40 CFR 1500-1508

40 CFR 1500-1508. REGULATIONS FOR IMPLEMENTING PROCEDURAL PROVISIONS OF NEPA Legislative vs. Discretionary Timelines - Agency Requirements for Implementing Project Level EAs and EISs June 11, 2008.

prudence
Télécharger la présentation

40 CFR 1500-1508

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 40 CFR 1500-1508 REGULATIONS FOR IMPLEMENTING PROCEDURAL PROVISIONS OF NEPA Legislative vs. Discretionary Timelines -Agency Requirements for Implementing Project Level EAs and EISs June 11, 2008

  2. Our discussion focuses on key tasks that have the most salient impact on the timingof O&G project EAs and EISs. Buys & Associates, Inc.

  3. Decision to Prepare an EA or EIS?(Sections 1501.3 and 1501.4) Task-Level Time Frames Buys & Associates, Inc.

  4. An EIS is prepared when: 1) The action normally requires an EIS; or 2) When the agency knows there will be significant impacts. For other situations, an EA is usually prepared. EISs are more involved than EAs, and have more task-specific, non-discretionary, and lengthy timeframes. Buys & Associates, Inc.

  5. Key Tasks for EISs: • Proposed Action • Internal Scoping • Draft Notice of Intent (NOI) Review • Public Scoping • Preparation of Preliminary Draft EIS (PDEIS) • Internal review of PDEIS • Notice of Availability (NOA) & Draft EIS (DEIS) Internal Review • DEIS Public Comment Period • Responses to Comments (RTCs) & Preparation of Preliminary Final EIS (PFEIS) • NOA, Final (FEIS) and Draft ROD Review • FEIS Availability • ROD Appeal Period Buys & Associates, Inc.

  6. Proposed Action Prior to public scoping the operator must have a Proposed Action to present to the public. This task, although technically outside the formal EIS process, can take a substantial amount of time. Timing is operator-specific: • How long will it take you to prepare a complete Proposed Action? • Do you know what the agency wants/needs to see in the Proposed Action? • Do you have a feel for the key issues of the project area; things that you may need to consider within the operational aspects of your Proposed Action? • Is the agency expecting you – are they planning for an EIS? All of the above boil down to pre-planning; start your pre-planning 6 to 18 months before you want the formal EIS process to begin. Buys & Associates, Inc.

  7. Internal Scoping • Once your Proposed Action is received by the agency, there is usually some level of internal scoping that is conducted in conjunction with the lead agency prior to the formal public scoping period. • During this general timeframe, the lead agency prepares the Notice of Intent (NOI). Internal scoping can take 2 – 6 months before agency is ready to officially scope the project to the public. Timing depends on the completeness of your Proposed Action, sensitivity of the project area, scope of the project, and budget and staffing availability. Buys & Associates, Inc.

  8. Draft NOI Review • Prior to publication in the Federal Register, the draft NOI is reviewed by (as appropriate) upper agency management (e.g., USFS Solicitor Office, BIA Regional Office, or BLM State and Washington Offices): • Although CEQ provides no guidance on time frames for NOI review, plan for at least30-90 days • Acceleration of this time frame often requires pressure by the lead agency and operator Recent Wyoming and Utah NOIs: Sat in the Washington Office of the BLM for over 6 months before being approved for publication Buys & Associates, Inc.

  9. Formal Public Scoping (1501.4 and 1501.7) • CLOCK STARTS when the EPA publishes the NOI (1501.7) in their Federal Register: • Although CEQ provides no guidance on required time frames, public scoping takes no less than 45 days • Lead agency has discretion to extend the scoping period Buys & Associates, Inc.

  10. Preparation of PDEIS Realistic estimate = 9 months to 2 years depending on: 1) The scope of the Proposed Action, 2) Degree to which the action is controversial, 3) Scope of the EIS (e.g., # of alternatives, depth of analysis), and 4) Degree to which relevant baseline information is available (i.e., is field work needed first ?), Buys & Associates, Inc.

  11. Preparation of PDEISOther factors affecting how long it takes to prepare the PDEIS: Involvement by Cooperating Agencies and Consulting Parties – it’s valuable, but consensus/compromise is difficult and time consuming Changes to the Proposed Action or alternatives – changes have ripple effects Buys & Associates, Inc.

  12. PDEIS Internal Review • i.e., Review of the PDEIS by the lead agency, Cooperating Agencies, and operator • timing is at the lead agency’s discretion, plan for at least 30 days. • At a minimum, the lead agency will review the PDEIS. • Limiting internal review periods becomes more difficult with each agency office, Cooperating Agency or Consulting Party in the mix (more schedules to accommodate) Buys & Associates, Inc.

