An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NPV and other Investment Criteria Capital Budgeting Decisions Financial management: lecture 6

  2. Today’s agenda • Net Present Value (revisit) • Other two investment rules Financial management: lecture 6

  3. Net Present Value rule (NPV) • NPV is the present value of a project minus its cost • If NPV is greater than zero, the firm should go ahead to invest; otherwise forget about this project • A hidden assumption: there is no budget constraint or money constraint. Financial management: lecture 6

  4. NPV (continue) In other words: Managers can increase shareholders’ wealth by accepting all projects that are worth more than they cost. Therefore, they should accept all projects with a positive net present value if there is no budget constraint. Financial management: lecture 6

  5. Net Present Value NPV = PV - required investment Financial management: lecture 6

  6. An Example • An oil well, if explored, can now produce 100,000 barrels per year. The well will produce forever, but production will decline by 4% per year. Oil prices, however, will increase by 2% per year. The discount rate is 8%. Suppose that the price of oil now is $14 for barrel. • If the cost of oil exploration is $12.8 million, do you want to take this project? Financial management: lecture 6

  7. Solution • Visualize the cash flow patterns • C0=1.4, C1=1.37, C2=1.34, C3=1.31 • What is the pattern of the cash flow? • g=C1/C0 -1 =-0.0208=-2.1% • PV( the project) =C0+C1/(r-g)=15 • NPV=PV( the project ) -12.8>0 • What’s your decision? Financial management: lecture 6

  8. Two other investment rules • IRR rule • Payback period rule Financial management: lecture 6

  9. IRR rule Internal Rate of Return (IRR) – Single discount rate at which NPV = 0. IRR rule - Invest in any project offering a IRR that is higher than the opportunity cost of capital or the discount rate. Financial management: lecture 6

  10. IRR rule Example You can purchase a building for $350,000. The investment will generate $16,000 in cash flows (i.e. rent) during the first three years. At the end of three years you will sell the building for $450,000. What is the IRR on this investment? Financial management: lecture 6

  11. Internal Rate of Return Example You can purchase a building for $350,000. The investment will generate $16,000 in cash flows (i.e. rent) during the first three years. At the end of three years you will sell the building for $450,000. What is the IRR on this investment? Financial management: lecture 6

  12. Internal Rate of Return Example You can purchase a building for $350,000. The investment will generate $16,000 in cash flows (i.e. rent) during the first three years. At the end of three years you will sell the building for $450,000. What is the IRR on this investment? IRR = 12.96% Financial management: lecture 6

  13. Internal Rate of Return IRR=12.96% Financial management: lecture 6

  14. What’s wrong with IRR? Pitfall 1 - Mutually Exclusive Projects • IRR sometimes ignores the magnitude of the project. • The following two projects illustrate that problem. Example You have two proposals to choose between. The initial proposal (H) has a cash flow that is different from the revised proposal (I). Using IRR, which do you prefer? Financial management: lecture 6

  15. Internal Rate of Return (1) Example You have two proposals to choose between. The initial proposal (H) has a cash flow that is different from the revised proposal (I). Using IRR, which do you prefer? Financial management: lecture 6

  16. Internal Rate of Return Financial management: lecture 6

  17. What’s wrong with IRR (2)? Pitfall 2 - Lending or Borrowing? Example project C0 C1 IRR (%) NPV at 10% +150 +50 +$36.4 -100 J K -150 +50 -$36.4 +100 Financial management: lecture 6

  18. What’s wrong with IRR (3)? Pitfall 3 - Multiple Rates of Return • Certain cash flows can generate NPV=0 at two different discount rates. • The following cash flow generates NPV=0 at both (-50%) and 15.2%. • Example • A project costs $1000 and produces a cash flow of $800 in year 1, a cash flow of $150 every year from year 2 to year 5, and a cash flow of -150 in year 6. Financial management: lecture 6

  19. Payback period rule • Payback period is the number of periods such that cash flows recover the initial investment of the project. • The payback rule specifies that a project be accepted if its payback period is less than the specified cutoff period. The following example will demonstrate the absurdity of this rule. Financial management: lecture 6

  20. Payback period rule The following example shows that all the three projects have a payback period of 2. If the payback period used by the firm is 2, the firm can take project C and lose money. Cash Flows Prj.C0C1C2C3Payback NPV@10% A -2000 +1000 +1000 +10000 2 7,429 B -2000 +1000 +1000 0 2 -264 C -2000 0 +2000 0 2 - 347 Financial management: lecture 6