240 likes | 257 Vues
REPUBLIC OF BULGARIA MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS. Road infrastructure in Bulgaria. Vasilka Kostadinova Director of Directorate “Implementation of EU funded Projects” Road Infrastructure Agency. Slovene – Bulgarian Business Forum, 12 th May 2010. 1.
E N D
REPUBLIC OF BULGARIA MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS Road infrastructure in Bulgaria Vasilka Kostadinova Directorof Directorate “Implementation of EU funded Projects” Road Infrastructure Agency Slovene – Bulgarian Business Forum, 12th May 2010 1
Road Junctions – 268 km Motorways – 418 km I Class roads – 2975 km II Class roads – 4027 km • Territory of Bulgaria: 110 900 km² • Total length of national roads: 19 436 km • Density of national roads: 0.18 km/km² 4
State budget; Pre-accession programmes PHARE and ISPA; Operational programmes Transport and Regional development 2007-2013(EU financing); State investment loans Sources of financing: 5
Operational Programme Transport 2007 – 2013 Total budget of 990Million Euro for construction of 213 km motorways and 69 kmI class roads, part of the TEN-T network. Road Infrastructure Agencyis the only beneficiary on Priority Axis II “Development of road infrastructure along the major national and Pan-European transport axes”. 6
Projects in Operational Programme Transport 1. Trakia MW (from Sofia to Burgas) – 115 km – 350 Million Euro 2. Mariza MW (from BG to TR) – 67 km – 208 Million Euro 3. Struma MW (from BG to GR) – 132 km – 250 Million Euro 4. Kardshali – Podkova (from BG to GR) – 28 km – 32 Million Euro 5. Hemus MW(from Sofia to Varna) – 8.5 km – 32 Million Euro 6. Е-79, Vraza – Botevgrad (north of Sofia) – 31 km – 85 Million Euro • Е-79, Vidin – Montana (from RO to BG) – 20 km – 32 Million Euro Σ 990 Million Euro 7
Projects on Operational Programme Transport 2007 - 2013 7 6 1 5 2 4 8 3
“Trakia” MW, Lot 2 Stara Zagora–Nova Zagorafromkm 210+100 to km 241+900 Length – 31.800 km Sections of Trakiya MW in exploitation Projected sections of Trakiya MW • The tender procedure for construction is completed. Signature of construction contract: 23 April 2010 Investment cost: 70.5 Million Euro. • The tender procedure for supervision was announced on 22 February 2010. Signature of contract: expected in May 2010 • End of construction: Summer 2012 9
“Trakia” MW, Lot 3 Nova Zagora – Yambol from km 241+900 to km 276+200 Length – 35.697 km Sections of Trakiya MW in exploitation Projected sections of Trakiya MW • Start of the tender procedure for construction: 26 February 2010. Signature of contract: expected inJuly 2010. • Start of the tender procedure for supervision: 23 April 2010. Signature of contract: expected in July 2010 • End of construction: Summer 2012 • Tentative investment cost: 108 Million Euro 10
“Trakia”, Lot 4 Yambol - Karnobat from km 276+200 to km 325+280 Length – 49.080 km Sections of Trakiya MW in exploitation Projected sections of Trakiya MW • Start of the tender procedure for construction: 07 April 2010. Signature of contract: expected in August 2010. • Start of the tender procedure for supervision: expected 14 May 2010. • Signature of contract: expected in August 2010 • End of construction: Autumn 2012 • Tentative investment cost: 146 Million Euro 11
“Maritza” MW, Orizovo – Harmanli (connection Trakia MW – Turkish border) from km 5+000 to km 71 + 011 Length – 66,011 km • Tender procedures for construction and supervision: Preparation of tender documentation is forthcoming. Start of tender procedures - second half of 2010 expected. • Possible division of the project implementation – in 2 lots. • Tentative investment cost: 209 Million Euro 12
Corridor No IV, Sofia to Greek border Lot 1 Dolna Dikania – Dupnitza from km 305+220 to km 322+000 Lot 2 Dupnitza-Blagoevrad from km 322+000 to km 356+000 Lot 4 Sandanski-Kulata from km 423+500 to km 438+500 Lot 3 will be constructed in the next programming period 2014-2020 Total length of Lot 1, Lot 2 and Lot 4: 65.78 km. Indicative cost: 250 Million Euro. Tender procedures for construction and supervision of Lot 1 and Lot 4: first half of 2011. Lot 2 – Tender procedure for design: forthcoming Struma Motorway 13
„Hemus” Motorway Section : „Sofia Ring Road – “Yana” road junction”from km 0 to km 8+460. • Start of the tender procedure for construction and supervision: expected in June 2011 • Selection of Contractor and Consultant: expected in October 2011 • Tentative investment cost:32 Million Euro 14
Corridor No IX, road to the Greek border The project includes rehabilitation of 8 km of the existing road and 24 km new construction from Kardzhali to Podkova. RoadI-5 Kardzhali – Podkova • Start of the tender procedure for construction and supervision: expected in December 2010 • Selection of Contractor and consultant: expected in April 2011 • Tentative investment cost: 32 Million Euro 15
Operational Programme Regional Development 2007 - 2013 OPRD Phase 1, 302 km 14 Lots, ongoing tender procedures for construction and supervision. Expected beginning of the construction – July 2010.Budget – 110, 6 mil. Euro OPRD Phase 2, 311 km 15 Lots, tender documents are approved. Expected start of tender procedures –second half of 2010. Budget – 135,5 mil. Euro OPRD Phase 3 Indicative list of projects, ready to be included in the programme. 16
ІI. Road infrastructure projects for design 2010 – 2013 under Operational Programme Transport Construction 2014 – 2020 17
Operational Programme Transport OPT – 2007-2013 PROGRAMME PERIOD OPT – 2014-2020 PROGRAMME PERIOD 18
Struma Motorway Lot 3 /Blagoevgrad - Sandanski/ • Total length: 67.5 km • 3 major sections: • 3.1 - Blagoevgrad – Krupnikfrom km 356+000 to km 380+000 • 3.2 – Krupnik – Kresna (Kresna defile) from km 380+000 to km 400+600 • 3.3 - Kresna – Sandanskifrom km 400+600 to km 423+500 Preparation of Application form for funding the design of Lot 3 by Technical Assistance of Operational Programme "Transport“ is ongoing. Start of tender procedures for design – Autumn 2010. 19
Trakia MWLot 6 (Black Sea Motorway) The project is part of the Pan-European Transport Corridor No. VIII and connects the two biggest ports of the Republic of Bulgaria – Varna and Burgas Length:100 km Indicative cost: 350 Million Euro 20
“Sofia – Kalotina (border to Serbia)” MW Length:50 km Indicative cost: 150 Million Euro 21
“Sofia – Gyueshevo (border to Macedonia)” MW Length:85 km Indicative cost: 260 Million Euro 22
“Shipka” Tunnel The total length is approx.:3.2 km 23