Alexandria City Public Schools FY 2015-2024 Capital Improvement Plan. City Council/School Board Work Session April 10, 2014. Purpose of the CIP.
E N D
Alexandria City Public SchoolsFY 2015-2024 Capital Improvement Plan City Council/School Board Work Session April 10, 2014
Purpose of the CIP To provide the Mayor, City Council, and Alexandria community the rationale behind the strategy to address the school division’s need for construction, expansion, and refurbishment of capital assets to ensure the provision of safe and conducive learning environments that support high performing schools
CIP Process • Enrollment projections & capacity • Building conditions and programmatic needs • Available funding • Good stewards of taxpayer dollars
Essential Questions • What is the impact of the enrollment projections on the existing approved capacity program? • What areas were identified to reduce the funding gap in order to respond to resource constraints? • How do we address the funding gap between City appropriation and ACPS capacity needs?
Capacity Planning • Enrollment has increased 3.9% from FY 2013 • FY 2015 Projected Enrollment is 14,171 • An increase of 4% from FY 2014 • Projected to average 3% growth through FY 2020 • No new capacity projects recommended in FY 2015-2024 CIP • Assumes maintaining current School Board approved elementary class sizes • Assumes no expansion of Pre-Kindergarten
Capacity Planning • Major Drivers #1 Student Enrollment #2 Capacity Analysis #3 Modular Building Projects #4 Core Spaces (e.g. cafeteria, parking, etc.) #5 K-8 Building Configuration
CIP Funding- Non-CapacityFY 2015-2024 • FY 2014-2023 School Board approved non-capacity budget exceeded the City Council’s allocation to ACPS by $38.9 million • Applied prioritization methodology and level-loading to meet City Council approved total non-capacity for the ten-year program
School Board Approved and City Manager Proposed Capacity Budget
Patrick Henry Capacity Project • Feasibility study to examine the construction of a new Patrick Henry Pre-K to 8 School on the existing • Areas of examination: • A survey of the existing building condition • A survey of the existing site and utilities including storm water management considerations • Research on all potential environmental constraints of issues that influence early determinations of the project’s feasibility, timing and cost • Existing Pre-K to 8 educational specifications
Overall Funding Gap and Primary Drivers • Over 10-year program there is a $36.6 million funding short-fall between School Board Approved FY 2015-2024 CIP and City Manager Proposed CIP • Major sources of the short fall • New Patrick Henry K-8 Facility (gap of $11.5 million) • New Cora Kelly Facility funded as TBD at $24 million (gap of $24.5 million) • New Facility at a Site TBD funded at $52 million in FY 2022 (gap of $0.4 million) • Non-capacity short fall of $0.2 million in FY 2016
Comments or Questions www.acps.k12.va.us/budgets 703-461-4168