An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DNAPL Recovery System July 2010 Progress Meeting McCormick & Baxter Superfund Site Portland, Oregon

  2. DNAPL Recovery System • Objectives • Previous Efforts at Recovery • Proposed Effort • Investigation • Design • Installation • Start-up • Schedule • Shallow contour maps • Hydrographs • Gradients

  3. ROD DNAPL RAOs • “Removing mobile NAPL to the extent practicable to reduce the continuing source of groundwater contamination and potential for discharge to the Willamette River.” • How do you measure extent practicable?

  4. End-Points for Recovery • Recovery of NAPL system is reduced to an established value (could be based on the asymptote or NAPL recovery decline method) • Concentrations of dissolved phase downgradient of the system are below MCLs • NAPL transmissivity is reduced to a given value • NAPL saturations are reduced to levels below residual saturations as measured by a given method (such as from cores, or product levels in wells) • NAPL chemistry has changed rendering it less mobile or less toxic • Containment is in place (works for barrier wall)

  5. Objectives of NAPL System • Recover DNAPL outside the barrier wall such that end-point measurements can be evaluated while being protective of the river and the current remedy (specifically the sediment cap). • Define “extent practicable” for NAPL removal through end-point technology.

  6. Historic NAPL Recovery • 1994: • A pilot-scale wastewater treatment • system was installed • Wells in the FWDA were used for • pure-phase NAPL extraction • Field data collected between 1992 and • 1994 indicated that weekly pumping yielded • as much NAPL as automated pumping. • Automated system was discontinued • because it required constant monitoring • 2004 - Current: • Select wells with NAPL are manually • extracted based on thickness. • 1991: • DEQ expanded recovery • efforts by using additional • monitoring wells • 2007: • A XITECH skimmer pump was installed • in EW-23s to automate LNAPL recovery. • The system was unsuccessful. • 1993: • Extraction wells EW-3 • through EW-10 were installed • NAPL extraction was automated • in selected wells in the TFA and FWDA • Manual extraction efforts continued in some wells • Interceptor trench was installed • Pilot testing was carried out on wastewater • treatment, total fluids extraction, and pure-phase extraction • 1998: • The treatment system in the TFA was • modified to that used in the FWDA. • 1999 & 2000: • The FWDA and TFA NAPL extraction • systems were shut down in September 2000 • NAPL extraction was continued manually

  7. Data Gap Investigation • Review previous coring information (primarily the 2004 investigation) • Advance up to 8 additional cores to define locations for extraction wells • Conduct product mobility testing on select cores for:1) free product mobility, 2) grain size, 3) Amott and USBM Wettability, and NAPL and water fluid properties (interfacial tension, density, and viscosity). • Submit recommendation for Extraction Wells (up to 3) and DNAPL Recovery System

  8. DNAPL Recovery System • System Design (extraction and separation) • Focus on ability to re-cycle water into barrier wall, recognize historic NAPL recovery failures, use energy efficient technology such as solar panels, and protection of river and sediment cap. • System Installation • System Start-up

  9. Schedule (Outdated) • Draft Detailed Data Gap Investigation Work Plan – beginning of June 2010 • Final Detailed Data Gap Investigation Work Plan – end of June 2010 • Procurement of Drilling Contractors and Laboratories for the specialized NAPL properties – July 2010 • Field Work to occur between August and October 2010. • Draft Data Gap Results and Detailed DNAPL Recovery System Design – January 2011. • Final Data Gap Results and Detailed DNAPL Recovery System Design – March 2011. • Procurement of Contractors for System Installation – April-May 2011. • Installation of system and start-up– July 2011