STANDING COMMITTEE ON APPROPRIATIONS (Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI)). 19 OCTOBER 2012. ASIDI BACKGROUND. SCHEDULE 7 : SCHOOL INFRASTRUCTURE BACKLOGS GRANT. The purpose of the grant is for the eradication of entire inappropriate schools;

saburo
Télécharger la présentation

19 OCTOBER 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STANDING COMMITTEE ON APPROPRIATIONS (Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI)) 19 OCTOBER 2012

  2. ASIDI BACKGROUND

  3. SCHEDULE 7: SCHOOL INFRASTRUCTURE BACKLOGS GRANT • The purpose of the grant is • for the eradication of entire inappropriate schools; • provision of basic level of water, sanitation and electricity to schools. • The grant is also referred to as the ASIDI (Accelerated School Infrastructure Delivery Initiative)

  4. ASIDI Targets The targets are as follows: The budget allocation for the ASIDI programme over the MTEF period is R8.2 billion and allocated as indicated in the table below:

  5. 2011/12ASIDI PROGRESS

  6. ASIDI 2011/12 TARGETS AND ACHIEVEMENTS The following work was implemented during the 2011/12 financial year:

  7. ASIDI 2011/12 TARGETS AND ACHIEVEMENTS • Projects completed from 2011/12 financial year • 8% of IS, 58% Electricity, 67% Sanitation and 63% Water • Water and sanitation Projects in Gauteng, Free State and Western Cape have reached practical completion. • 17 of 60 Sanitation projects in KZN have reached practical completion. • On Water and sanitation projects in EC, forty seven (47) of the 58 sanitation projects have achieved practical completion, • 84 schools in EC have been provided with Rain Water Harvesting tanks and related infrastructure,31 projects have been connected to municipal bulk supply. • Gauteng, Western Cape and Free State have completed the electrification projects. • Eskom has electrified 66 schools to date.

  8. ASIDI PROGRESS ON 49 SCHOOLS • 49 inappropriate schools are progressing as follows: • Progress at 12 of the schools is between 20.1% and 40%; • Progress at 17 of the schools is between 40.1% and 60%; • Progress at 16 of the schools is between 60.1% and 80%; • 4 of the 49 schools are at Practical Completion. • Aerial Photo Survey available for information • The remaining 45 of 49 are planned to be handed over during the October, November and December months. NB: The projections for completion are dynamic and can be earlier or on target date. *schools that experienced delays due to non-performing contractors

  9. ASIDI PROGRESS ON 49 SCHOOLS • Various challenges were encountered during implementation such as: • Difficulty in obtaining material supply - Suppliers not in a position to meet the demand placed by the ASIDI contractors • Difficult terrain requiring unusual earth works and poor access to schools particularly those in remote areas in the Eastern Cape • Redesign of site drawings due to unforeseen physical features on site such as graves • Non performance by contractors: Under estimated the resources required on an accelerated programme • Competition with other business sectors on transportation of bulk • Inclement weather conditions which results in work stoppage on sites and hinders access to project sites for delivery of materials due to poor conditions of the roads, • The effect of the recent trucks strike • Some of these challenges continue to impact on planned completion dates.

  10. ASIDI PROGRESS ON 49 SCHOOLS • DBE interventions • Terminations of contracts ( Inyameko Vukukhanye and TBP Contractors (have applied for business rescue) • A First meeting with contractors chaired by Deputy Minister Surty was held in 25 June • Deputy Minister for Finance together DBE and DBSA officials were in attendance. • SSI Mafuri, TBP and Armstrong who were implementing 24 of 49 ASIDI schools were invited to sort their commitment to complete the schools as planned in August 2012. • These were chosen due to the significant number of projects they were implementing and the slow progress made at the time. • undertakings and commitments were made by contractors to implement measures to recover on the construction programme. • Significant progress was seen from SSI Mafuri and Armstrong • TBP contract was later terminated due to pursuant non performance

