsibility Matrix - Holiday Chapter 5 Planning

  28. Linear Responsibility Example Chapter 5 Planning

  29. Linear Responsibility Example Chapter 5 Planning

More Related