An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PSRC Regional Passenger-Only Ferry Study BACKGROUND AND STATUS REPORT PSRC Executive BoardJanuary 22, 2009

  2. POF-RELATED STUDIES AND PLANS 2005 • King County Waterborne Transit Policy Study 2006 • Joint Transportation Committee Task Force • King County POF Business Plan • Kitsap Transit POF Investment Plan • Ferry Finance Study • WSF Long-Range Plan • PSRC Transportation Policy Board weighs in

  3. PSCR INTEREST IN THE POF ISSUE • State mandate to exit the POF business • Ferries are on MTS (regionally significant) • POF are defined as High Capacity Transit • DESTINATION 2030 does not adequately address POF • Forecast growth vs loss of service • Need for a regional approach • Opportunity to coordinate efforts

  4. RELATED ISSUES • Integrate POF with transit, roads, and non-motorized • Guide ferry-oriented development • Address impacts in ferry terminal communities • Improved technical capabilities (forecasting, travel demand modeling)

  5. WORK TASKS • Synthesis • Issues & Trends • Policy & Reg’l Roles • Demand Forecasts • Travel Demand Modeling • Comparisons • Regional POF Strategy • Landside integration

  6. INITIAL ROUTE SCREENING 32 ROUTES WERE IDENTIFIED BY • Previous planning processes • PAC members • Community members • Market analysis INITIAL ROUTE SCREENING • Prepare Demand Forecasts • Run Travel Demand Model • Daily Ridership Threshold > 200 • Retain all KCFD Routes RESULT: 14 Routes Retained for Further Evaluation

  7. DAILY RIDERSHIP FORECASTS* (2030) * Average Weekday Demand (one way) • Existing Kitsap Transit Foot Ferry operated by Kitsap Transit • Existing POF service operated by King County Ferry District

  8. BREMERTON-SEATTLE ROUTE

  9. ROUTE EVALUATION FINDINGS IMMEDIATE TERM(next 3 yrs) Maintain & enhance existing routes: • Seattle - Vashon Island • Seattle - West Seattle • Bremerton - Port Orchard • Bremerton - Annapolis Most viable new cross-sound routes (crossing times): • Bremerton – Seattle (30 min.) • Kingston – Seattle (37 min.) • Southworth – Seattle (22 min.)

  10. ROUTE EVALUATION FINDINGS(2) MEDIUM TERM(4-10 yrs) Viable based on market demand, require demonstration testing, improved landside connections • Seattle - Port Orchard • Bainbridge - Des Moines • Kirkland - U of W LONG TERM(beyond 10 yrs) Require demonstration testing, market analysis, terminal siting, landside connections • Seattle - Suquamish • Kenmore - U of W • Renton - Leschi • Seattle - Des Moines • Seattle - Shilshole TOURISM AND RECREATION FOCUSED ROUTES Viable in short/medium term: service more likely by private operator • Seattle - Port Townsend • Seattle - Vancouver, B.C.

  11. Resolution EB-09-01 • Supports Passenger-Only Ferry Study Findings • Supports work of local ferry operators • Directs staff to integrate Passenger-Only Ferry Study into Transportation 2040 • Asks staff to engage in regional coordination to implement Passenger-OnlyFerry service: - Funding - Boat, dock, and terminal design and siting - Shared use facilities, fare integration, etc. - Landside connections (transit, bike/ped., etc.) - Planning for water-oriented development - Integrate Passenger-Only Ferries with WSF ferry system - Passenger-Only Ferry role in emergency response

  12. CONTACTS Passenger-Only Ferry Study www.psrc.org/projects/ferry/index.htm Charlie Howard, Transportation Planning Director 1-206-464-7122, choward@psrc.org Stephen B. Kiehl, principal planner 1-206-971-3290, skiehl@psrc.org