1 / 16

Mini Quiz Prep for Test #2

Mini Quiz Prep for Test #2. MIS 592. 1. The __ ultimately decides if the project quality is acceptable. 10. Project team CEO Project Manager Customer. 0 of 30. 2. The __ is the portion of the approved total cost planned to be spent on an activity during a period. 10. AC EV RP PV.

shina
Télécharger la présentation

Mini Quiz Prep for Test #2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mini Quiz Prep for Test #2 MIS 592

  2. 1. The __ ultimately decides if the project quality is acceptable 10 • Project team • CEO • Project Manager • Customer 0 of 30

  3. 2. The __ is the portion of the approved total cost planned to be spent on an activity during a period 10 • AC • EV • RP • PV 0 of 30

  4. 3. The __ is an estimate of the value of physical work actually completed 10 • AC • EV • RP • PV 0 of 30

  5. 4. __ is the ability of a product or service to perform as expected under normal conditions 10 • Reliability • Performance • Maintainability • Functionality 0 of 30

  6. 5. Testing needs to be done only during the prototype and implementation stages 10 • True • False 0 of 30

  7. 6. Rough order of magnitude estimates are used: 10 • When no other estimates are available • In all cases • Early in a planning process when the project is initially being considered 0 of 30

  8. 7. Databases are a common tool for cost estimating, cost budgeting and cost control 10 • True • False 0 of 30

  9. 8. Monte Carlo simulations may be used to determine the number of lines of code in a project 10 • True • False 0 of 30

  10. 9. ___ use the actual costs of a previous, similar project as the basis for estimating the cost of the current project 10 • Actual estimates • Parametric estimates • Bottom up estimates • Analogous estimates 0 of 30

  11. 10. DMAIC would be associated with: 10 • Costing • Quality • Human Resources • Communication Plans 0 of 30

  12. 11. To assist in resource leveling one would: 10 • Go to Home Depot and purchase a level • Use a pareto chart • Use a trigger in a risk management plan • Use the critical path diagram looking for slack 0 of 30

  13. 12. A trigger refers to: 10 • An event in testing • An event in a WBS • An item in a gun • An event in risk planning 0 of 30

  14. 14. Cost and time monitoring involves: 10 • EV • PV • SV • All of the above • 1 and 2 • 2 and 3 • 1 and 3 0 of 30

  15. 15. A(n) ___ is a hierarchy of potential risks for a project 10 • Risk breakdown structure • RACI • WBS • Triggers 0 of 30

  16. 16. Spelling is an expertise of this insructor 10 • True • False 0 of 30

More Related