1 / 36

Contractor’s Orientation

Contractor’s Orientation. Behailu Demeke, West Region Directorate P/Director Ethiopian Roads Authority August 2011. Outline of the presentation. Introduction What you should do to succeed Risks in construction The contractor’s obligation Concluding remarks. 1. Introduction.

sinjin
Télécharger la présentation

Contractor’s Orientation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Contractor’s Orientation Behailu Demeke, West Region Directorate P/Director Ethiopian Roads Authority August 2011

  2. Outline of the presentation • Introduction • What you should do to succeed • Risks in construction • The contractor’s obligation • Concluding remarks

  3. 1. Introduction • Currently 27 contractor’s work with ERA • It is planned to increase this number to 100 by 2007 EFY • Why? • To develop the LCI • To create healthy competition • How? • With your participation • With ERA’s support

  4. Introduction, … Our Common Goals Safely • Finish the Project • As specified • On schedule • Within budget We understand contractor works to make reasonable profit in the process

  5. 2. What you should do to succeed • Plan • Organize • Control The Golden Rule of Construction Management

  6. 2.1 What you should do,Plan! • Physical Plan • Construction execution plan • Detailed schedule, clause 14.1 & 14.2 • Financial Plan • Cash flow clause 14.3

  7. 2.1.1 Clause 14 program • Critical path method with Logical link • Description of work method & arrangements • Period of construction for each activity, daily/monthly productivity rates • Equipment, labor and material arrangements & sources • Climatic conditions, subsurface conditions, custom process, LC & etc

  8. 2.1.1 Clause 14 program… Cont’ • The program should detail • Deadline for the provisions of engineer’s facility • Timeline for completion of contractor’s site facility • Time frame for the delivery of plant, equipment and material • Right of way and other land requirements • Temporary works arrangement • HIV alleviation programs, safety & environmental issues

  9. 2.2 What you should do,Organize! • Organizational Activities • Developing system • Organizational chart • Key positions & descriptions • Site operation procedures • Site facility • Issue control procedure • Mobilize & motivate field staff

  10. 2.2.1 Organizational activities • Appoint competent project management team • Timely mobilization of equipment, manpower and material (proper utilization of the mobilization advance) • Timely establishment at the site • Office, accommodation, laboratory, workshops etc • Put in place effective communication system • Recording system

  11. 2.2.1 … activities cont’ • Establish work procedures (mandatory to avoid rework) • Environmental management should be part of the work system/flow • Safety of workers & third party has to be an inbuilt element of the work method/procedure • Traffic management plan is mandatory

  12. 2.3 What you should do,Control! • Control activities • Quality – materials, products, • Time – measured against the schedule • Money – construction budget and cash-flow • Physical Progress and Productivity • Reporting – informs the output of the Controlling activity

  13. 2.3.1 Controlling the site activities • Make sure the work being done is of the required quality (regardless of the engineer’s checking and approval) • Make sure that the actual productivity for each activity is as planned or even better • Monitor the return on financial spending • Report is the most important tool to follow up your performance • Visit your sites regularly

  14. 3. Risks as to construction • Construction work is inherently a risky venture • Risk is the probability that an adverse event occurs during the construction period • Establish the probability of occurrence of the adverse events, Measure/estimate the potential impact and account it in your tender Risk can be managed, minimized, shared, transferred or accepted, but it cannot be ignored!

  15. 3. Risks … cont’ • Estimation and pricing of risk is very difficult (lack of database and documentation) • The condition of contract serves to allocate the risks and liabilities • The risks are usually allocated based on the fact that who is best suited to handle them • Contractor’s have to assess which risks they assume as per the contract and/or the law

  16. 4. The Contractor’s Obligation • Construction & completion within the time allowed • The use of material & workmanship as specified & instructed by the Engineer • Provision of securities, indemnities & insurances

  17. 4. The … Obligation cont’ • Supply of information and notices • Perform certain administrative & other functions These obligations are spread through time

