1 / 4

St. Louis District Westport RRAT

St. Louis District Westport RRAT. FY 14 Workload O&M – Westport RM 257 - 253. Address a repetitive dredge location – We have dredged over 1.8M cy since 2007 at a cost of $4.4M. Design includes the construction of 8 weirs, 2 dike extensions, 1 trail dike, and 1 SCED.

Télécharger la présentation

St. Louis District Westport RRAT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. St. Louis District Westport RRAT

  2. FY 14 Workload O&M – Westport RM 257 - 253 • Address a repetitive dredge location – We have dredged over 1.8M cy since 2007 at a cost of $4.4M. • Design includes the construction of 8 weirs, 2 dike extensions, 1 trail dike, and 1 SCED. • The total project cost is estimated at $5.2M. • The GP was approved at E-Action in 2013. • Phased construction with funding taken incrementally from the Upper D&R budget. • $700k was used for the upper most weirs in 2014

  3. FY 14 Workload O&M – Westport RM 257 - 253 5 Weirs at RM 258 SCED at RM 255 and 3 Weirs near RM 254 2 Dike Extensions and Trail Dike near RM 257

  4. Rock Quantities and Cost Estimate

More Related