1 / 21

Difference Between Unified Processes ( RUP,OpenUP,OUM )

Difference Between Unified Processes ( RUP,OpenUP,OUM ). Covered By: Harkul R. Bhatia MBA(SDM). Brainstorming Of. RUP (Rational Unified Process) is a framework of Rational Corporation, a division of IBM since 2003.

sunee
Télécharger la présentation

Difference Between Unified Processes ( RUP,OpenUP,OUM )

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Difference Between Unified Processes(RUP,OpenUP,OUM) Covered By: Harkul R. Bhatia MBA(SDM)

  2. Brainstorming Of RUP (Rational Unified Process) is a framework of Rational Corporation, a division of IBM since 2003. Open UP (Open Unified Process) is a part of eclipse process framework, an open process framework developed under eclipse Foundation. OUM (Oracle Unified Method) is a framework developed by Oracle.

  3. RATIONAL Unified Process • Project failure is caused by a combination of several symptoms, though each project fails in a unique way. The outcome of their study was a system of software best practices they named the Rational Unified Process. • The Process was designed with the same techniques the team used to design software; it has an underlying object-oriented model, using Unified Modeling Language (UML).

  4. RATIONAL Unified Process..cntd. RUP is based on a set of building blocks, or content elements, describing what is to be produced, the necessary skills required and the step-by-step explanation describing how specific development goals are achieved. The main building blocks, or content elements, are the following: Roles (who) –A Role defines a set of related skills, competences, and responsibilities. Work Products (what) – A Work Product represents something resulting from a task, including all the documents and models produced while working through the process. Tasks (how) – A Task describes a unit of work assigned to a Role that provides a meaningful result.

  5. RATIONAL Unified Process..cntd. • RUP contains four Phases : • Inception phase • Elaboration phase • Construction phase • Transition phase

  6. RATIONAL Unified Process..cntd. • Inception phase In this phase the business case which includes business context, success factors (expected revenue, market recognition, etc), and financial forecast is established. To complement the business case, a basic use case model, project plan, initial risk assessment and project description (the core project requirements, constraints and key features) are generated.

  7. RATIONAL Unified Process..cntd. After these are completed, the project is checked against the following criteria: • Stakeholder concurrence on scope definition and cost/schedule estimates. • Requirements understanding as evidenced by the fidelity of the primary use cases. • Credibility of the cost/schedule estimates, priorities, risks, and development process. • Depth and breadth of any architectural prototype that was developed. • Establishing a baseline by which to compare actual expenditures versus planned expenditures.

  8. RATIONAL Unified Process..cntd. Elaboration phase The primary objective is to mitigate the key risk items identified by analysis up to the end of this phase. The elaboration phase is where the project starts to take shape. In this phase the problem domain analysis is made and the architecture of the project gets its basic form.

  9. RATIONAL Unified Process..cntd. This phase must pass the Lifecycle Architecture Milestone by the following criteria: • A use-case model in which the use-cases and the actors have been identified and most of the use-case descriptions are developed. The use-case model should be 80% complete. • A description of the software architecture in a software system development process. • An executable architecture that realizes architecturally significant use cases. • Business case and risk list which are revised. • A development plan for the overall project. • Prototypes that demonstrably mitigate each identified technical risk.

  10. RATIONAL Unified Process..cntd. • Construction phase The primary objective is to build the software system. In this phase, the main focus goes to the development of components and other features of the system being designed. This is the phase when the bulk of the coding takes place. In larger projects, several construction iterations may be developed in an effort to divide the use cases into manageable segments that produce demonstrable prototypes. This phase produces the first external release of the software. Its conclusion is marked by the Initial Operational Capability Milestone.

  11. RATIONAL Unified Process..cntd. • Transition phase The primary objective is to 'transition' the system from the development into production, making it available to and understood by the end user. The activities of this phase include training of the end users and maintainers and beta testing of the system to validate it against the end users' expectations. The product is also checked against the quality level set in the Inception phase. If all objectives are met, the Product Release Milestone is reached and the development cycle ends.

  12. Oracle Unified Method Oracle Unified Method (OUM) is a iterative and incremental software development process framework developed by Oracle to achieve the vision of supporting the successful implementation of every Oracle product – applications, middleware, and database. The Oracle Unified Method is one of many variations of the generic Unified Process. The current release, OUM 4.3, supports the complete range of technology projects including deep support for Service Oriented Architecture (SOA), Enterprise Integration, Custom Software, Identity Management (IdM), and Governance, Risk and Compliance (GRC).

  13. Open Unified Process The Open Unified Process (Open UP) is a part of the Eclipse Process Framework (EPF), an open source process framework developed within the Eclipse Foundation. It provides best practices from a variety of software development thought leaders and the broader software development community that cover a diverse set of perspectives and development needs. Open UP preserves the essential characteristics of RUP / Unified Process, which includes iterative development, use cases and scenarios driving development, risk management, and architecture-centric approach.

  14. Open Unified Process…cntd. The most agile and lightweight form of Open UP, Open UP/Basic, targets smaller and co-located teams interested in agile and iterative development. Small projects constitute teams of 3 to 6 people and involve 3 to 6 months of development effort.

  15. Open Unified Process…cntd. • Inception Phase Iteration • Initiate Project • Plan and Manage Iteration • Identify and Refine Requirements • Agree on Technical Approach • Objective of Inception phase • Understand what to build • Identify key system functionality • Determine at least one possible solution • Understand the cost, schedule and risks associated with the project

  16. Open Unified Process…cntd. • Elaboration Phase Iteration • Plan and Manage Iteration • Identify and Refine Requirements • Define the Architecture • Develop Solution Increment • Test Solution • Ongoing Tasks • Objective of Elaboration phase • Get a more detailed understanding of the requirements • Design, implement, validate, and baseline an Architecture • Mitigate essential risks, and produce accurate schedule and cost estimates

  17. Open Unified Process…cntd. • Objective of Elaboration phase • Get a more detailed understanding of the requirements • Design, implement, validate, and baseline an Architecture • Mitigate essential risks, and produce accurate schedule and cost estimates

  18. Open Unified Process…cntd. • Construction Phase Iteration • Plan and Manage Iteration • Identify and Refine Requirements • Develop Solution Increment • Test Solution • Ongoing Tasks • Objective of Construction phase • Iteratively develop a complete product that is ready to transition to its user community • Minimize development costs and achieve some degree of parallelism

  19. Open Unified Process…cntd. • Transition Phase Iteration • Plan and Manage Iteration • Develop Solution Increment • Test Solution • Ongoing Tasks • Objective of Transition phase • Beta test to validate that user expectations are met • Achieve stakeholder concurrence that deployment is complete

  20. Open Unified Process…cntd.

  21. Reference http://www.eclipse.org/epf/general/OpenUP.pdf http://www.numbersix.com/news/n6articles/openUp.html http://www.oracle.com/consulting/library/briefs/oracle-unified-method.pdf http://en.wikipedia.org/wiki/IBM_Rational_Unified_Process http://en.wikipedia.org/wiki/Oracle_Unified_Method

More Related