An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CRR Offers in the Day-Ahead Market TPTF – August 28, 2007Presented by Mark Patterson

  2. CRR offers to DAM CRR Offers and Validations CRR DAM Clearing and Settlement An example Contents TPTF – CRR Offers in DAM

  3. Who can offer their CRRs into the Day-Ahead market? Only NOIEs, through their QSE Protocol ref: 4.3 (1) (b) What products can be offered into DAM? PTP Options PTP Options with Refund Products acquired through Allocation or Auction may be offered Protocol ref: 4.4.5 (2) & (3) Once paid for, PCRR allocations of Capacity type, are not differentiated from other PTP Obligations or PTP Options awarded via Auction. What is the meaning of a CRR offer to DAM? If the DAM LMP is greater than or equal to the Minimum Reservation Price of a CRR offer, the CRR Account Holder will be paid based on DAM LMPs; If the DAM LMP is less than the price offered, the offer is not cleared and the CRR Account Holder will be paid based on RT LMPs. If no offer is made, the CRR Account Holder will be settled at DAM LMPs CRR offers TPTF – CRR Offers in DAM

  4. CRR Offers shall include the following information: The name of the QSE submitting The name of the CRR Account Holder who owns the CRRs CRR ID – Unique identifier provided by the CRR system at the conclusion of each allocation and auction Minimum Reservation Price ($/MWh) Quantity (MW) … Validation rules If the QSE and CRR Account Holders are separate entities, the relationship between the two must be formalized. The CRR Account Holder is identified as a NOIE The CRR ID will be validated against the CRR Ownership information provided on a daily basis to the MMS-DAM by the CRR system … Validation of CRR Offers TPTF – CRR Offers in DAM

  5. After DAM execution, If a CRR offer is partially cleared in DAM, the cleared quantity will be settled using DAM LMPs Not cleared CRR offers will be settled by Real-Time LMP Two notes: If a NOIE wants declare its CRR PTP options to be settled in Real-Time, this NOIE shall submit CRR offers to DAM and indicate the Minimum Reservation Price; If no Minimum Reservation Price is specified, $2000/MWh will be assigned as a default. Settlement of DAM Results TPTF – CRR Offers in DAM

  6. An Example NOIE: ee QSE: qqSource/Sink settlement points: A/B CRR settlement: • “CRRID-1” • 100 MW will be settled by DAM LMP • “CRRID-2” • 40 MW not offered part will be settled by DAM LMP • 60 MW not cleared part by Dam will be settled by RT LMP TPTF – CRR Offers in DAM

  7. Joe’s NOIE CRR Account Holder, owns 100 MW PTP Option between PointA and PointB (CRRID #1) Joe’s NOIE QSE offers 100 MW of CRRID #1 into the DAM, with a minimum reservation price of $30 /MW After DAM clearing, the price difference between PointA and PointB is $40 / MW All 100 MWs of the offered CRR clears at DAM LMPs Joe’s NOIE CRR Account Holder will receive $40 /MW for all 100 MW Example 1 TPTF – CRR Offers in DAM

  8. Joe’s NOIE CRR Account Holder, owns 100 MW PTP Option between PointA and PointB (CRRID #1) Joe’s NOIE QSE offers 60 MW of CRRID #1 into the DAM, with a minimum reservation price of $30 /MW After DAM clearing, the price difference between PointA and PointB is $40 / MW 60 MWs of the offered CRR clears at DAM LMPs 40 MWs of the non-offered CRR is paid based on DAM LMPs Joe’s NOIE CRR Account Holder will receive $40 /MW for all 100 MW Example 2 TPTF – CRR Offers in DAM

  9. Joe’s NOIE CRR Account Holder, owns 100 MW PTP Option between PointA and PointB (CRRID #1) Joe’s NOIE QSE offers 60 MW of CRRID #1 into the DAM, with a minimum reservation price of $80 /MW After DAM clearing, the price difference between PointA and PointB is $40 / MW After RT clearing the price difference between PointA and PointB is $90 / MW 40 MWs of the non-offered CRR is paid based on DAM LMPs 60 MWs of the offered CRR is not cleared, and will flow to RT and be paid based on RT LMPs Joe’s NOIE CRR Account Holder will receive $40 /MW for 40 MW and $90 / MW for 60 MW Example 3 TPTF – CRR Offers in DAM

  10. Joe’s NOIE CRR Account Holder, owns 100 MW PTP Option between PointA and PointB (CRRID #1) Joe’s NOIE QSE offers 100 MW of CRRID #1 into the DAM, but does not specify a minimum reservation price After DAM clearing, the price difference between PointA and PointB is $40 / MW After RT clearing the price difference between PointA and PointB is $90 / MW 100 MWs of the offered CRR is not cleared because the default price is $2000 / MW, and will flow to RT and be paid based on RT LMPs Joe’s NOIE CRR Account Holder will receive $90 /MW for 100 MW Example 4 TPTF – CRR Offers in DAM

  11. Tom’s NOIE CRR Account Holder, owns 100 MW PTP Option between PointA and PointB (CRRID #1) Bill’s QSE is authorized to represent Tom’s NOIE CRR Account Holder Bill’s QSE offers 100 MW of CRRID #1 into the DAM, with a minimum reservation price of $30 /MW After DAM clearing, the price difference between PointA and PointB is $40 / MW All 100 MWs of the offered CRR clears at DAM LMPs Bill’s CRR Account Holder will receive $40 /MW for all 100 MW Example 5 TPTF – CRR Offers in DAM

  12. DAM Questions? TPTF – CRR Offers in DAM