An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bored Pile Procedure

  2. Content Bored Pile Procedure : 1. Set up the Location of Bored Pile 2. Insert Casing 3. Drilling 4. Removing Slime 5. KODEN-Test 6. Insert of Steel Cage 7. Insert Tremie Pipe 8. Pouring the Concrete 9. Removing Casing Cycle Time of a Bored Pile

  3. Bored Pile Procedure 1. Set up the location of Bored Pile

  4. Bored Pile Procedure We use Total Station instrument to survey each pile point.

  5. 2. Insert casing  casing must be stand vertical ( by checking verticality of casing when insert casing ) Bored Pile Procedure

  6. Bored Pile Procedure  use Vibrodriver or Vibrohamer to insert casing

  7. Bored Pile Procedure 3. Drilling  Drilling Machine : weight : 130tons BG - 40 drilling depth : 49m diameter : 3m weight : 96tons BG - 28 drilling depth : 39m diameter : 2.5m weight : 91tons SD - 515 drilling depth : 36m diameter : 2.5m BG - 40 BG - 28 SD - 515

  8. Bored Pile Procedure 4. Removing slime when finish drilling , we use Mechanical pump equipment to remove slime .

  9. Bored Pile Procedure 5. KODEN Test KODEN test utilizes the principle of ultrasonic wave travel from sensor to the wall of drilled hole and reflect to the sensor through the bentonite slurry.  Equipment KODEN equipment consists of two parts, recorder unit and winch unit . Recorder Unit Winch Unit

  10. Bored Pile Procedure Recorder unit controls the operation and record the test result. On the other hand, winch unit lowers the probe (sensor) down the hole for ultrasonic reflection .  Testing Procedure 1. Remove any obstacle around the hole area in order that the test equipment can access to the hole . 2. Place the winch unit over the top of drilled hole or on the steel casing. Position the sensor (probe) at the center of the hole . 3. Lower the sensor into bentonite slurry. Hold the sensor at depth approximately 1 to 1.5m . 4. Restore the sensor to the starting position and perform the test.

  11. Bored Pile Procedure  Test Result Test results are presented in graphical plot and show characteristics below : 1. Profile along two perpendicular axes. 2. Average verticality of the hole. 3. Location or depth where abnormality Occurs such as reduction in diameter, or collapsed wall of the hole. 4. Depth of drilled hole.

  12. Bored Pile Procedure 6. Insert of steel cage

  13. Bored Pile Procedure 7. Insert Tremie

  14. Bored Pile Procedure Type of tremie pipe : we have 3 types of tremie : 1m, 2m and 3m Length 1m Length 2m Length 3m Length

  15. Bored Pile Procedure How to insert tremie pipe : Use mobile crane to hang the hopper Then connect each tremie pipe After that put it into the bored pile hole until bottom When we pour concrete, we have to bury the tremie pipe into concrete as below :

  16. Bored Pile Procedure 8. Pouring the concrete Quality of Concrete :  Max. size of Aggregate : 2.5cm  Workability : 55cm ( Flow )

  17. Bored Pile Procedure  Strength of concrete : ► Design strength : fck =300kg/cm² ( 28day’s cure concrete ) ► Strength of mix ( Target Strength ) : according to the Standard Specifications of Concrete ( Korea Concrete Institute ) Strength of mix ( Target Strength ) So, for Actual Concrete Strength : 400kg/cm²

  18. Bored Pile Procedure 9. Remove casing

  19. Cycle Time of a Bored Pile