An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fick Observatory - Boone, IA

  2. Faculty advisor: Dr. John P. Basart Client: Joe Eitter ISU Physics Department Team members: Justin Doyle(2nd sem) Derek Halverson (2nd sem) Rob Walstrom (2nd sem) Tai Ward (2nd sem) Shahril Abdullah (1st sem) Jeff Rastrelli (1st sem) Nick Williams (1st sem) Fook-Keong Yap (1st sem) Observatory Automationongo02eMarch 26, 2002

  3. Presentation Outline • Problem Statement • Design Objectives • End Product Description • Assumptions and Limitations • Project Risks and Concerns • Technical Approach • Evaluation of Project Success • Recommendation of Future Work • Human and Financial Budget • Lessons Learned • Summary

  4. Problem Statement • Automation of the Fick Observatory • Phase 1: Remote Control • Phase 2: Automated System

  5. Design Objectives • Functionality • Control the telescope • Collect telescope data • Operate the roof • Gather weather conditions • Provide visual feedback • Provide remote control via the Internet • Automate the system

  6. Control the Telescope • Control via serial port • Filter wheel • Slides/covers • Focus • Raw code vs. commercial • The Sky • Orchestrate

  7. Collect Telescope Data • Combine filtered images • Clean images • CCD video capture • MaxIm DL/CCD

  8. Operate the Roof

  9. Operate the Roof • Telescope room has movable walls and roof • Existing system built in 60’s • Current system uses manual levers • New system run by actuators • Old system had no safety stops • Redundant magnetic and optical safety stops • Computer software controlled

  10. Operate the Roof • Actuators • Magnetic switches • Extensive safety measures • Visual feedback from cameras

  11. Provide Visual Feedback • Surveillance camera system • Streaming live video over the Internet

  12. Provide Remote Control • Main computer accessible via remote access software • PCAnywhere • GoToMyPC • WindowsXP • Radmin • Allow systems to be turned on remotely

  13. Gather Weather Conditions • SkyCam • Protective housing • Weather station • Temperature sensors • Online resources

  14. Design Constraints • Location of observatory • Limited space for adding equipment • Budget • External weather conditions • Overheating of equipment in summer • Interfacing with old equipment • High-speed Internet connection

  15. Intended Users and Uses • Intended users • Physics faculty • Astronomers • Intended uses • Fully automated control (like a VCR timer) • Remote control from campus

  16. End-Product Description • Remote control of all equipment within the observatory • Programmable system to gather data while not being user-controlled

  17. Assumptions and Limitations • Assumptions • Single user access at one time • High-speed Internet connection • Must be secure from Internet attacks • All components powered up prior to use • Limitations • Limited site access for team members • Speed of Internet connection • Hydraulics of existing roof control system • Two speeds at which roof may open or close • Telescope may not be compatible with commercial software • Existing hardware

  18. Project Risks and Concerns • Knowledge of telescope operation • Damaging the telescope • Existing hardware failure • Loss of client

  19. Technical Approach Division of project into sub-projects • Telescope operation • Video • Roof control • Weather station • Remote control

  20. Technical Approach • Split processing to two computers • Roof sensors: magnetic vs. optical • Telescope software: commercial vs. raw code

  21. Evaluation of Project Success • Research (90%) • Documentation (100%) - ongoing • Network (25%) – in progress • Roof control (10%) – in progress • Telescope control (10%) – in progress • Video (20%) – in progress • Weather monitoring (90%) – future semester • Temperature monitoring (0%) – future semester • Remote operation (0%) – future semester

  22. Future Work • Prototype roof control board • Complete roof control implementation • Install surveillance video cameras • Setup server for video streaming • Install remote access software • Remote climate control • Installation of weather station • Fully network all computers in observatory

  23. Human Budget

  24. Financial Budget

  25. Lessons Learned • Communication with client • Clearly defined requirements • Interfacing with old technology can be difficult • Gained knowledge on video frame grabbers, control software, data acquisition cards, etc.

  26. Summary • Firm foundation of research and design • Finished project will greatly increase usability of the observatory

  27. Questions Questions?