Project Task Planning 1

Project Task Planning 1. Concepts and Definitions Work Breakdown Structures. Concepts. First, some terms: Deliverables: Things you produce and deliver to a stakeholder Activities: Major work groupings whose completion result in the completion of a deliverable

savea
Télécharger la présentation

Project Task Planning 1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Task Planning 1 Concepts and Definitions Work Breakdown Structures

  2. Concepts First, some terms: • Deliverables: Things you produce and deliver to a stakeholder • Activities: Major work groupings whose completion result in the completion of a deliverable • Tasks: Smaller units of work from which activities are composed • Milestone:measurable achievement on a project; typically the completion of an activityor the completion of a deliverable. • Work package:Leaf nodes of a work breakdown structure; these represent the atomic units of work from that WBS’ perspective • Subprojects may decompose a work package in a separate WBS Second, notice what terms are not on here: • Schedule, Dependency, Time, Resources • These are not today’s game

  3. Work Breakdown Structures What are WBSs for? • Before worrying about what to do first (or next), a project manager must first have a tool for organizing the scope of work. • This dictates team composition, phases of work, reporting structure, … • An excellent “macro-”level tool • This is big picture, “get your arms around it” organizational stuff • Therefore, this tool is useful early in a project or in a phase. Approaches to Developing WBSs: • Deliverables driven: Remain focused on decomposing by deliverable to ensure better estimating and tracking. • Guidelines: Some organizations (DOD), provide guidelines for preparing WBSs • Analogy approach: It often helps to review WBSs of similar projects • Top-down approach: Start with the largest items of the project and keep breaking them down • Bottom-up approach: Start with the detailed tasks and roll them up Course Technology, 1999

  4. Work Breakdown Structure A work breakdown structure (WBS) is an outcome-oriented analysis of the work involved in a project that defines the total scope of the project • Provides the basis for planning and managing project schedules, costs, and changes • Does not show interdependencies or sequencing • Captures the total scope of the project • Note the tree-like, taxonomical categorization of work • Can be organized many ways - this one by Deliverable Course Technology, 1999

  5. Intranet WBS Organized by  Phase More WBS Examples Intranet Project Application Dev Systems Arch Deploy- ment UI Design Course Technology, 1999 Middle ware Database Schema Security Arch E- Commerce Message Service Intranet WBS Organized by Function 

  6. Even More WBS Examples Build software System design (2.0) Coding (3.0) Testing(4.0) Delivery (5.0) Review specification(1.1) Top-level design (2.1) Review budget (1.2) Prototyping (2.2) Review schedule(1.3) User interface (2.3) Develop plan (1.4) Detailed design (2.4) Intranet WBS Organized by Lifecycle Phase  Activities «break down into» System planning (1.0) 1.0 Concept 1.1 Evaluate current systems 1.2 Define Requirements 1.2.1 Define user requirements 1.2.2 Define content requirements 1.2.3 Define system requirements 1.2.4 Define server owner requirements 1.3 Define specific functionality 1.4 Define risks and risk management approach 1.5 Develop project plan 1.6 Brief web development team 2.0 Web Site Design 3.0 Web Site Development 4.0 Roll Out 5.0 Support WBS Tabular Organization Tasks «roll up into» Course Technology, 1999

  7. A Bad WBS Example

  8. WBS Top 10 Best Practices* • The top element of the WBS is the overall deliverable of the project, and all stakeholders agree with it. • The first two levels of the WBS (the root node and Level 2) define a set of plannedoutcomes that collectively and exclusively represent 100% of the project scope. • The WBS elements are defined in terms of outcomes or results. (Outcomes are the desired ends of the project, and can be predicted accurately). • The WBS encompasses everything that will ultimately comprise the project deliverable, and all deliverables in the project are included. • Each WBS element contains the following two items: • the scope of work, including any “deliverables,” • the name of the person responsible for the scope of work. • There is no overlap in scope definition between two elements of a WBS. • The WBS is not a project plan or schedule, and it is not a chronological listing. • The WBS is not an organizational hierarchy. • The WBS has been decomposed and it is no longer possible to define planned outcomes–the only details remaining are actions. • The WBS is not an exhaustive list of work. It is a comprehensive classification of scope. *Abridged from M.D. Taylor, http://www.pmhut.com/wbs-checklist

  9. Pros and Cons of WBSs Benefits: • Organized, hierarchical structure of tasks • Leads to traceability • Easier to plan task categories • Easy to track task categories at various levels • Accountability can be assigned at various levels • Tool support • There are a lot of WBS/PM tools available to you • RC/Jazz WorkItem hierarchies can be organized likewise Drawbacks: • Horizontal task dependencies not identified • Does not provide a calendar or other type view of concurrent tasks • These drawbacks are really common misuses of WBSs!