1 / 20

Project Management Tools

Project Management Tools. Stephanie Schmit June 24, 2013 Source: Project Engineering ESD.062 / Oliver de Weck. Methods and Tools you will learn. Work breakdown structure Task List Scheduling and Gantt Charts: Critical Path Method. Tasks are the building blocks of projects.

tamma
Télécharger la présentation

Project Management Tools

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management Tools Stephanie Schmit June 24, 2013 Source: Project Engineering ESD.062 / Oliver de Weck

  2. Methods and Tools you will learn • Work breakdown structure • Task List • Scheduling and Gantt Charts: Critical Path Method Tasks are the building blocks of projects Project = set of related tasks

  3. Work Breakdown Structure (WBS) • Used to create the task (job) list • Tree-decomposition of project tasks • WBS identifies “terminal elements” • The key starting point for project planning • Required by contracts as part of the SOW • Can be activity-oriented or deliverable- oriented • Use “sticky-notes” method early on • Carl L. Pritchard. Nuts and Bolts Series 1: How to Build a Work Breakdown Structure. ISBN 1890367125 Job X Job B Job A Job G

  4. Example Work Breakdown Structure HumLog DC Project 3 Staffing 2 Contracting 5 Commissioning 1 Planning 4 Construction 2.1 Government Approval 2.2 Request for Proposal 2.3 Evaluate Proposals 2.4 Select Main Contractor 2.5 Finalize Contract 1.1 Location Analysis 1.2 Capacity Modeling 1.3 Transportation Analysis 4.1 Site Preparation 4.2 Dig and Pour Foundation 4.3 Erect Main Structure 4.4 Install Building Systems 4.5 Install Security Systems … 3.1 Staffing for Operations 3.2 Staff Training And Instruction 5.1 Stock Up Initial Inventory 5.2 Commissioning And Test 5.3 Final Acceptance IOC

  5. Discussion Point • Why is it difficult to come up with a good WBS (task list, task structure) in a complex project? • Not all tasks known ahead of time if completely new product/system • Others…?

  6. WBS Guidelines • No more than 100-200 terminal elements, if more  use subprojects • Can be up to 3-4 Levels deep • Not more than 5-9 jobs at one level • Human cognitive “bandwidth” only 3 bits=23=8 • Short term memory for most people 5-9 items • Poorer planning if “too-fine grained” – dilution of attention • The more tasks there are, the more intricate dependencies there will be to keep track of • Jobs should be of similar size/complexity • Manageable chunks  sense of progress • Level of graininess  very difficult to answer

  7. Task List • List all tasks in a table with • Identifying symbol (tag, ID number) • Task description • Immediate prerequisite jobs (predecessors) • Expected task duration • Arrange jobs in “technological order” • No job appears in the list until all its predecessors have been listed • Iterations are NOT allowed  “cycle error” • Job a precedes b precedes c precedes a

  8. Task List – HumLog DC Project

  9. today completion actual planned D Gantt Charts • Attributed to Henry Gantt – most popular PM tool (80%) • Used to plan big shipbuilding projects (cargo ships WWI) • Graphical way of showing task durations, project schedule • Does not explicitly show relationships between tasks • Limited use for project tracking • Easy to understand calendar Gantt Chart Builder System (Excel) 1.6 milestone tasks

  10. CPM Assumptions • Project consists of a collection of well defined tasks (jobs) • Project ends when all jobs completed • Jobs may be started and stopped independently of each other within a given sequence (no “continuous-flow” processes) • Jobs are ordered  “technological sequence”

  11. Critical Path • CP is the “bottleneck route” • Shortening or lengthening tasks on the critical path directly affects project finish • Duration of “non-critical” tasks is irrelevant • “Crashing” all jobs is ineffective, focus on the few % of jobs that are on the CP • “Crashing” tasks can shift the CP to a different task • Shortening tasks – technical and economical challenge • How can it be done? • Previously non-critical tasks can become critical • Lengthening of non-critical tasks can also shift the critical path

  12. Discussion Point • What is the usefulness of knowing the Critical Path in a project? • Tells which task to shorten to finish project earlier. • Others …?

  13. Latest Start and Finish Times • Set target finish time for project: T >= F • Usually target is a specific calendar date, e.g. October 1, 2010 • When is the latest date the project can be started? • Late Finish (LF) - latest time a job can be finished, without delaying the project beyond its target time (T) • Late Start: LS = LF-t

  14. Slack • Some tasks have ES=LS --> no slack • Total Slack of a task TS=LS-ES • Maximum amount of time a task may be delayed beyond its early start without delaying project completion • Slack time is precious … managerial freedom, don’t squander it unnecessarily • e.g. resource, work load smoothing • When T=F then all critical tasks have TS=0 • At least one path from Start->Finish with critical jobs only • When T>F, then all critical jobs have TS=T-F

  15. Example Gantt Chart Deadline 15 days away Build part A (3 days) Assemble part AB (5 days) Build part B (2 days) Finish (2 days) Build part C (6 days) time now Goal: Complete big project by deadline!

  16. Example Gantt Chart Deadline 15 days away Build part A (3 days) Assemble part AB (5 days) Build part B (2 days) Finish (2 days) Critical Path = 10 Float time = 5 Build part C (6 days) time now Goal: Complete big project by deadline!

  17. Example Gantt Chart Finished Critical Path Build part A (3 days) Assemble part AB (5 days) Deadline Now 8 days away Critical Path = 8 days Float time = 0 days Build part B (2 days) Finish (2 days) Build part C (6 days) time now No more float time! 7 days later…

  18. Main CPM Errors that people make • Estimated job times are wrong • Predecessor relationships may contain cycles  “cycle error” • List of prerequisites contains more than the immediate predecessors, e.g. 12, 23 and 1,23 • Overlooked some predecessor relationships • Some predecessor relationships may be listed that are spurious • and …. Some tasks/jobs may be missing !!!

  19. Summary • Work breakdown structure • Task List • Scheduling and Gantt Charts: Critical Path Method

More Related