  18. 4.1 Obligations during tendering • Inspecting the site & its surroundings • Inspect information available in connection with the site • Receive & interpret data on hydrological & subsurface conditions So far as is practicable, having regard to considerations of cost and time Sub-clause 11.1

  19. Obligations during tendering • Satisfied himself • The form & nature of the site, including the subsurface condition • The hydrologic & climatic conditions • The extent & nature of work & material necessary Sub-clause 11.1

  20. Obligations during tendering • Obtain necessary information as to risks, contingencies & all other circumstances which may influence or affect his tender • Based his tender on the data made available by the Employer & on his own inspection & examination • Satisfied himself as to the correctness & sufficiency of his tender (cl 12.1)

  21. Obligations during tendering • To agree on the general terms of the insurance (cl 25.1) • Arrangements for price adjustment should be reflected in the tender rate • Indices should relate to proposed source of supply

  22. 4.2 Obligations during Construction • Prior to commencement of the works • Provision of performance security (cl 10.1) • Program submission (cl 14.1) • Insurance evidence (cl 25.1) • Breakdown for lump sum items (cl 57.2)

  23. Obligations during Construction • Construction & completion of the works with duecare and diligence & within the time for completion (cl 8.1, 41.1) • Substantial completion (cl 48.1) • A stage that warrants issuance of DLC (62.1) • The contractor has to complete the works irrespective of any difficulties he may experience

  24. Obligations during Construction • Do anything necessary to complete the works • Incidental works when risks eventuate, (repair of damage, additional works etc) • Rate of progress should enable to meet the time for completion (cl 46.1)

  25. Obligations during Construction • Use of materials, plant and workmanship as specified and instructed • The GCC & COPA set the principles (the Specs give details)

  26. Obligations during Construction • Provision of securities, indemnities & insurances • Performance security • Care for the works and materials and plant for incorporation therein • The indemnity & insurance cover are listed in cl 20 to 25 (CAR, Workmen, third party, etc) • Compliance with statutes & regulations

  27. Obligations during Construction • Provision of securities, indemnities & insurances • Patent rights, design trademarks or names & other protected rights • Interference with traffic & adjoining property • Indemnity for use of in-route facilities

  28. Obligations during Construction • Supply of information, notices or alerts • Design related information • Program • Cash flow estimates • Geological & archeological finds • Details of labor and equipment returns • Particulars of EOT

  29. Obligations during Construction • Supply of information, notices or alerts • Emergency works • Varied works, to be executed under day-works • Contemporary records • Measurement • Use of provisional sums • Payment to nominated subcontractors • Monthly statements

  30. Obligations during Construction • Performance of certain administrative functions • Not to assign the contract, any obligation or benefit to others • Is responsible for the acts of sub-contractors • To afford reasonable opportunity to other contractors on site • Engagement of staff and labor (observing the law)

  31. Obligations during Construction • Performance of certain administrative functions • Making payments in some cases (temporary rows, reinforcing bridges along the route improving the roads, etc) • Making and keeping further copy of drawings (cl 6.1) • Assigning benefit to the employer in case of termination (cl 6.1)

  32. 4.3 Obligations after substantial completion • Site clearance cl 33.1 • Searching defects and remedying (cl 50.1) • Preparation and submission of statement at completion (cl 60.5) • Draft final statement and further information (cl 60.6) • Issuing discharge to the employer (cl 60.7)

  33. 5. Concluding remarks • You have to carefully plan, organize and control your work • You have to mobilize and commence work at the site ASAP • You have to monitor the progress and quality of the work

  34. Concluding remarks … cont’ • You should have a robust financial utilization and controlling system • You have to have a good supply chain management system • You have to take corrective measures through close follow up

  35. Concluding remarks … cont’ • This is a one time opportunity • If you succeed a lot more is coming for you • If you fail in this opportunity you may jeopardize the opportunity of others • This projects will be counted as an experience for you when you complete 70% of the work • You will be eligible for another opportunity after you progress 50%

  36. Thank you and Good Luck

More Related