1 / 3

Activities of TOF assembly@CERN(Dec-Jan. 2008)

Activities of TOF assembly@CERN(Dec-Jan. 2008). SM13: Completed LV cables installation HV cables & HV boxes test VME 4 crates test & installation FEA cards & record ID Amphenol cables done (both) FEAC cards & cables installation Gluing done for both sides Pulser test : done

portia
Télécharger la présentation

Activities of TOF assembly@CERN(Dec-Jan. 2008)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Activities of TOFassembly@CERN(Dec-Jan. 2008) • SM13: Completed • LV cables installation • HV cables & HV boxes test • VME 4 crates test & installation • FEA cards & record ID • Amphenol cables done (both) • FEAC cards & cables installation • Gluing done for both sides • Pulser test : done • Closed & moved to storage area

  2. Activities of TOFassembly@CERN(Dec.-Jan 2008) • SM14 : 50 % done • Cooling pipe • Aluminum frame done • VME 2 crates tested & installed (baby) • Put mylar to protect interface cards • gas leak test • FEA cards & recode ID • Baby : amphenol cable done • SM15 : 5 modules lined up on the frame SM15 SM14

  3. Summary & Milestone • Summary (1 post doc. & 2 students) • Cabling : FEA, FEAC cards & Amphenol cables for SM13 & SM14 • Test & cabling : LV cables, HV cables, control cables • TRMs, CPDM, LTM, DRM & crate test ,etc….. • SM13 : 100 % Completed • SM14 : 50 % Completed • SM15 : just lined up on the assembly frame • 3 SMs installed@pit : sectors 9,10 & 16 • Guide a student in the “Study of Λc →pKπ analysis” for PWG3 meeting • Total : 10 SMs installed@pit + 4 SMs waiting for next installation • Milestone • Assembly@CERN : 4 SMs to be done • Installation period : • next period : Mar. 2008 (8 SMs)

More Related