This update provides a comprehensive overview of the progress on the EMMA project. Key highlights include the current status of the injection line, recent developments in ALICE Pb wall components, and the procurement timeline for various magnets and systems. The report also details the production status of quadrupoles, dipoles, and cavities, emphasizing the completion of machining, welding, and testing procedures. The expected delivery dates and challenges faced in manufacturing and assembly are outlined to ensure clarity on project timelines.
E N D
EMMA DELIVERY UPDATE Neil Bliss
CONTENTS • Layout update • Injection line • ALICE Pb wall • Procurement status
INJECTION LINE Tomography Section Screens x 3 (emittance measurement) New Quadrupoles x 13 New Dipole 30° & BPM at dipole entrance New Dipoles x 2 (33°) & BPMs at dipole entrance Screen Screen & Vert. Slit SRS Quadrupoles x 6 New Dipole 30° Vacuum valve Screen Beam Direction Vacuum Valve Wall Current Monitor ALICE Faraday Cup Spectrometer Screen BPM Neil Bliss
INJECTION LINE Vacuum valve Tomography Section Screens x 3 (emittance measurement) SRS Quadrupoles x 3 Screen SRS Quadrupoles x 2 BPM & Wall Current Monitor Vacuum valve Screen Screen & Vert. Slit Beam Direction New Dipole 30° New Quadrupoles x 13 Ion Pump New Dipoles x 2 (33°) & BPMs at dipole entrance
ALICE 1st Arc Pb Wall SHIELDING WALL THICKNESS: 50 mm Pb
Production Quadrupole Yokes and Clamp Plates • 42 QFs poles have been wire eroded and returned from Metric (sub contractor) and are awaiting painting. • 20 QDs have been assembled • One in five yokes have been measured at Tesla and are within tolerance • Clamp plates laminations have been punched. Stacking and bonding is in progress • Delivery July 16 – Oct 18
Production coils • All coils are wound and over wrapped • 44 QD and 66 QF coils are potted • Brazing and bending of terminations is in progress
Production Cavities Machining • Machining is complete • EB welding in progress • Brazing • Re measure Frequency & Q • Dimensional checks • Chemical etching • Clean • Assemble and pump down • Measure F & Q • Leak Check • Bakeout • RGA & vacuum measurement • Delivery of 7 batches 10 Jul – 10 Sep E B welding
Procurement Exercise Progress • Injection line magnets Contract placed with Scanditronix 29.5.08 required delivery – 4 x dipoles 1.9.08, 12 x quadrupoles 12.10.08 • Ring standard vacuum chamber Tender 23.5.08 – 11.6.08 required delivery 8.10.08 • BPM quotation Tender return 6.6.08 required delivery 29.8.08 • RF system OJEC Tender 12.4.08 – 23.6.08 required delivery 28.2.09 • Septums, kickers & kicker power supplies OJEC Tender 23.6.08 – 7.8.08 required delivery kickers & power supply 3.4.09, delivery of septums 10.11.08