1 / 14

ENVISAT PDS Status & Plans

ENVISAT PDS Status & Plans. First 6 Months in Orbit & Objectives for the Last Quarter 2002. PDS Overall Status and Plans: Points to be addressed. Operation strategy (the Kiruna scenario) Encountered difficulties and progress Recovery Plan for the last Quarter 2002

shilah
Télécharger la présentation

ENVISAT PDS Status & Plans

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ENVISAT PDS Status & Plans First 6 Months in Orbit & Objectives for the Last Quarter 2002

  2. PDS Overall Status and Plans: Points to be addressed • Operation strategy (the Kiruna scenario) • Encountered difficulties and progress • Recovery Plan for the last Quarter 2002 • Stabilisation of the PDS towards a sustained throughput • Evolution of the operation scenario (Kiruna- Svalbard) • Services to be made progressively available in NRT (Kiruna and ESRIN PDHS) and Offline (LRAC and PACs) • Progressive opening of the User services and phase in of the PIs • Objectives for the last quarter 2002: • Fulfilling the validation objectives (PDS serving all Cal/Val PIs in time) • ENVISAT Mission to be operational by end 2002 For a subset of products and services

  3. Kiruna Only Scenario • Kiruna Station Data Reception • Receives the complete global mission data dump • 8 orbits are received nominally ( dump of the previous orbit within the Kiruna visibility) • 4 to 5 orbits out of visibility are recorded and dumped in the first two orbits of the morning, together with the nominal preceding orbit • Receives all recorded ASAR HR and MERIS FR • Receives ASAR HR and MERIS FR in direct visibility • Matera Station Operation • Receives ASAR HR and MERIS FR in direct visibility (2 orbits in the morning, 2 orbits in the evening) • Copies the data on D1 tapes, sent to ESRIN • Processing at ESRIN PDHS-E

  4. 6 5 4 3 2 1 Kiruna Blind Orbits • 5 consecutive blind orbits (marked 1 to 5) recorded on SSR 1 and 2 • Dump of the recorded data over Kiruna on the first two orbits of Kiruna (first orbit marked 6 )

  5. Kiruna Station Data Processing (PDHS-K) • Global Mission processing strategy • Generation of all level 0 (recovery of any missing level 0 offline over night) • Processing of all level 1B and 2 for the nominal 9 to 10 orbits per day • All level 0 copied on NTP tapes for the LRAC • Dissemination of level 0, level 1B and level 2 products to Cal/Val users according to GSOCP • Over the DDS • On FTP server • On media ( CD-rom and exabytes generated at Kiruna), duplication of AATSR and SCIAMACHY media foreseen at UK-PAC and D-PAC

  6. Kiruna Station Data Processing (PDHS-K) cont’d • Regional Mission Strategy • All ASAR HR processed to level 0 and sent, on NTP tapes, to the 3 PACs • All ASAR HR data processed to medium resolution and Browse • On request processing of ASAR full resolution images • MERIS FR processed to level 0 and sent, on NTP tapes, to the 3 PACs (MERIS browse obtained from the RR data processing) • Dissemination to Cal/Val users according to GSOCP: • On DDS • On media (CD-Rom and Exabytes) • Recent decision to provide full resolution ASAR and MERIS images from PDHS-E and PACs (offline processing and dissemination on media)

  7. Mission Planning • Global Mission defined using the RGT ( Reference Ops Mission generation Tool) • Regional Mission • ASAR operation and on request processing defined by the Cal/Val coordinator via a USF script • MERIS operation and on request processing defined by the Cal/Val coordinator via a script • Background mission defined by the Mission Manager and entered via the USF • Additional PR images requested by ESRIN via the USF • All above nominally defined one week ahead of its execution schedule

  8. Problems Encountered • Lack of robustness of the PDS facilities; • Missing/incomplete functionalities (e.g. concatenation of product slices to make complete instrument operation segments, incomplete follow up and reporting of orders, recovery of failed orders, etc…); • Misfit between the installed Kiruna configuration and the Kiruna scenario • Irregular production throughput at PDHS ; To be noted: • The Kiruna scenario is much more demanding for this station than any future nominal scenario • Testing of the operation, pre-launch, was very much constrained by the limited set of satellite simulated data available ( 3 orbits)

  9. Corrective Actions Implemented Significant progress achieved, today: • PDCC ( mission planning): problems circumvented; • Kiruna configuration partially corrected ( hardware upgrade planned 8 to 12 September) • PDHS: scheduling and production throughput under control, still some product losses in between production, archiving and dissemination (under analysis); • Procedures and scripts put in place to recover failures and missing products ( still to be improved) • LRAC and PACs activities initiated • Instrument Processors corrected to reflect current Cal/Val status.

