1 / 12

AD-Target Area Consolidation 6th meeting Planning review

AD-Target Area Consolidation 6th meeting Planning review. Rui Ximenes; Sven De Man EN-STI. Summary. EDMS: 1751018 Planning overview. EDMS: 1751018. Planning can be found in EDMS 1751018 . MsProject document ; Milestones doc; “Linear planning ”. Planning overview.

rwest
Télécharger la présentation

AD-Target Area Consolidation 6th meeting Planning review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AD-Target Area Consolidation6th meetingPlanning review Rui Ximenes; Sven De Man EN-STI

  2. Summary • EDMS: 1751018 • Planning overview EDMS: 1751018 | Planning overview

  3. EDMS: 1751018 • Planning can be found in EDMS 1751018. • MsProject document; • Milestones doc; • “Linear planning”. EDMS: 1751018 | Planning overview

  4. Planning overview • Planning updated: • 196 Strip down activities updated; • Added updates about CV works in new 196; • Added Fire detection system works in new 196; • Target Area dismantling works reviewed; • Milestones line added to the linear planning. EDMS: 1751018 | Planning overview

  5. Planning overview EDMS: 1751018 | Planning overview

  6. Planning overview Other… 853 works 232 works 196 works 195 works Project Milestones EDMS: 1751018 | Planning overview

  7. Planning overview Other… 853 works 232 works 196 works 195 works Project Milestones EDMS: 1751018 | Planning overview

  8. Planning overview EDMS: 1751018 | Planning overview

  9. Planning overview 196 Strip down (Now – End Jan/19) EDMS: 1751018 | Planning overview

  10. Planning overview 196 Strip down (Now – End Jan/19) EDMS 2030611 EDMS: 1751018 | Planning overview

  11. Planning overview Dismantling Target Area (starting March/19) EDMS: 1751018 | Planning overview

  12. Thank you!

More Related