STATUS UPDATE FOR CPRA September 21, 2011. SOUTHWEST COASTAL LOUISIANA FEASIBILITY STUDY. Overview 1. We are 2.5 years into the Feasibility Study Study is being cost shared 50-50 between the State and the Corps. State is performing half of the work

rea
Télécharger la présentation

SOUTHWEST COASTAL LOUISIANA FEASIBILITY STUDY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STATUS UPDATE FOR CPRA September 21, 2011 SOUTHWEST COASTAL LOUISIANA FEASIBILITY STUDY

  2. Overview 1 • We are 2.5 years into the Feasibility Study • Study is being cost shared 50-50 between the State and the Corps. State is performing half of the work • Study remains very visible to stakeholders and officials • The current schedule indicates a Draft Feasibility Report in November 2012 and a Signed Chief’s Report in July 2013

  3. Overview 2 • Changes in Corps policy and guidance have required additional hydraulic modeling and economics inventory work , which has lengthened the study schedule • FOR a CORPS REPORT-HOW MUCH IS ENOUGH? • Corps Reviews • Sea level rise requirements/Future Without Project condition • Hydraulics issues

  4. STATUS • We have worked through many of the requirements and screened the measures under consideration • Through an iterative process we continue to consider measures and the measure types still under consideration include: • Shoreline stabilization • Unique natural features restoration • Marsh creation/restoration • Hurricane risk reduction • Hydrologic and salinity control

  5. STATUS cont’d • Our next step is to combine the best measures/alternatives into plans • Weekly Project Delivery Team meetings should resume in October

  6. ISSUES • No Corps Funding for FY 2012; Southwest Coastal is not in the President’s Budget for 2012 and is unlikely to get a Congressional Add if an Appropriations Bill is ever passed (This means the Corps involvement would stop on September 30, 2011)

  7. PROPOSED PATH FORWARD The State continues with the study and provides the Corps funding for their review and processing in order to achieve a Federally authorized project. (Would require a new Project Management Plan and/or Memorandum of Understanding signed by the State and the Corps)

  8. QUESTIONS Contact Information = norwyn.johnson@la.gov 225-342-0924 Paul.A.Varnado@usace.army.mil 504-862-1808