1 / 16

F-18 IETM Development and Implementation Lessons Learned

F-18 IETM Development and Implementation Lessons Learned. Presented By Denny Raitz February 10 2004. Lessons Learned. Lessons Learned Customer Contractor IETMs Cost IETM Conversion Cost Example IETMs Savings Data Development And Sustainment Cost Savings Data Reuse

palmer-hale
Télécharger la présentation

F-18 IETM Development and Implementation Lessons Learned

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. F-18 IETM Development and ImplementationLessons Learned Presented By Denny Raitz February 10 2004

  2. Lessons Learned • Lessons Learned • Customer • Contractor • IETMs Cost • IETM Conversion Cost Example • IETMs Savings • Data Development And Sustainment Cost Savings • Data Reuse • Savings Realized in the Field

  3. Lessons Learned - Customer • Develop a Business Case to Justify IETM • Include Life Cycle Cost Analysis • Benefits Analysis • Determine Funding Source • Standard Tech Data Funding • Procurement • Sustainment • Consider Aging Aircraft Initiatives • Document Requirements • Functionality Matrix • CONOPS

  4. Lessons Learned - Customer • Create/Accept Estimating Methodology • Can Be Paper Based IF Conversion • Task-based If New Program • Get End-User Involved Early • In-Process Reviews • Functionality Requirements • Verification • Display Hardware Procurement • Identify Quantity And Replenishment Strategy • Identify Identify Funding

  5. Lessons Learned - Customer • Availability & Capability of Needed IT Infrastructure • Interface With Diagnostics Or Weapon System? • Interface With Maintenance Management System? • Training • End User • Training Organization • Verification • Fund And Staff It • Provide Resources (Equipment) • Schedule It

  6. Lessons Learned - Contractor • Planning • Schedule It • Experience Has Shown 1 Man Year Minimum (2 Persons – 6 Months) • Fund It • Funding The Planning Will Recoup Huge Benefits Later • Staff It • Part Timers Not Wanted!

  7. Lessons Learned - Contractor • Create/Accept Estimating Methodology • Can Be Paper Based IF Conversion • Task-based If New Program • Training • Technical Writers And Illustrators • Management • Engineering • Manufacturing • Training Organization

  8. Lessons Learned - Contractor • Create Process Documentation • Work Flow • Metrics • Style and Format Documentation • Style Guide Prevents “Innovative” Authoring • Data Validation Software Assists In Enforcement Of Style • Develop Versioning Techniques Early • Assists In “Backing Out” Errors • Configuration Management

  9. Lessons Learned - Contractor • Identify Utilities • Importing Software • LSA Data • Engineering Data • Metric Reporting • Non-IETM data access • PDF Files • Wiring And Schematic Viewers • Engineering Documents • Etc.

  10. IETMs Cost Too Much – Not! • “New” Weapon Systems Initial Development No More Than Developing Paper • Costs Less If Data Development And Database Population “Managed” Properly • Benefits Are In The “Out Years” Of The Life Cycle • Conversion Does Bring A Non-Recurring Cost • Business Case Should Determine Go-Ahead • Life Cycle Cost Analysis Should Identify ROI

  11. (C-130 Conversion) ROI FY 2009 (5 years out)

  12. Good Data Development Cost Savings 7 % Reduction in Initial Publication Development due to Class 4 IETM Authoring For all Organizational Level Maintenance Tasks Initial Publication Authoring Costs 1.00 0.93

  13. 1.00 0.64 Good F/A-18 E/F F/A-18 C/D Data Sustainment Cost Savings 36% Reduction in Sustainment Authoring Costs of Publications due to Class 4 IETM Authoring (Average costs over 3 years after initial release) Sustaining Publication Costs

  14. Data Reuse Total Elements 11,853 Graphics 1057 Consumables 666 Support Equip. 3226 Common Steps 85,523 Parts 21,422 Tasks

  15. 1.00 0.78 Good F/A-18 C/D F/A-18 E/F Savings Realized in the Field 22 % Reduction in Maintenance Manhours Due to Class 4 IETM and Automated Maintenance Environment Maintenance Manhours

  16. Questions?

More Related