1 / 18

LHC UPS Systems and Configurations: Changes during the LS1

LHC UPS Systems and Configurations: Changes during the LS1. LHC Beam Operation Committee 11 February 2014. V. Chareyre / EN-EL. 1. EDMS No. 1354977. 11/02/2014. LHC Beam Operation Committee Changes in UPS Configurations . Outline UPS systems and replacement project during LS1

tarika
Télécharger la présentation

LHC UPS Systems and Configurations: Changes during the LS1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC UPS Systems and Configurations: Changes during the LS1 LHC Beam Operation Committee 11 February 2014 V. Chareyre / EN-EL 1 EDMS No.1354977 11/02/2014

  2. LHC Beam Operation Committee Changes in UPS Configurations Outline • UPS systems and replacement project during LS1 • New configuration in the alcoves and LHC odd points • New configuration in LHC even points • New powering interlock rules • EMC considerations • Conclusion 2 EDMS No.1354977 11/02/2014

  3. LHC Beam Operation Committee Changes in UPS Configurations UPS Systems for the LHC • Critical equipment around the LHC powered by Uninterruptible Power Supply (UPS) systems • QPS (Quench Protection System), Beam Dump System, Beam Loss Monitor, etc.  Machine Protection • Cryogenics and vacuum control systems, power converters auxiliary circuits, etc.  Machine Availability • UPS principle  Continues to provide power to critical loadswhenever the input power fails for the time given by the backup battery • Nominal conditions:load powered via the double conversion path • Input source failure:the load remains supplied by the inverter using the battery stored energy • Load automatically transferred to the bypass line in case of: • Internal UPS failure • End of battery autonomy (requires bypass AC source available) • Short-circuit or overload on the downstream distribution (unlikely) • Fully automatic, load transfers < 1 ms 3 EDMS No.1354977 11/02/2014

  4. LHC Beam Operation Committee Changes in UPS Configurations LHC UPS Systems Replacement Project • Replacement of the existing APC Silcon UPS systems during the LS1(see EDMS 1151991) • Project motivations: • Improve the reliability • Decrease the failure rate • Minimize LHC run time losses • Change of UPS system topology: come back to the conventional double conversion UPS topology (with output isolation transformer) Double Conversion Delta Conversion 4 EDMS No.1354977 11/02/2014

  5. LHC Beam Operation Committee Changes in UPS Configurations Basic Requirement for the QPS • Basic requirement for a safe powering: 2 independent power paths and protected by upstream UPS systems • So-called F3 and F4 power lines distributed all along the tunnel • QPS redundant equipment connected to F4 5 EDMS No.1354977 11/02/2014

  6. LHC Beam Operation Committee Changes in UPS Configurations UPS Configurations before the LS1: Alcoves (REs) and Odd Points • Basic requirement: 2 independent power paths and protected by upstream UPS systems • No link between both UPS units • UPSs interfaced with the Powering Interlock Controller (PIC): Magnet powering stopped when loosing one UPS Output UPS power protected 6 EDMS No.1354977 11/02/2014

  7. LHC Beam Operation Committee Changes in UPS Configurations New UPS Configurations in the Alcoves (REs) and Odd Points • 3rd UPS (UPS backup) poweringthe bypass of both UPS F3 and UPS F4 = Stand-by redundancy • ‘Natural’ redundancy:no communication busbetween the 3 UPS units Distribution Unchanged Output UPS power protected 7 EDMS No.1354977 11/02/2014

  8. LHC Beam Operation Committee Changes in UPS Configurations Tolerance to the First Failure • Example: UPS F3 internal failure • UPS F3 transfers to bypass instantaneously • UPS backup takes over the F3 load • 2 power paths still protected • After a failure, we come back tothe same situation as today(but with conventional UPS systems!) • Failure of a second UPS in the same zone will stop the magnet powering (PIC triggered) Output UPS power protectedOutput UPS power NOT protected 8 EDMS No.1354977 11/02/2014

  9. LHC Beam Operation Committee Changes in UPS Configurations UPS Configurations in LHC Even Points (Before 2009) • 2 parallel-redundant UPS systems in: • UA (IP left side) • US • UA (IP right side) 9 EDMS No.1354977 11/02/2014

