This report details the progress of the Bang Pa-In Industrial Estate Rehabilitation Project as of July 22, 2012. Soil compaction has reached 100%, achieving both progress and schedule targets. Overall project work is 67.90% complete, with a schedule completion rate of 61.20%. The construction of the R.C. flood wall is at 41.93% progress and 34.29% scheduled. Key activities include pouring concrete for retaining walls and slope protection in designated areas, as evidenced by photographs showcasing the ongoing work.
E N D
The Industrial Estate Authority of Thailand Bang-Pa-In Land Development Co.,Ltd. CH.Karnchang Public Company Limited โครงการฟื้นฟู นิคมอุตสาหกรรมบางปะอิน Report Date : 22July 2012
soil compaction Work progress Main Entrance • soil compaction Work progress = 100.00% • soil compaction Schedule = 100.00% • OVERALL PROJECT Work progress = 67.90% • OVERALL PROJECT Schedule= 61.20% Picture 1 Update 22 July2012 Progress of work 100% Remark
R.C.FLOOD WALL Work progress Main Entrance • R.C.FLOOD WALL Work progress = 41.93% • R.C.FLOOD WALL Schedule = 34.29% • OVERALL PROJECT Work progress = 67.90% • OVERALL PROJECT Schedule = 61.20% Picture 2,3 Update 22 July2012 Key Slab Wall
Pic 1 : Pouring Concrete Retaining Wall at Connection Between Dike Sta. 2+875
Pic 2: Pouring Concrete Slab and Wall of R.C. Flood Wall Sta. 4+000 to 4+500
Pic 3: Pouring Concrete Slope Protection Sta. 4+000 to 4+500