  11. ASIDI PROGRESS ON 49 SCHOOLS • DBE interventions (continued) • A second meeting with contractors chaired by the Deputy Minister Surty was held on the 15 October 2012. • The meeting sort to get commitments from contractors to complete the schools before builder’s holiday break in Dec 2012 without absolving them of the contractual obligations. • Deputy Minister for Finance and Justice together DBE and DBSA officials were in attendance. • Base Major, Leungo, Marnolda, Maunga Projects, Setheo, Trencon Construction, Armstrong Construction, Keren Kula Construction and SSI Mafuri JV were invited • All contractors committed to compete the schools within the 2012 Calendar year, provided circumstances beyond their control do not interrupt progress. • PSPs have been instructed to have weekly supervision to monitor Recovery Plans

  12. ASIDI 2012/13 TARGETS The Targets includes 100 inappropriate, 692 electrification, 453 sanitation, 928 water projects.

  13. ASIDI PROGRESS ON 100 INAPPROPRIATE SCHOOLS • On 2012/13 Inappropriate schools implementation • COEGA (24), IDT (11) AND DRPWEC (15) have been appointed for the implementation of the 50 schools in the EC. • CDC • Site Development Plans have been approved and contract documentation is complete • 22 schools have gone out to tender and tenders closed on the 12 October 2012 • 2 schools have land issues which are being resolved with the province • Adjudication on the 25 October • Site handover is scheduled for the 25 November 2012

  14. ASIDI PROGRESS ON 100 INAPPROPRIATE SCHOOLS • IDT EC • Site Development Plans have been approved and contract documentation is complete • 10 schools have gone out to tender and all tenders closing on the 22 October 2012 • Site handover is scheduled for the 16 November 2012 • DRPW EC • Most of the Site Development Plans have been approved and contract documentation is underway • Schools going out to tender on the 29 Oct, 12 Nov and tenders closing on the 20 and 31 Nov respectively. • 3 schools will go out on tender in Jan 2013

  15. ASIDI PROGRESS ON 100 INAPPROPRIATE SCHOOLS • On 2012/13 Inappropriate schools implementation • IDT FS is appointed for implementation of 10 schools in FS and has appointed teams of professional service providers PSPs (engineers, quantity surveyor, architects, etc.), who will start with the preliminary designs. • WCED • is appointed for implementation of 14 schools in WC and has WC Dept. of Public Works as its implementing agent and teams of professional service providers PSPs (engineers, quantity surveyor, architects, etc.), who are in the process of undertaking preliminary designs. • 6 schools have gone out to tender and closing in the 1st week of November • Additional 3 going out to tender in the 1st wk of Nov and the balance in the 2nd week of November • The award is scheduled for January 2013

  16. ASIDI PROGRESS ON BASIC SERVICES • On 2012/13 basic services implementation, • Mvula Trust’s appointment includes implementation of Water and Sanitation in Limpopo and Eastern Cape for 2012/13 as well as Mpumalanga. • Implementation of Water, Sanitation and Electrification in FS, NC and Gauteng will continue to be implemented by the provincial PED’s. • NW PED is the implementing agent of water and sanitation projects in NW. • ESKOM is appointed for the duration of ASIDI for Electrification. • Appointment of additional implementing agents in KZN and EC for water and sanitation as well as Inappropriate schools (21) in Limpopo, Mpumalanga, North West, KZN and North Cape is in progress and will be finalized by end of October 2012.

  17. BUDGETS AND EXPENDITURE

  18. ASIDI: BASELINE BUDGET REDUCTION • No roll-over has been granted on the R700 million which was not spent for the 2011/12 financial year • R76.084 million was spent from the 2011/12 financial year allocation. • R250 million has been cut from the 2012/13 allocation • R2,065 billion is the available budget for the 2012/13 implementation

  19. ASIDI: TOTAL EXPENDITURE • 2011/12 commitments were approximately R1 billion • R76.084 million was paid in 2011/12 and R944.9 million was carried forward into the 2012/13 financial year. • R2.0 billion is the allocated budget for 2012/13 and commitments carried forward are paid from this allocated budget. • 18.19% of the R2.0 billion has been paid as at end of September 2012. • 51.01% of the current allocations has been committed.