  13. NOA and DEIS Internal Review • i.e., Review by USFS Solicitor Office, BIA Regional Office, or BLM State and Washington Offices • Although CEQ provides no formal guidance on time frames for NOA review, plan for at least30-90 days • Timeframe can usually be expedited if the Solicitor/Regional/State/Washington Office(s) is involved early in the process • Last minute involvement can result in significant delays (e.g., 2 recent NOAs and DEISs sat in the Washington Office of the BLM for over 6 months, were remanded and had to be revised/re-printed) • For recent EIS where Washington BLM had been involved since scoping, the NOA and DEIS review took about 2 months Buys & Associates, Inc.

  14. NOA and DEIS Internal Review And sometimes, even with early involvement, review by agency upper management can result in major schedule slip. Acceleration of this time frame often requires pressure by the lead agency, operator, and sometimes legal counsel Buys & Associates, Inc.

  15. DEIS Public Review After preparing a DEIS, the agency shall (1503.1): • Obtain comments of any Federal agency with jurisdiction by law or special expertise with respect to any environmental impact involved or which is authorized to develop and enforce environmental standards (e.g., EPA under Clean Air Act). • Request the comments of appropriate State and local agencies…, Indian Tribes…, and any [other] agency which has requested that it receive [DEISs]. • Request comments from the public. Buys & Associates, Inc.

  16. DEIS Public Review • CLOCK STARTS when EPA publishes NOA in their Federal Register • CEQ guidelines (1506.10(d)) require no less than 45 days for DEIS public review but agencies have discretion to add additional time – plan for at least 60 days plus requests for additional time • Minimum 90-day review period if the EIS decision is going amend a land use plan Buys & Associates, Inc.

  17. Responses to Comments & Preparation of PFEIS Realistic range = 3 months to 1 year depending on the volume of comments and whether comments: • modify the alternatives, • lead to consideration of additional alternatives, • modify the impact analysis. Buys & Associates, Inc.

  18. PFEIS Internal Review • i.e., review/edits by lead agency, upper agency management, Cooperating Agencies, and operator: • Although CEQ provides no formal guidance on time frames for NOA review, plan for at least30 days • Reviewers will be looking at how the EIS was revised based on public comments – RTCs generally receive careful scrutiny Buys & Associates, Inc.

  19. NOA, FEIS and Draft ROD Review • i.e., Review by USFS Solicitor Office, BIA Regional Office, or BLM State and Washington Offices: • Although CEQ provides no guidance on time frames for NOA, FEIS, and Draft ROD review - plan for at least 30-90 days. Again, acceleration of this discretionary time frame often requires pressure by the lead agency, operator, and legal counsel Buys & Associates, Inc.

  20. FEIS Availability • CLOCK STARTSwhen the EPA publishes the NOA (1506.6) in their Federal Register: • CEQ guidelines require no less than 30 days • Substantive comments on FEISs do not have to be incorporated into a revised FEIS, but are generally responded to by the agency within the ROD Buys & Associates, Inc.

  21. ROD Appeal Period No less than 30 days for ROD appeal + additional time if there’s a land use plan amendment (40 CFR 1610), which for BLM projects are becoming commonplace given the number of outdated RMPs: • 60-day Governor’s consistency review with State and local plans (is sometimes concurrently with FEIS review), • 30-day protest period afforded to the public (can run concurrently with 30-day ROD appeal period), • discretionary protest resolution period (up to 90 days can be taken to resolve protests on land use plan decisions) Buys & Associates, Inc.

  22. Save appeals and/or litigation, the EIS process is now complete, but what about timing on EAs? Buys & Associates, Inc.

  23. TYPICAL Task Level Timing for EAs isAgency-specific & Project-specific: TasksTime Frames Pre-planning & Internal scoping 2 – 4 months Public Scoping 0 - 30 days Prep. of Internal Draft EA 2 – 4 months Internal Draft EA Review(s) USUALLY 1 - 3 months per review Draft EA Public Review 0 - 30 days RTCs and EA Revisions 2 weeks - 2 months Agency Final Review USUALLY 2 weeks - 2 months Final EA Public Review Usually 0 days Decision Record/Notice 30-day average Appeal Period Buys & Associates, Inc.

  24. Start – Finish? Project Level Time Frames (Section 1501.8) Buys & Associates, Inc.

  25. CEQ says: Large, complex energy project EISs - 12 months start to finish. More realistic - 3 to 5 years CEQ says: EAs – 3 months start to finish. More realistic - 6 months to about 2 years While CEQ has made suggestions on time limits for EAs and EISs, in reality, timeframes are agency-specific, operator-specific, and (especially these days) project scope, project area, and issue-specific. Buys & Associates, Inc.

  26. Keys to keeping the NEPA process running: Operator needs to establish early dialogue with the lead Agency – get on the agency’s schedule; Operator needs to prepare a thorough Proposed Action - avoid 11th hour changes when feasible; Early/Ongoing involvement by upper agency management, Cooperating Agencies, other stakeholders - avoid 11th hour revisions; Know the sticking points of the project and project area and try to preempt holdups; Understand that small details can yield big delays. So, COMMUNICATE - Make sure everyone understands roles, responsibilities, and timelines throughout the process Buys & Associates, Inc.