TEKNIK-TEKNIK PERANCANGAN PROJEK BINAAN

TEKNIK-TEKNIK PERANCANGAN PROJEK BINAAN. A TYPICAL BAR CHART. AKTIVITI FOUNDATION GROUND BEAM STRUCTURE WALL ROOF ELECTRICAL PIPING FINISHING EXTERNAL WORKS. MONTH 1 2 3 4 5 6 7 8 9 10 11 12 13. Rangkaian . Anak Panah.

teryl
Télécharger la présentation

TEKNIK-TEKNIK PERANCANGAN PROJEK BINAAN

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TEKNIK-TEKNIK PERANCANGAN PROJEK BINAAN

  2. A TYPICAL BAR CHART AKTIVITI FOUNDATION GROUND BEAM STRUCTURE WALL ROOF ELECTRICAL PIPING FINISHING EXTERNAL WORKS MONTH 1 2 3 4 5 6 7 8 9 10 11 12 13

  3. Rangkaian Anak Panah (Arrow Networking) A B Akt. Atas Anak Panah Tamat Mula /Milestone CPM Aktiviti Nod /event Forward Pass A 1 3 Backward Pass B 4 2 • - CPM – Critical Path Method; CPA – Critical Path Analysis • (2) - PERT – Program Evaluation dan Review Technique • (3) - Rajah Rentetan (Precedence Program)

  4. Dependency/Bergantungan Berturutan 3 A B C 4 1 2 3 F D 5 6 E Serentak

  5. 1 Merge A B 2 E 5 6 C 3 D 4 6 E E F 1 2 5 G Burst 5

  6. CPM CRITICAL PATH METHOD MEMBINA RANGKAIAN ? A • APAKAH AKTIVITI SEBELUM? • APAKAH AKTIVITI SELEPAS? • APAKAH AKTIVITI SERENTAK? • JANGKAMASA (DURATION) A ? A B • SIZE KUMPULAN • JUMLAH KUMPULAN • LOJI/PERALATAN • DLL

  7. ACTIVITY ON ARROW NERTWORK PRECEDENCE DIAGRAM BAR CHART

  8. ACTIVITY ON ARROW NERTWORK PRECEDENCE DIAGRAM BAR CHART

  9. ACTIVITY ON ARROW NERTWORK PRECEDENCE DIAGRAM BAR CHART

  10. ACTIVITY ON ARROW NERTWORK PRECEDENCE DIAGRAM BAR CHART

  11. PRECEDENCE DIAGRAM EXCAVATE FOUNDATIONS A B POUR CONCRETE

  12. PRECEDENCE DIAGRAM 0 6 STEELFIXING 6 8 2 2 ERECT FORMWORK 0 16 6 15 CONCRETING 9 4

  13. Grade S Approaches N Apron N wing walls N roof slab Base Slab N side walls S side walls S roof slab Clear site S Apron S wing walls Grade S Approaches PRECEDENCE DIAGRAM

  14. CRITICAL & NON CRITICAL ACTIVITIES ACTIVITIES FOUNDATION GROUND BEAM STRUCTURE WALL/DR/WIN ROOF ELECTRICAL PIPING FINISHING EXTERNAL WORKS MONTH 1 2 3 4 5 6 7 8 9 10 11 12 13 CRITICAL ACTIVITIES NON-CRITICAL ACTIVITIES

  15. FLOATS/APUNGAN START EVENT FINISH EVENT TEi TLi TEj TLj Activity duration Total float Free Float Activity duration Independent float Areas of shared float

  16. LANGKAH 1 DAN 2

  17. LANGKAH 3 1. Menyediakan taqpak, mengukur & menggali tanah 2. Mengkonkrit Asas, Tiang & Rasuk Bumi 4. Memasang rangka tingkap & pintu 9. Kakilima dan parit 3. Menerap dinding bata 5. Kerja bumbung & siling 6. Pemasangan letrik 7. Tangki dan paip air 8. Tangki dan saluran najis 10. Kerja-kerja penyudahan 11. Pembersihan & penyerahan

  18. 2 6 7 S 1 3 4 5 11 D TF EST LST EFT LFT 8 9 10

  19. PENYEDIAAN RAJAH RENTETAN • Bahagikan projek kepada beberapa aktiviti. • Tentukan jangkamasa setiap aktiviti. • Kenalpasti perhubungan antara aktiviti-aktiviti:- • - dependent • - parallel • - overlapping • - dulu, kemudian • Lakarkan rajah Rentetan • Hitung masa projek • Hukmum Rangkaian Kerja • Mula - akhir • Tiada nod tergantung • Tiada gelung • Satu anak panah menyambung 2 nod • Dari kiri ke kanan.

  20. Rajah Rentetan (Precedence Diagram) Nod Sumber Nombor aktiviti n Nama aktiviti Jangka masa d TF Masa terluang (float) Masa mula terawal EST LST Masa mula terakhir Masa siap terakhir EFT LFT Masa siap terakhir d i j 1. ESTj = (EFTi) = ESTi - di 2. LFTj = (LSTj) = LFTj - dj 3. EFTj = ESTj + di 4. LSTj = LSTj - di • TFj = LSTj - ESTj

  21. Definision R/R • EST – masa terawal memulakan sesuatu aktiviti. • LST - masa terakhir memulakan sesuatu aktiviti. • EFT - masa terawal siap • LFT - masa terakhir siap Contoh Projek Aktiviti Masa/hari 1 2 3 4 5 6 1 3 2 4 6 1

  22. 1 1 1 3 3 2 4 3 0 4 3 1 1 3 6 4 4 7 10 2 2 6 1 1 0 0 10 10 0 0 11 11 3 4 3 5 2 1 6 0 1 2 4 4 3 4 10 10 • Awal (forward pass) • Terakhir (backward pass) LSTj = LSTj - dj

  23. Masa JUMLAH SUMBER