Bored Pile Procedure. Content. Bored Pile Procedure : 1. Set up the Location of Bored Pile 2. Insert Casing 3. Drilling 4. Removing Slime 5. KODEN-Test 6. Insert of Steel Cage 7. Insert Tremie Pipe 8. Pouring the Concrete 9. Removing Casing Cycle Time of a Bored Pile.
E N D
Content Bored Pile Procedure : 1. Set up the Location of Bored Pile 2. Insert Casing 3. Drilling 4. Removing Slime 5. KODEN-Test 6. Insert of Steel Cage 7. Insert Tremie Pipe 8. Pouring the Concrete 9. Removing Casing Cycle Time of a Bored Pile
Bored Pile Procedure 1. Set up the location of Bored Pile
Bored Pile Procedure We use Total Station instrument to survey each pile point.
2. Insert casing casing must be stand vertical ( by checking verticality of casing when insert casing ) Bored Pile Procedure
Bored Pile Procedure use Vibrodriver or Vibrohamer to insert casing
Bored Pile Procedure 3. Drilling Drilling Machine : weight : 130tons BG - 40 drilling depth : 49m diameter : 3m weight : 96tons BG - 28 drilling depth : 39m diameter : 2.5m weight : 91tons SD - 515 drilling depth : 36m diameter : 2.5m BG - 40 BG - 28 SD - 515
Bored Pile Procedure 4. Removing slime when finish drilling , we use Mechanical pump equipment to remove slime .
Bored Pile Procedure 5. KODEN Test KODEN test utilizes the principle of ultrasonic wave travel from sensor to the wall of drilled hole and reflect to the sensor through the bentonite slurry. Equipment KODEN equipment consists of two parts, recorder unit and winch unit . Recorder Unit Winch Unit
Bored Pile Procedure Recorder unit controls the operation and record the test result. On the other hand, winch unit lowers the probe (sensor) down the hole for ultrasonic reflection . Testing Procedure 1. Remove any obstacle around the hole area in order that the test equipment can access to the hole . 2. Place the winch unit over the top of drilled hole or on the steel casing. Position the sensor (probe) at the center of the hole . 3. Lower the sensor into bentonite slurry. Hold the sensor at depth approximately 1 to 1.5m . 4. Restore the sensor to the starting position and perform the test.
Bored Pile Procedure Test Result Test results are presented in graphical plot and show characteristics below : 1. Profile along two perpendicular axes. 2. Average verticality of the hole. 3. Location or depth where abnormality Occurs such as reduction in diameter, or collapsed wall of the hole. 4. Depth of drilled hole.
Bored Pile Procedure 6. Insert of steel cage
Bored Pile Procedure 7. Insert Tremie
Bored Pile Procedure Type of tremie pipe : we have 3 types of tremie : 1m, 2m and 3m Length 1m Length 2m Length 3m Length
Bored Pile Procedure How to insert tremie pipe : Use mobile crane to hang the hopper Then connect each tremie pipe After that put it into the bored pile hole until bottom When we pour concrete, we have to bury the tremie pipe into concrete as below :
Bored Pile Procedure 8. Pouring the concrete Quality of Concrete : Max. size of Aggregate : 2.5cm Workability : 55cm ( Flow )
Bored Pile Procedure Strength of concrete : ► Design strength : fck =300kg/cm² ( 28day’s cure concrete ) ► Strength of mix ( Target Strength ) : according to the Standard Specifications of Concrete ( Korea Concrete Institute ) Strength of mix ( Target Strength ) So, for Actual Concrete Strength : 400kg/cm²
Bored Pile Procedure 9. Remove casing