1 / 9

Click on the arrow to go to the next question.

You will be asked seven (7) short questions. Please answer 'yes' or 'no' to these questions to find out if you need a Permit to Work from Port of Brisbane Pty Ltd. At the end of the questionnaire, you will be provided with a list of forms for you to complete. Please

Télécharger la présentation

Click on the arrow to go to the next question.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. You will be asked seven (7) short questions. Please answer 'yes' or 'no' to these questions to find out if you need a Permit to Work from Port of Brisbane Pty Ltd. At the end of the questionnaire, you will be provided with a list of forms for you to complete. Please click on the link provided. Then, print, complete and give the relevant forms to an Authorised Person from the Port of Brisbane. Click on the arrow to go to the next question.

  2. Q1. Is the specified plant or energy isolation required? • Yes • No Does the plant isolation involve the hanging of isolation locks &/or isolation tags (apart from high-voltage switching)? • No • Yes

  3. Q2. Is high-voltage switching required? • Yes • No Is switching of high voltage apparatus required for plant maintenance, fault response or electrical loading changes? • No • Yes

  4. Q3. Is specified work on/near electrical installations required? • Yes • No • Does it involve electrical maintenance work to be undertaken on live plant / parts? This excludes: • • test to prove de-energised actions during isolations, or • • basic low voltage fault finding tasks that are undertaken prior to an isolation and corrective electrical works. • No • Yes

  5. Q4. Does the work involve specified hot works? • Yes • No • Does it involve hot work that is not within a designated area? Designated hot work areas include: • specific maintenance / repair workshops fitted with extraction and other easily accessible fire controls, • the bow of the Ken Harvey vessel, • the cutter platform of the Amity vessel, • reclamation field areas where plant or any other flammable substance / material is not within a 15m radius of the hot work location. • No • Yes

  6. Q5. Does the work involve specified excavating or digging? • Yes • No • Does it involve specific excavation or digging tasks at a depth of > 300mm, including the driving of objects into the ground? Exclusions, however, include the followings: • • the movement of spoil piles or clearing of drains, • • reclamation works within established reclamation field zones where services are known not to exist and entry to excavations is not required. • No • Yes

  7. Q6. Does the work involve specified work at heights? • Yes • No • Does it involve specific access or work at height where a fall of 2m or more could occur and/or there is a risk of impalement? This excludes: • • accessing a fixed stairway or ladder, • • using a portable ladder for permitted light work duties, • • accessing or working from fit for use scaffolding, • • access or work on a rooftop that does not require a clearly delineated fall zone to be entered (an area within 3m from an unprotected edge on a flat roof). • No • Yes

  8. Q7. Is entry/work in a confined space required? • Yes • No • Refer to the following as guidance in determining whether a space is confined: • • the confined space definition, • • on-site confined space signage, • • confined space registers. • No • Yes

  9. Click here to view the list of forms you are required to complete. These forms are available under the Health and Safety section on the Port of Brisbane website. - Complete the Permit to Work form and contact an Authorised Person from the Port of Brisbane. - Plant Isolation Control Form. Plan Isolation Steps Sheet might be needed. - High Voltage Switching Sheet - High Voltage Access Form - High Voltage Test Permits - Live Electrical Control Form - Hot Work Control Form - Excavation Digging Control Form - Work at Heights Control Form - Confined Space Control Form Click to print this slide.

More Related