Explore beam instrumentation, BPM activities, and future proof-of-principle demonstrations within allocated budget constraints in the field of beam instrumentation. Learn about CTF3 tests, bunch length measurement, Dundee University involvement, and non-going activities like intensity measurements. Discover the challenges of allocating a limited budget of 240kCHF and the importance of optimizing resources for all instruments in the beam instrumentation domain.
E N D
BEAM INSTRUMENTATION Beam instrumentation
Other activities Beam instrumentation
Other activities Parameter specifications for all instruments CTF3 tests / proof of principle Future activity: Bunch length measurement, resolution 10-20fs, Dundee university. No resources for the moment. Non going activities Intensity measurements 0.1% All injector and transfer line instruments Beam instrumentation
Budget 2010 But only 240kCHF allocated…so no money for hardware!! Beam instrumentation
MB BPM Beam instrumentation