1. The __ ultimately decides if the project quality is acceptable 10 • Project team • CEO • Project Manager • Customer 0 of 30
2. The __ is the portion of the approved total cost planned to be spent on an activity during a period 10 • AC • EV • RP • PV 0 of 30
3. The __ is an estimate of the value of physical work actually completed 10 • AC • EV • RP • PV 0 of 30
4. __ is the ability of a product or service to perform as expected under normal conditions 10 • Reliability • Performance • Maintainability • Functionality 0 of 30
5. Testing needs to be done only during the prototype and implementation stages 10 • True • False 0 of 30
6. Rough order of magnitude estimates are used: 10 • When no other estimates are available • In all cases • Early in a planning process when the project is initially being considered 0 of 30
7. Databases are a common tool for cost estimating, cost budgeting and cost control 10 • True • False 0 of 30
8. Monte Carlo simulations may be used to determine the number of lines of code in a project 10 • True • False 0 of 30
9. ___ use the actual costs of a previous, similar project as the basis for estimating the cost of the current project 10 • Actual estimates • Parametric estimates • Bottom up estimates • Analogous estimates 0 of 30
10. DMAIC would be associated with: 10 • Costing • Quality • Human Resources • Communication Plans 0 of 30
11. To assist in resource leveling one would: 10 • Go to Home Depot and purchase a level • Use a pareto chart • Use a trigger in a risk management plan • Use the critical path diagram looking for slack 0 of 30
12. A trigger refers to: 10 • An event in testing • An event in a WBS • An item in a gun • An event in risk planning 0 of 30
14. Cost and time monitoring involves: 10 • EV • PV • SV • All of the above • 1 and 2 • 2 and 3 • 1 and 3 0 of 30
15. A(n) ___ is a hierarchy of potential risks for a project 10 • Risk breakdown structure • RACI • WBS • Triggers 0 of 30
16. Spelling is an expertise of this insructor 10 • True • False 0 of 30