1 / 23

Current Practice in Buried Structures & Pipelines April 2012

Current Practice in Buried Structures & Pipelines April 2012. Presentation by: Howard Lum, P.E., S.E . Agenda. Design Criteria AASHTO Design Standards Concrete Box Culvert Design Steel Pipe Design Cut-and-cover Construction Tunneling Methods. Design Standards. Loads:

ramya
Télécharger la présentation

Current Practice in Buried Structures & Pipelines April 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Current Practice in Buried Structures & PipelinesApril 2012 Presentation by: Howard Lum, P.E., S.E.

  2. Agenda • Design Criteria • AASHTO Design Standards • Concrete Box Culvert Design • Steel Pipe Design • Cut-and-cover Construction • Tunneling Methods

  3. Design Standards Loads: • California Building Code • Caltrans/AASHTO LRFD Standards Concrete Box Culverts: • ACI 318 & AASHTO LRFD Steel Pipes: • AWWA M11 – Steel Pipe Design Guide Concrete Pipes: • AWWA M9 – Concrete Pressure Pipe

  4. Vehicular Load • HS-20 (20-ton) semi-truck • Axle Load (LL) = 32 kips • Wheel Load = 32k/2 = 16 kips • Max Impact = 30% of LL

  5. Projection of Wheel Loads • Live Load diminishes uniformly below grade • AASHTO equation: LL1 = 4 kips / Z12 (in ksf) LL2 = 16 kips / Z12 (in ksf)

  6. Concrete Box Culvert Design • ACI 318 – LRFD • U = 1.2 (D + F + T) + 1.6 (L + H) where D: Dead; F: Fluid/Water; T: Temperature; L: Live; H: Soil/Ground Water F F

  7. SAP Analysis

  8. AASHTO LRFD Procedures • Determine Mu (moment), Vu (shear) and Pu (axial) based on factored loads • Assume concrete section, As (reinforcement), f’c (concrete compressive strength) & Fy (60 ksi) • Check Flexure: Mn = 0.9 (As*Fy)*(d - a/2) > Mu • Check Shear: Vn = 0.9 (Vc + Vs) > Vu • Check Axial Compression: Pn = 0.7 Pn > Pu

  9. Vehicular Loads (HS-20) • Tire contact area (rectangle): • length in the direction of traffic = 10 inches • width of tire = 20 inches 10” 20” Direction of Traffic

  10. AWWA M-11 Design • Internal Pressure (Hoop Stress) • Min. pipe thickness t = p*D/(2S) • p: internal pressure (psi) • D: outside diameter • S: allowable stress (20,000 psi)

  11. AWWA M-11 Design • External Loads • Wc (dead load) = DH • Check axial stressand deflection • Deflection governs as mortar lining is rigid with low tolerance • Allow. Deflection = 2% of pipe D

  12. Cut-and-cover Pipeline • Open excavation and temporary support prior to pipeline installation • Advantages: • Conventional excavation equipment • Lower cost of construction • Exposed ground conditions • Disadvantages: • Access and Right-of-way issues • Disturbance to neighborhood • Traffic control • Environmental issues

  13. Vertical Ditch Construction

  14. Sloped Excavation 68 feet 25 feet 18 feet

  15. Tunneling Methods • Drill and Blast Tunneling • Micro-tunneling • Tunnel Boring Machine (TBM) • New Austrian Tunneling Method (NATM) or Sequential Excavation Method (SEM)

  16. First Drilling Jumbo in USA Hoover Dam 1931

  17. Drill and Blast Tunneling

  18. Micro-tunneling Micro-Tunneling Micro Tunneling TBM

  19. Microtunneling • Diameter ranges from 18” to 108” (9 ft) • Length - less than 1,500 feet • Straight drives between shafts • Limitations: • Boulders and rocks • Very soft ground • Mixed face conditions • Construction debris or fill • Shaft construction

  20. Tunnel Boring Machine (TBM) • First TBM invented in 1846 for Fréjus Rail Tunnel between France and Italy through the Alps • Adaptable to various ground conditions • Hard Rock vs. Soft Ground TBM • Soft Ground TBM: • Earth Pressure Balance (EBP) – up to 7 bars pressure • Slurry Shield (SS) – high pressure

  21. Arrowhead Tunnel TBM’s

  22. Questions and Answers

More Related