Workshop on Pressure Equipment Directive: In-Service Inspection in UK Legislation
160 likes | 177 Vues
This workshop provides an overview of UK legislation on in-service inspection of pressure equipment, including the Pressure Systems Safety Regulations 2000. It covers responsibilities, exemptions, written schemes of examination, examination requirements, and actions in case of imminent danger.
Workshop on Pressure Equipment Directive: In-Service Inspection in UK Legislation
E N D
Presentation Transcript
Workshop on the Implementation of the Pressure Equipment DirectiveWorking Group 4: In-Service InspectionOverview of UK LegislationMartin YatesSafety Assessment Federation
History • Factories Acts • Steam Boilers • Steam Receivers • Air Receivers • Pressure Systems Safety Regulations • All Pressure Systems • All Places of Work
Pressure Systems Safety Regulations 2000 Responsibilities for: • Designers • Manufacturers • Installers • Owners and Users • Repairers • Competent Persons
Pressure Systems Safety Regulations 2000 Applicable to: • Rigid Pressure Vessels, Pipework, Protective Devices • Pipework and Protective Devices with Gas Cylinders • Pipelines and Protective Devices
Pressure Systems Safety Regulations 2000 Relevant Fluid • Steam • Gas > 0.5 bar • Liquid with vapour pressure > 0.5 bar
Pressure Systems Safety Regulations 2000 Exemptions • Ships or aircraft • Braking systems on vehicles • Road tankers subject to ADR • Research experiments • Refrigeration systems < 25 kW
Pressure Systems Safety Regulations 2000 Partial Exemptions • Each pressure vessel < 250 bar litres (Not steam) Exempt from in-service inspection • Equipment supplied under PED Exempt from new construction requirements
In-Service Inspection Requirements • Regulation 8 – Written Scheme of Examination • Regulation 9 – Examination in Accordance with the Written Scheme • Regulation 10 – Action in case of Imminent Danger
Regulation 8 – Written Scheme of Examination • Owner/User must have a written scheme • Pressure vessels • Protective devices • Pipework • Certified by Competent Person • Reviewed periodically
Content of Written Scheme • Parts to be Examined • Nature of Examinations • Preparations Required • Intervals between Examinations • Competent Person • Date of Certification
Regulation 9 - Examination in Accordance with Written Scheme • Carried out by Due Date • Preparations and Safety Requirements • Suitable Examinations • Reports
Regulation 10 - Action in Case of Imminent Danger • Site Defect Report • Report to Enforcing Authority • System not to be Operated
Categories of System • Minor • Intermediate • Major
Attributes of Competent Person • Staff • Specialist Services • Organisation • UKAS
Conclusions • Goal Setting Legislation • Flexibility of In-Service Inspection • Can Reduce Costs with Increased Inspection Periods • Can Reduce Downtime with Alternative Inspection Techniques
Examination Frequency • Records for System/Similar Plant • Current Condition • Operating Conditions/Contents • Levels of Maintenance • Industry Guidance • Risk Based Inspection