An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. September 11, 2002 ALEOC Meeting Midland, Texas 1

    2. September 11, 2002 ALEOC Meeting Midland, Texas 2 Test Well Facilities The Texas Tech University Test Well Facilities is currently completing the initial procurement stage to complete the well bore portion of the facilities. Donations have been secured for the following items. Two-Phase separator and Heater Treater from NATCO GROUP. Lufkin C456D-305-144 Pumping Unit with Pump off Controller.

    3. September 11, 2002 ALEOC Meeting Midland, Texas 3 Donated Equipment Specifications Lufkin Pumping Unit C456D-305-144 Pump off Controller Contact: Mr. Cecil L. Hunt Jr. Lufkin Industries, Inc. Oilfield Division P. O. Box 849 Lufkin, Texas 75902-0849 Phone:(936) 637-5667 Fax: (936) 637-5306 Email: chunt@lufkin.com

    4. September 11, 2002 ALEOC Meeting Midland, Texas 4 Lufkin Pumping Unit Pad Red Raider No. 1

    5. September 11, 2002 ALEOC Meeting Midland, Texas 5 Donated Equipment Specifications NATCO GROUP Two Phase Separator 16 in x 5 ft x 1440 psi. 800 bbls of Fluid per day Contact Information: NATCO ODESSA 6609 West 16th Street Odessa, Texas 79763 Phone: (915) 530-3600 Fax: (915) 530-3636

    6. September 11, 2002 ALEOC Meeting Midland, Texas 6 Donated Equipment Specifications NATCO GROUP Heater Treater 4 ft x 20 in. x 50 psi 860 bbls of Fluid per day Contact Information: NATCO ODESSA 6609 West 16th Street Odessa, Texas 79763 Phone: (915) 530-3600 Fax: (915) 530-3636

    7. September 11, 2002 ALEOC Meeting Midland, Texas 7 Red Raider No. 1 Equipment (Awaiting Delivery) Stock Tanks (Permian Tank Company, Odessa, Texas) Three (3) 12ft x 25 ft, API 12F Type B Cone bottom, tanks with inch plate and 1 in roll lines. OCTG Pipe (Tubing) Five Star Pipe (Odessa, Texas) 4150 ft, 2-7/8 inch, J-55, 6.5 #/ft, R2, SCC Cont. Casing (Houston, Texas) 1500 ft, 3-1/2 inch, J-55, 9.30 #/ft, R2, SCC

    8. September 11, 2002 ALEOC Meeting Midland, Texas 8 Toshiba Oil Field Motor and Cutler Hammer Panel

    9. September 11, 2002 ALEOC Meeting Midland, Texas 9 Red Raider No. 1 Equipment (Toshiba Motor Name Plate Specs.) Toshiba Oil Well Pump 3-Phase Induction Motor NAME PLATE SPECIFICATIONS Model No.: F0506DKF3PDP02 ENCL.: DP HP: 50 POLES: 6 INC. CLASS: F NEMA DES.: - NEMA CODE: G S.F.: 1.00 TYPE: TIKS FORM: DBK1 FR#: 365T DUTY: CONT. MAX. AMB.: 40 C VOLTS: 230/460/796 HZ 60 RPM: 1120 AMP: 120/60/34.5 SER. NO.: 001202523 BRG NO.: L.S. 6314C3 O.S. 6313C3

    10. September 11, 2002 ALEOC Meeting Midland, Texas 10 Seating Nipples

    11. September 11, 2002 ALEOC Meeting Midland, Texas 11 Pipe Racks Red Raider No. 1

    12. September 11, 2002 ALEOC Meeting Midland, Texas 12 Test Well Web Page (1)

    13. September 11, 2002 ALEOC Meeting Midland, Texas 13 Test Well Web Page (2)

    14. September 11, 2002 ALEOC Meeting Midland, Texas 14 Test Well Facilities Schedule We are currently waiting on the split hanger for the tubing head. We hope to have the Lufkin Unit set by Oct. 1, 2002. We will move tubing to the racks after the pumping unit is set. The Separation facilities and stock tanks will be ready by the end of Sept. 2002. We hope to have the puping unit component ready for testing by Dec. 2002.