1 / 24

CFS Group Report of the 3rd Meeting of the ILC-MAC CFS Position on MAC Comments

CFS Group Report of the 3rd Meeting of the ILC-MAC CFS Position on MAC Comments. J-L Baldy DRAFT. Page 3 The Project does not contain Preconstruction Costs (as Regards CFS Activities) : Not Obvious which costs excluded from Estimates. 1. Page 4 Costs Risk Analysis for CFS Activities.

ownah
Télécharger la présentation

CFS Group Report of the 3rd Meeting of the ILC-MAC CFS Position on MAC Comments

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CFS GroupReport of the 3rd Meeting of the ILC-MACCFS Position on MAC Comments J-L Baldy DRAFT GDE Meeting, Beijing, 4-7 February 2007

  2. Page 3 The Project does not contain Preconstruction Costs (as Regards CFS Activities) : Not Obvious which costs excluded from Estimates 1 Page 4 Costs Risk Analysis for CFS Activities 2 Page 5 Optimization of Overall Heat Dissipation Confirmation / Clarification on Air Conditioning System Cost 3 Page 6/1 No Attempts Reported to Investigate ILC Costs assuming a Shallow Site 4 Page 6/2 Lists of Buildings : Two Lists needed, One for Needed Buildings on a Stand Alone Site, One for Sites close to Existing HEP Laboratories 5 Page 8 Combination of Service Access Shaft and Neighboring Detector Installation ? Reasons for the Necessity of an Access Shaft over the Service Cavern for BDS Area. Page 7 The Committee suggests reassessing the Specified Emergency Power Value since it appears quite Low. Page 7 Give the Cost and Benefits for an Insulated Water Return Pipe. Give Consequences for Rising the Delta For Water Temperature (of more than the present 10°C). 8 9 7 Page 6/3 Shaft Diameter depending on Details of the Cavity Module Cryostat Design Overall Savings for reducing the 14 m Shafts to 9 m Diameter. 6 GDE Meeting, Beijing, 4-7 February 2007

  3. 1 • Page 3 • The Project does not contain Preconstruction • Costs (as Regards CFS Activities) : • Not Obvious which costs excluded • from Estimates GDE Meeting, Beijing, 4-7 February 2007

  4. CFS Preconstruction Costs • Civil Engineering – Basis of Costing Exercise (4) • Not Included in Cost Estimates : • All R&D (before T0) : Survey and Alignment for CFS only) • Geotechnical Investigations (before T0) : 0.3% of • Civil Engineering Costs • Purchase of Land (Surface, and Underground if needed) • Cost of Local Formalities (Impact Study, …) • Consultants, Architects, Experts fees before T0 : all design and Specifications up to Tender Stage, 3.5% of Civil Engineering Cost GDE Meeting, Beijing, 4-7 February 2007

  5. RDR/Reviews Bid to Host Specs Preparation of Bids to Host Site Selection Process EDR (All CFS) Selection of Main Consultants Site Investigations CE + other CFS Works Machine Supply, Install, Assembly TENTATIVE OVERALL TIME SCHEDULE T0 = 2012 2007 2018 -5 -4 -3 -1 +1 +2 +3 +4 +5 +6 +7 -2 DRAFT Site Independent Eng. Studies (All CFS) Call for Tender Preparation (CE Works + early Services) Call for Tender Procedure (CE Works + early Services) Contract(s) Placing (CE Works + early Services) Administrative Procedures + Site Preparation Utilities Commissioning GDE Meeting, Beijing, 4-7 February 2007 R&D

  6. 2 • Page 4 • Costs Risk Analysis for CFS Activities GDE Meeting, Beijing, 4-7 February 2007

  7. 3 • Page 5 • Optimization of Overall Heat Dissipation • Confirmation / Clarification on Air Conditioning • System Cost GDE Meeting, Beijing, 4-7 February 2007

  8. 4 • Page 6/1 • No Attempts Reported to Investigate • ILC Costs assuming a Shallow Site GDE Meeting, Beijing, 4-7 February 2007

  9. European Sites “For Reference” • DESY Site • Shallow Site (-10 m to -20 m) in Sedimentary Sand 70% and Marl (30%) in Water Table • Tunnel Excavation by Hydro or Earth Pressure Balanced TBMs, other Works from Surface • Design and Costing Carried Out to the Same Level of Detail as for the CERN Site, with the Same Consultant • Same Layouts adapted to Specificities of Site • Cost by Compare to CERN Site : • Total CFS : +13 % • Civil Engineering : + 20% • (1) Official Confirmation “for Reference” Not Received GDE Meeting, Beijing, 4-7 February 2007

