1 / 10

Les Recksiedler

Three Winding ConverterTransformer Gassing and Failures. Les Recksiedler. Background – Transformers with a Wye and Delta secondary winding . Similar transformers not gassing or failing Increased harmonic currents No gassing during factory load run

oro
Télécharger la présentation

Les Recksiedler

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Three Winding ConverterTransformer Gassing and Failures Les Recksiedler

  2. Background – Transformers with a Wye and Delta secondary winding • Similar transformers not gassing or failing • Increased harmonic currents • No gassing during factory load run • No increase in gassing during 2 day Field test load run • One supplier known for “cookie cutter” approach • Failure of three winding transformers in USA analyzed to be due to harmonics. • All transformer in each HVDC system either gassing or not. • Data is sparse

  3. Case A– Three Phase Transformers with a Wye and Delta secondary winding • HVDC System one year earlier all transformers not gassing • All Transformer one year later gassing badly • One transformer failed after 5 years • 3 transformer failures so far in 26 years • Reports not available for transformer repairs • No gassing during factory load run assumed to be 12 hours • No appreciable gas increase during 2 day Field load run. • Appreciable gassing within two months of in-service

  4. Case A– Gassing Results • Duval’s Triangle – about 700 oC • No Furans one test only

  5. Case A – Field Load Run Tests – Two Days • Hydrogen 117 ---- 133 • Methane 273-----259 • Ethane 95------99 • Ethylene 305----311 • Acetylene 3--------3 • CO 438---- 419 • CO2 1671----1689 • TDCG 1231----1224

  6. Case B – Single Phase Transformers with a Wye and Delta Secondary winding • All transformers in one HVDC system gassing • One unit has acetylene and is being repaired • Similar HVDC scheme all transformers not gassing • Same supplier for both. • Non gassing transformers produced 11 years earlier • Remaining units are acceptable ????

  7. Case B – Gassing Results – Two worst units excluding unit with Acetylene • Unit 1 Unit 2 Condition/Risk • Methane 800 500 Medium • Ethylene 780 650 High • Acetylene < 5 < 5 Normal • Extreme gassing above 70% loading • Gassing 100 to 1000 times the daily gas volume in IEC 60599 table A3 at high loading

  8. Case C – Gassing and Failures linked to Harmonics • IEEE transactions Volume 19, No 1, pp208-213 dated January 2004, “Thermal problems caused by Harmonic Frequency Leakage Fluxes in 3 Phase 3 winding Converter Transformers” • Magnetic fluxes must be managed • Use CTC cable • Leads arranged to cancel fluxes • Increased distances • Non-magnetic structural framework

  9. Conclusions • Factory Testing cannot ensure a reliable converter transformer? • Design Review a possible solution? • What are critical factors to consider? Winding configuration, lead routing, flux cancellation? • Should warranty consider gassing results? If so at what level?

  10. QUESTIONS & ANSWERS

More Related