  20. ASIDI BUDGET ESTIMATES FOR THE 2012/13 PLANS • The budget estimates for the 4 sub-programmes based on the assessment costs is R 3,82 billion. • Due to no roll-over from 2011/12 allocations • Commitments from 2011/12 of approx. R1bil and the 2012/13 costs estimated at R3,82 billion will be funded from the current reduced allocation of R2,065 billion • The available balance from this financial year’s budget after 2011/12 commitments deduction is approx R1 billion • Of the R3,82 billion estimated for 2012/13 targets, R1 billion is available. • Projects started in this year • Will be implemented over two financial years, i.e 2012/13 and 2013/14 to avoid budget overrun. • Will therefore be completed in the 2013/14 financial year. • Cash flows will be managed closely to keep expenditure within the R2,065 billion available in 2012/13 financial year

  21. ASIDI PROGRAMME OF ACTION Including 12/13 and 13/14 Plans

  22. INFRASTRUCTURE DELIVERY MANAGEMENT SYSTEM (IDMS): The Programme will be delivered according to the Integrated Infrastructure Management System (IDMS) from the CIDB and National Treasury as depicted below.

  23. PROGRAMME MANAGEMENT FRAMEWORK • The ASIDI Programme adheres to the Infrastructure Delivery Management System (IDMS) and has implemented the phases, stages and gates • Phase A: Programme Planning • Phase B: Project Implementation • Stage 1: Delivery Planning • Stage 2: Professional Service Provider (PSP) Procurement • Stage 3: Design • Stage 4: Contractor Procurement • Stage 5: Works & Practical Completion • Stage 6: Final Completion and Hand-over • Stage 7: Project Closing • Phase C: Programme Closure

  24. PROGRAMME MANAGEMENT FRAMEWORK • As depicted in the Programme Delivery Process Map, the ASIDI programme has also implemented a comprehensive programme management approach including the following: • Scope Management • Cost Management • Time Management • Procurement and Contract Management • Monitoring and Reporting • Budgeting and Programme Accounting • Performance Management • Risk Management • Quality Management

  25. PROGRAMME MANAGEMENT FRAMEWORK • Scope Management: The scope of the ASIDI will be managed through the scope management documents. Each scope management document must be approved according to the formal approval process. • Cost Management: The National DBE has compiled a Standard Bill of Quantities (BoQ) for each type of project to be executed. PSP will be obliged to use the standardised bill of quantities for cost estimation. • Time Management: The Department of Basic Education has adopted the project execution plan (PEP) approach from the IDMS as its approach to time management of the ASIDI projects.

  26. PROGRAMME MANAGEMENT FRAMEWORK • Procurement and Contract Management: Appointment of Implementing Agents, Professional Service Providers and contractors is done within the context of section 217 of the Constitution and PFMA regulations 16A. Framework agreements will be established with PSP`s, IA`s and contractors for a period of 3 years. • State-owned implementing agents may be appointed through a negotiated process in terms of the Intergovernmental Relations Act. • The following contracts will be used, Memorandum of Understanding for state Implementing Agents, The NEC3 will be entered into with the Private Implementing Agents for all elements and PSP`s for each school individually, and JBCC (2000) between the IA and contractor

  27. PROGRAMME MANAGEMENT FRAMEWORK • Monitoring and Reporting: DBE has adopted the IDMS Gateway System for the Monitoring, Reporting and Control of the project. • Budgeting and Programme Accounting: Programme budgets will be updated with the actual cost for implementation for each programme phase; invoices will be paid within 21 days once verified against the certificates. Trenches will be managed and a reconciliation on all outstanding payments conducted. • Performance Management: Key Performance Indicators (KPI`s) have been established and will be monitored on a quarterly bases through feedback from the monitoring and reporting process.

