This document highlights the essential lessons learned from the NLRIP and QSRA initiatives, emphasizing the importance of proactive engagement rather than mere compliance. Key aspects include integrating a comprehensive P3e program, eliminating unnecessary contingencies, and developing robust contingency plans that encompass operational activities. Effective discussions among clients and contractors, early operational engagement, and honest reporting are critical. Discussions focus on worst-case scenarios and include checkpoints to ensure thorough participation. These practices not only facilitate informed decision-making but also enhance overall project success.
E N D
QSRA • Not just used as a tick in the box exercise • Used to support decisions with scope, durations and risk mitigation • Key part of the discussions with ops / contractors • Key ingredients are:- • Integrated P3e programme • Contingency removed from activities • Client and Contractor PM’s
Contingency Plans • Expanded to cover site activity mitigations • Include hold / go no go points • Gain buy in from contractors and Ops • Walk through the programme • Ensure plans cover worse case
Site Reporting Tool • Doesn’t work for blockades • Linked to live P3e updates • P3e outputs showing status / progress • Honest reporting • Programme Controls driven
Reviews • Honest reviews / good attendance • Contractor presentations • Ops early engagement • Challenge / Challenge • Part of the day job • No Go’s give focus