  10. LHC Beam Operation Committee Changes in UPS Configurations UPS Configurations in LHC Even Points: before LS1 • Redundant QPS equipment powered from the UPS system located in the adjacent zone • F3 and F4 lines always powered from 2 different redundant UPS configurations (one in US, one in UA) • Allowed to preserve parallel-redundant UPS systems in UAs and USs • Was already tolerant to the first UPS failure (in each zone) 10 EDMS No.1354977 11/02/2014

  11. LHC Beam Operation Committee Changes in UPS Configurations New UPS Configurations in LHC Even Points • Distribution remains unchanged • Standby redundancy applied in UAs and USs • F3 and F4 lines still powered from 2 different redundant UPS configurations (one in US, one in UA) 11 EDMS No.1354977 11/02/2014

  12. LHC Beam Operation Committee Changes in UPS Configurations Tolerance to the First Failure (in each Zone) • Example: failure of the first UPS in UA • Transfers to bypass instantaneously • UPS backup takes over full load in UA • Redundant power paths still protected • Failure of one UPS in the adjacent zone (US in this case) is allowed • Failure of 2 UPS units in the same zone will stop the magnet powering (PIC triggered) 12 EDMS No.1354977 11/02/2014

  13. LHC Beam Operation Committee Changes in UPS Configurations New Powering Interlock Rules • One single UPS failure = 2 power paths still protected = No PIC triggered • New rules: • Magnet powering can continue upon one single UPS failure • Machine can start with 2 UPS systems out of 3 in the alcoves and LHC odd points • Machine can start with one UPS system out of 2 in the UA and US zones • New UPS configurations allows to wait for the next stop for repairing an UPS failure • Gives us more time for preparing and optimizing the intervention • UPS redundancy restored(and improved) • Increases availability for all users, including EN-EL for fault repairs 13 EDMS No.1354977 11/02/2014

  14. LHC Beam Operation Committee Changes in UPS Configurations New UPS Systems – EMC Considerations • APC Silcon UPS systemswell-known to produce noise at 8 kHz • High frequency noise caused byswitching transistors (IGBTs) for creatingthe sine wave at the output • Switching frequencies varies according tothe UPS manufacturer and the design • New UPS specified according to applicable standards (IEC-62040-2) • With the objective of attenuating perturbation at around 8 kHz:reduce noise level or shift it to higher frequencies (MHz frequencies are damped by distribution cables) 14 EDMS No.1354977 11/02/2014

  15. LHC Beam Operation Committee Changes in UPS Configurations New UPS Systems – EMC Performance • Industrial double conversion BORRI UPS selected from invitation to tender • New UPS fully compliant with required standard (IEC-62040-2: EMI and EMC) • CERN internal (re-)qualification of the new UPS with the help of TE-EPC • Noise immunity (UPS = victim) • Burst immunity (high frequency, low power): within IEC standards • Surge immunity (lightning, high power): very good (2 x IEC standard levels) • Noise emission (UPS = aggressor) • EMC conducted noise on AC input/output lines created by the UPS: within IEC standards • UPS output (< 100 kHz): the peak at ~8 kHz (now at ~7 kHz) is reduced by a factor 5 • UPS output (> 100 kHz): another peak appears at ~1.3 MHz (but still 4 times lower than the existing at 8 kHz) 15 EDMS No.1354977 11/02/2014

  16. LHC Beam Operation Committee Changes in UPS Configurations EMC Performance Comparison 0.4Vrms @ 1MHz 3Vrms @ 8kHz 16 EDMS No.1354977 11/02/2014

  17. LHC Beam Operation Committee Changes in UPS Configurations EMC Performance – Situation Assessment in the Tunnel UPS output 5 m Downstream distributionswitchboard Downstream distributionswitchboard with UPS OFF 150 m Local distribution in tunnel Local distribution in tunnel with UPS OFF 17 EDMS No.1354977 11/02/2014

  18. LHC Beam Operation Committee Changes in UPS Configurations Conclusion • Change of UPS system topology: • Conventional double conversion topology much more reliable • New UPS system network configuration • Delocalization in points 5, 7 and 8 (R2E project) • UPS network majorly improved during LS1: • Safe powering for machine protection system with independent and redundant paths • Availability increased for all users and thus for LHC operation • Tolerance to the first UPS failure in each zone • Noise in the 8 kHz range reduced with new UPS systems • Noise in the MHz range: ‘false’ problem since noise is attenuated along the distribution cables • Up to now: ~80 new UPS BORRI installed and in operation on surface and underground, no problem reported today • Filtering solution (MHz) being studied with TE-EPC 18 EDMS No.1354977 11/02/2014

More Related