  28. PROGRAMME MANAGEMENT FRAMEWORK • Risk Management:The programme manager must establish a risk register. • The risk register must contain a risk description, category, evaluation and actions for the treatment of the risk. Key programme risks which will be managed include: • projects not delivered on time and expenditure behind cash flow project; • key information not available; • projects not completed on time or poor quality; • clash of dates and non-availability of key stakeholders; and • signboards erected late or with wrong details. • Quality Management: a number of standards and guidelines have been compiled for each programme phase and all programme role-players will be required to adhere to these standards and guidelines.

  29. DEVELOPMENT MANAGEMENT • Social (Including Stakeholder Community) Facilitation: DBE will ensure that communities are informed of all the developments occurring around their specific environment. This will include traditional leaders, School Governing Bodies (SGB`s), and the community through various forums.

  30. ASIDI 2012/13 PLANS- RISK MITIGATION • Involvement of PICC • To help remove bottlenecks such as ESKOM connections • Where there are access challenges • Integration of planning between infrastructure projects in provinces and government contracts • Involvement of suppliers to ensure sufficient quantities of Programme supplies • Allocation of Manageable projects to IAs to enhance effective control • Increase in the number of contractors to spread the risk • HR Strategy in provincial Departments to enhance Monitoring • Monitoring Agreements with DRPW in Provinces for quality control

  31. ASIDI IMPLEMENTATION APPROACH • The programme approach has been revised. • It is not limited to the existing relationships with DBE’s implementing agents as the only mode of delivery. This has already demonstrated the risk and constraints. • DBE is increasing its capacity to ensure that it is able to maintain a greater degree of control at project level. • DBE is also beginning to encourage efficiency by allowing the slack capacity to be used to accelerate delivery where practical. • There is a conversation underway between DBE and NT to revise the current allocations in the outer years.

  32. ASIDI: IMPLEMENTATION APPROACH • The following implementation measures and principles have been adopted and adhered to in the programmes: • Work Packages as a mechanism to manage the work breakdown structure but, retain the economy and scale required to accelerate delivery. • The Project Cycle turnaround time can be reduced to accelerate the programme and minimise bottlenecks. • Procurement bottlenecks be minimised by using a range of procurement strategies and expanding the resource pool beyond DBE. • Adopt a mix of delivery modalities increasing the number and diversity of implementing agents. • In addition to traditional procurement and procurement through implementing agents, DBE has entered into strategic relationships with those PED’s who have already established their own resources panels. These rosters be made available to the programme in the procurement of professional service providers and contractors.

  33. ASIDI: IMPLEMENTATION APPROACH • The following implementation measures and principles will be adopted and adhered to in the programmes: • DBE will negotiate with other National Department of Public Works in relevant provinces, their rosters are constituted of the relevant built environment skills sets and may already have a geographic focus. • The DBE has initiated a process to implement a framework agreement procurement model. • Implementing Agents, Professional Service Providers and Contractors are pre qualified. The services can be secured through their inclusion in a pre approved panel. DBE and the implementing agents have access to the panel appointed through the framework agreement. Thus reducing procurement through traditional open tender routes. It has the possibility of attracting larger contractors and professional teams. Project Teams will be assembled from the framework agreement.

  34. ASIDI 2013/14 PLANS • 346 remain to be implemented in 2013/14 • 328 in EC, 8 in WC and 10 in FS • 50 in EC have been issued to DBSA to star with the planning process • The remaining 75 in EC, 8 in WC and 10 in FS will also be issued to other IAs to commence with Planning process • 203 Inappropriate schools EC have enrolment figures of below 135 learners • In line with the guidelines these schools cannot be provided with a full compliment of infrastructure to schools with higher enrolment (over 135 learners) • DBE is working closely with the Province on rationalisation process to avoid delays in implementation in the next financial year.

  35. THANK YOU