  10. Data Distribution Current Status • Global Mission Data Products • Meteo products on FTP server towards meteo centre started on 15 August for RA-2, MERIS, AATSR and MIPAS (ASAR Wave to be activated this week) • Media copying at PDHS-K of level 1B and 2 products for distribution to Cal/Val PIs • Product dissemination via DDS ( the best of all services so far) and FTP server • Unfortunately, production not yet achieving the 90% availability target • Regional Mission Data Products • Cal/Val PIs served via on line distribution from PDHS-K (DDS) • Media copying of products at PDHS-K for distribution to Cal/Val PIs • ASAR and MERIS FR images to be produced at PACs: test images already produced and copied on media, production of images for Cal/Val PIs to be started next week

  11. Plan for last Quarter 2002 (1) • Upgrading of the PDHS-K hardware (processor nodes) to ensure the required throughput, 8-12 September (while the payload is stopped for the inclination manoeuvre and for loading of the updated PMC software) • Getting the LRAC operational for systematic production of consolidated level 1b (prerequisite for PAC level 2 offline production): • production testing and analysis on going, • objective: operational readiness 15 October • Getting the PACs operational for offline production and delivery of ASAR and MERIS FR images (test in progress, production to start by 15 September for the Cal/Val PIs)

  12. Plan for last Quarter 2002 (2) • Global Mission service • Priority given to Cal/Val PIs for level 1b and level 2 product delivery • Cal/Val PIs to be served with non consolidated products level 1b and 2 (produced at PDHS) as long as consolidation not available operationally • DDS and FTP servers to be used in priority for Cal/Val needs • Use of PACs for archiving of non consolidated level 1b and 2 products and duplication/distribution on media (to reduce the burden on the PDHS) • For Non Cal/Val PIs: • progressive access to calibrated level 1B to be provided, service to be enlarged to level 2 products as they become validated (towards end 2002) • Service to be provided offline from the PACs, starting with non consolidated products ( on request service for images MERIS RR and AATSR, subscription service wherever compatible with the product size)

  13. Plan for last Quarter 2002 (3) • Regional Mission service: ASAR and MERIS FR • Priority to be given to Cal/Val PIs for data acquisition, production and distribution • PDHS-K and E (Kiruna and ESRIN) to ensure the complete level 0 delivery to PACs • Production of all ASAR medium resolution images and browse at PDHS-K and E • Limited NRT processing and delivery of full resolution images from Kiruna • On request production of level 1 b and 2 products at PACs and distribution on media from PACs (some offline processing at ESRIN PDHS if needed); • Progressive phase in of non Cal/Val PIs starting mid September, the objective is to have 250 PIs phased in by end 2002 • Help/Order Desk interfacing with the PIs • Access to the user service inventory and on line browse • Delivery of level 1b image data products offline via the PACs • Extensive background acquisition to build up an archive, accessible to PIs

  14. Plan for last Quarter 2002 (4) • Initiation of the Kiruna-Svalbard Scenario mid October, with the following Global Mission scenario: • The 5 orbit Svalbard received data to be transmitted by DDS to ESRIN for pseudo NRT (delivery within 12 hours from data take ) • The 9 to 10 orbit Kiruna received data to be processed and disseminated to users within 3 hours from data take • Regional Mission (ASAR and MERIS FR) benefit from Kiruna-Svalbard scenario: • Data acquisition anywhere on the globe, using the SSR, with data dump available every orbit. • Concurrent recording of ASAR and MERIS FR to be provided before mid December 2002. This PDS Plan will fulfill the Cal/Val PIs data needs

More Related