  10. European Sites “For Reference” • DUBNA Site • Shallow Site (- 20 m average) in drift Clay under Superficial Layer of Alluvial Deposits • Tunnel Excavation by Shield TBMs, other Works from Surface • Cost Estimates Based on Valencia Layouts (Last Information Received by End November Possibly Not Taken into Account) • Cost by compare to CERN Site : • Total CFS : +9% • Civil Engineering : -13% (Underground -29%) • Electrical Engineering : +43% • Process Cooling Water : +58% • (2) According to Last Information Provided by G. Shirkov 11-12-06 GDE Meeting, Beijing, 4-7 February 2007

  11. GDE Meeting, Beijing, 4-7 February 2007

  12. Distribution of CE Costs (One IR Alternative) Europe CERN Site Europe DESY Site Americas CERN Site Asian Site GDE Meeting, Beijing, 4-7 February 2007

  13. GDE Meeting, Beijing, 4-7 February 2007

  14. 5 • Page 6/2 • Lists of Buildings : Two Lists needed, One • for Needed Buildings on a Stand Alone Site, • One for Sites close to Existing HEP • Laboratories GDE Meeting, Beijing, 4-7 February 2007

  15. GDE Meeting, Beijing, 4-7 February 2007

  16. 6 • Page 6/3 • Shaft Diameter depending on Details of the • Cavity Module Cryostat Design • Overall Savings for reducing the • 14 m Shafts to 9 m Diameter. GDE Meeting, Beijing, 4-7 February 2007

  17. SHAFTS Diameter Reduction from 14 m to 9 m • (Shafts 2, 3, 4, 5, 10, 11) • EUROPE : • ∆ Cost : 100’523 – 49’818 = 50’705 USD/m • Average depth : 100 m • Savings : 50’705 x 6 x 100 = 30.4 MUSD • + 10% uncertainties on moraines = - 33.5 MUSD • AMERICAS : • ∆ Cost : 134’768 – 78’280 = 56’488 USD/m • Average depth : 135 m • Savings : 56’488 x 6 x 135 = -45.8 MUSD • ASIA : Not Applicable (Slopped Access Galleries) • Additional Costs on Reinforcement of Modules Structures to • be assessed by RF GDE Meeting, Beijing, 4-7 February 2007

  18. 7 • Page 7 • Give the Cost and Benefits for an Insulated • Water Return Pipe. • Give Consequences for Rising the Delta • For Water Temperature • (of more than the present 10°C) GDE Meeting, Beijing, 4-7 February 2007

  19. 8 • Page 7 • The Committee suggests reassessing the Specified Emergency Power Value since it appears quite Low. GDE Meeting, Beijing, 4-7 February 2007

  20. Emergency Power Value (1) • What should be taken for emergency power needs further consideration • and clear decision at EDR stage • At present stage, we guestimated that following items should be considered: • - Emergency ventilation • - Emergency ligthing • - Emergency drainage pumps • - Alarms and signalling systems • - Access control systems • - lifts GDE Meeting, Beijing, 4-7 February 2007

  21. Emergency Power Value (2) • Steady state consumption is 1.4 MW • Emergency supply system as designed and costed allows for 5 to 10 MW • Inrush current for users requires a factor of 2 to 3 • We suggest to state 3.8 MW in EMER column of power table • hence an overall total of 229.7 MW • However main cost driver is distance rather than power GDE Meeting, Beijing, 4-7 February 2007

  22. 9 • Page 8 • Combination of Service Access Shaft and Neighboring Detector Installation ? • Reasons for the Necessity of an Access • Shaft over the Service Cavern for BDS Area. GDE Meeting, Beijing, 4-7 February 2007

  23. Reasons for Necessity of an Access Shaft to the Service Cavern of the BDS Area System • Easy and Direct Access to all Equipment/Components • in Service cavern • Safety Access Required to such a Large cavern • Possibility to Access the Service cavern at all Times • (Shielding not Required) • Specific Crane and Lift in the Service Shaft : no need • for time sharing with one of the Detectors (nearest one) • Direct Access to the BDS Service Tunnel : easier transport • of BDS equipment from the surface • Easier Access to Survey Galleries for Alignment of Machine/Detectors Components • Access to Detectors hall in case of Failure of Lowering Equipment • in the 16 m Diameter Shafts over the Detector Hall • CE Cost : Europe ~ 5.5 MUSD • Americas ~ 10.6 MUSD • Asia ~ 13.7 MUSD GDE Meeting, Beijing, 4-7 February 2007

  24. GDE Meeting, Beijing, 4-7 February 2007

More Related