1 / 4

Progress Update on West Entry Demolition and Construction Activities (05/07/12 – 05/13/12)

This week's report covers significant milestones achieved during the demolition and construction phases at the site. The West Entry demolition is complete, and work on drilled piers and footers has begun. The 1927 wing demolition is nearing completion, and phase 1 tasks, including removal of air handling units and shutdown of the main electrical panel, have been accomplished. Continued efforts are focused on MEP installations in the 1927 wing, preparation for floor cuts, and wall work to facilitate relocations for Taco Bell and C-Store.

sorley
Télécharger la présentation

Progress Update on West Entry Demolition and Construction Activities (05/07/12 – 05/13/12)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

  2. 05/07/12 – 5/13/12 Demolition at 1927 wing nearing completion

  3. 05/07/12 – 5/13/12 Phase 1 Air Handler Units removed

  4. 05/07/12 – 5/13/12 • Field Measured Phase 3 Rotunda • Completed Electrical Shutdown to relocate Main Electrical Panel During the break… • Exterior • Complete drilled piers • Form and Pour Footings at South Side • Interior • Continue with MEP in 1927 Wing • Prep for floor cut at main electrical room • Wall off existing area at Spartan Grille to facilitate Taco Bell/C-Store Relocation NEXT WEEK LOOK AHEAD Phase 3 Rotunda Field Measurement and Verification

More Related