470 likes | 480 Vues
Test your knowledge of Monitoring & Controlling in project management! Win up to $1 million by answering questions and earn a spot on the millionaire scoreboard.
E N D
Who Wants To Be A PMP? Montoring & Controlling
MILLIONAIRE SCOREBOARD $16,000 $1 MILLION $8,000 $4,000 $500,000 $2,000 $250,000 $1,000 $125,000 $500 $64,000 $300 $32,000 $200 Click the $ for questions $100
All of the following occur during Monitoring & Controlling, except: A:Quality Assurance is performed B:Execution of the project is controlled C:Preventive & corrective actions are recommended D:Scope, Schedule, Cost, & Quality are controlled Click on the letter of the correct answer $100 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $100 Click on the money bag to return to the scoreboard
Which of the following is an output of the Monitor and Control Project Work process? A:Cost forecasts B:Work performance reports C:Validated changes D:Schedule forecasts Click on the letter of the correct answer $200 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $200 Click on the money bag to return to the scoreboard
All of the following relate to a Work Authorization System, except: A:May take the form of a WBS dictionary B:Helps control gold plating C:Essentially the same as a Responsibility Assignment Matrix D:Can help with properly sequencing the activities Click on the letter of the correct answer $300 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $300 Click on the money bag to return to the scoreboard
All of the following relate to Earned Value, except: A: Most commonly used method for performance measurement B:Use to objectively measure project performance C:Budgeted cost of work performed D:Finding a cheaper, faster, and better way to increase value Click on the letter of the correct answer $500 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $500 Click on the money bag to return to the scoreboard
All of the following Earned Value formulas are correct, except: A:SV = EV - PV B:CPI = EV / SV C:SPI = EV / PV D:CV = EV - AC Click on the letter of the correct answer $1,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $1,000 Click on the money bag to return to the scoreboard
All of the following relate to the Quality Control process, except: A:Following ISO and other standards B:Verified deliverables C:Quality control charts D:Inspection Click on the letter of the correct answer $2,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $2,000 Click on the money bag to return to the scoreboard
All of the following are true concerning Monitoring and Controlling, except: A:Variance analysis is performed B:Corrective action is taken C:Risks are monitored/controlled as per the risk register D:Deliverables are verified, validated, and accepted Click on the letter of the correct answer $4,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $4,000 Click on the money bag to return to the scoreboard
All of the following are inputs to the Control Stakeholder Engagement Process, except: A:Work performance information B:Issue log C:Project Management Plan D:Work performance Data Click on the letter of the correct answer $8,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $8,000 Click on the money bag to return to the scoreboard
Quality Control tools & techniques include all of the following, except: A:Cause-and-effect diagrams & scatter diagrams B:Pareto charts, histograms, & checksheets C:Pareto charts & earned value analysis charts D:Process flowcharts & quality control charts Click on the letter of the correct answer $16,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $16,000 Click on the money bag to return to the scoreboard
All of the following relate to Quality Control Charts, except: A:Mean, assignable cause, & specification limits B:Rule of seven C:Upper and lower control limits D:Shows the pattern of relationship between two variables Click on the letter of the correct answer $32,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $32,000 Click on the money bag to return to the scoreboard
After controlling scope, schedule, cost, and quality, you should: A:Validate scope (accepted deliverables) B:Perform Integrated Change Control C:Control procurements D:Take preventive & corrective action Click on the letter of the correct answer $64,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $64,000 Click on the money bag to return to the scoreboard
Reviewing, approving, or denying corrective and/or preventive actions refers to: A:Scope control B:Schedule control C:Integrated change control D:Cost control Click on the letter of the correct answer $125,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $125,000 Click on the money bag to return to the scoreboard
All of the following are true of Integrated Change Control, except: A:Outputs are approved change requests B:Inputs include change requests C:Tools and techniques include change control tols, meetings & expert judgment D:Compares planned to actual Click on the letter of the correct answer $250,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $250,000 Click on the money bag to return to the scoreboard
All of the following relate to the Risk Control Process, except: A:Contingency and fallback measures are taken as per the risk register B:Risk Register is developed and used for workarounds C:Tools and Techniques include risk reassessment, risk audits, & reserve analysis D:Technical performance measurements are made Click on the letter of the correct answer $500,000 Question
INCORRECT! TRY AGAIN!
Correct! SCORE $500,000 Click on the money bag to return to the scoreboard
All of the following are Tools and Techniques for the Control Procurements Process, except: A:Contract change control system & procurement performance reviews B:Inspections and audits & performance reporting C:Source selection criteria, payment systems, & records management system D:Payment systems,claims administration, & records management system Click on the letter of the correct answer $1 Million Question
INCORRECT! TRY AGAIN!
Correct! SCORE $1 MILLION