110 likes | 351 Vues
OPERATIONAL PERFORMANCE MAY’13. Tonnage - MT. COMMODITY-WISE LOADING – FOR THE MONTH OF MAY’13. Tonnage in Lakhs. COMMODITY-WISE REVENUE – FOR THE MONTH OF MAY’13. ` - Crores. Commodity wise Net Revenue Including OH. ` - Crores.
E N D
OPERATIONAL PERFORMANCE MAY’13 Tonnage - MT
COMMODITY-WISE LOADING – FOR THE MONTH OF MAY’13 Tonnage in Lakhs
Commodity wise Net Revenue Including OH ` - Crores • May’13 -Net Revenue Includes Def OH of ` 110 Lakhs ,O&M Cost Inclusive of Def OH- ` 173/T • May’12 –Net Revenue Includes Def OH of ` 90 Lakhs,O&M Cost Inclusive of Def OH- ` 179/T
Commodity wise Gross & Net Revenue Including OH (Per Tonne) Amt - ` • May’13 - Net Revenue Includes Def OH of ` 24/T , O&M Cost Inclusive of Def OH - ` 173/T • May’12 – Net Revenue Includes Def OH of ` 26/T, O&M Cost Inclusive of Def OH - ` 179/T
Operating Ratio for the month of May 2013 ` - Crores NOTE : In O&M costs, cost of fuel is calculated as per service & direction wise
COST OF FUEL (SERVICE WISE/ DIRECTION WISE) for May’13 Cost of Fuel From April ’13 – May’13 – 7.90 Cr
Line Capacity Utilization for the month of May’13 : Permissible Capacity : 340 Utilized : 306 Percentage of Utilization : 90% Percentage of Utilization Loaded : 46% Engine Hour Cost : 84.36 Lakhs NOTE: * Moved between SKLR-SBHR-SKLR
WAGON DAYS – MAY 2013 Rate per Day in terms of 8 wheeler : ` 1038.30 Wagon Hire Charges (Actual) : ` 71.01 Lakhs Wagon Hire Charges for Abnormal : ` 9.56 Lakhs Detention (Avoidable) *Abnormal Detention : Time taken for completing the journey > 15 Hrs
Details of Payments Received from Mysore Division after adjusting O&M Costs