The Fiber Optic Data Network Project for the Tuscaloosa County School System, initiated in 2006, aims to significantly improve data communications and Internet access among schools and the Board of Education. This ambitious project boasts a 40,000% increase in average communications speed (from 256 Kbps to 100 Mbps) and a 650% boost in Internet speed (from 6 Mbps to 45 Mbps). The project involves multiple phases for the installation of fiber optic infrastructure, equipment upgrades, and rigorous testing to ensure efficient operation for enhanced educational experiences.

1 / 10

Télécharger la présentation

Fiber Optic Data Network Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript

Playing audio...

  1. Fiber OpticData Network Project Tuscaloosa County School System 2006

  2. Project to Improve Data Communications and Internet Access • 40,000% increase in average communications speed between the schools and BOE (avg: 256KBPS to 100MBPS) • 650% increase in Internet speed (6MBPS to 45MBPS) • Dedicated data only service connection (Not shared with voice traffic).

  3. Project Timeline

  4. Project Timeline

  5. Phase IWhat to expect • TCSS contractor will install entrance conduits for Bellsouth access of the fiber optic cable. • Equipment Racks will be installed where needed to house equipment. • Some schools will be retrofitted with new equipment locations and/or have extensions of new service routed to existing LAN equipment.

  6. Example of Equipment Racks Wall Mount Rack Floor Mount Rack

  7. Phase IIWhat to expect • TCSS Maintenance department will upgrade electrical and grounding to new network equipment D-Marc points as necessary. • TCSS IT Dept. will install and terminate district supplied fiber optic cable to all schools that require D-Marc extensions. • TCSS IT Dept will install or upgrade existing LAN equipment and switches to handle fiber optic handoff from Bellsouth.

  8. Example of D-Marc Extension

  9. Phase IIIWhat to expect • Bellsouth contractor will trench or run aerial fiber optic cable to the school. • Bellsouth contractor will route fiber optic cable through the entrance conduits previously installed by TCSS contractor. • Bellsouth cable specialist will terminate fiber optic cable. • Bellsouth equipment engineers will install fiber control equipment and Cisco routers.

  10. Phase IV • Bellsouth engineers and TCSS IT staff will work to configure equipment to route traffic across the fiber network. • Testing phase will run for 24-hours and switch over will take place following successful test of all equipment. • Removal of old WAN connection equipment and routers. • School will now be fully operational on the new Fiber Optic Wide Area Network.