An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. California Water Service CompanyPCH Pipeline Replacement Project Community Meeting February 15, 2006

  2. Project Overview

  3. Project Details • Phase 1 (Knob Hill Avenue to Pearl Street) • Replace 2,885 feet of water main lines and install 9 new fire hydrants • Project will improve water quality, increase fire flow, and increase water reliability • Construction will take place Monday through Friday from 9 a.m. – 3 p.m. • Construction will begin March 1 and end by May 26

  4. Estimated Timeline • March 1-3 Phase 1 construction to begin • March 6 – April 6 New pipeline to be installed • April 6 - 12 Fire hydrants to be installed • April 13 – May 22 Services to be tied-in • May 26 Phase 1 construction completed

  5. Traffic Control

  6. Potential Impacts • Access to businesses and residences on east side of PCH may be obstructed for 1-2 days between 9 a.m. and 3 p.m. • Traffic control plan may limit accessibility and parking availability on Pacific Coast Highway • Additional noise and dust not expected to be inordinately disruptive • Water service may be temporarily interrupted during tie-in to new water main line

  7. Customer Communications • Bill insert • Direct mailer • Door hangers • Weekly e-mail updates • Updates on web site (www.calwater.com)

  8. Cal Water Contacts • Linda Giardini, Project Manager (310) 257-1428 • 24-hour emergency number (310) 257-1400

  9. Questions?