CDAWG Regulatory Update – MDAQMD

CDAWG Regulatory Update – MDAQMD. Alan De Salvio Deputy Director - Operations. MDAQMD Board Actions. Intra-air basin and Inter-air district ERC trade to AVAQMD (150 tons (per year) of NOx)

Télécharger la présentation

CDAWG Regulatory Update – MDAQMD

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CDAWG Regulatory Update – MDAQMD Alan De Salvio Deputy Director - Operations

  2. MDAQMD Board Actions • Intra-air basin and Inter-air district ERC trade to AVAQMD (150 tons (per year) of NOx) • $300,000 in unobligated FY11/12 Carl Moyer funds to AVAQMD; $40,000 in unobligated FY11/12 Carl Moyer funds to SJVAPCD • Met with SCAQMD Board at their May 2014 retreat • RACT revision to Rule 464 – Oil-Water Separators • 3.25% permit fee increase effective 1/1/2015 • Sponsoring legislation to allow local regulation of unpaved road speeds

  3. Photovoltaic Project Dust • In May 2014 expanded existing Dust Control Plan guidance (dust rule enforceable and CEQA mitigation) to include specific solar project fugitive dust control (construction AND operation): • SCAQMD 403 signage • Exposed sand/fines stabilization • Perimeter wind fencing (4 ft) and maintenance • Road, parking, earthen surface stabilization Will be retrofit as required by Complaint/Nuisance to older projects

  4. Federal SIP Cleanup • In direct response to USEPA request we have prioritized identifying SIP cleanup actions • As an initial action we have requested state and federal concurrence on the invalidity of SIP submittals affecting 23 rules for both San Bernardino County and Riverside County (October 1, 2014 request to CARB) • Future SIP cleanup actions include: identifying ancient SIP rule removals, expanding SIP applicability of selected past MDAQMD SIP actions, and correction/synchronizing MDAQMD/CARB/USEPA SIP databases

  5. MDAQMD Rule Development • Federal RACT SIP supplement identified 461 –Gasoline Transfer and Dispensing, 462 – Organic Liquid Loading, 463 – Storage of Organic Liquids, 1104 – Organic Solvent Degreasing, 1160 – Internal Combustion Engines, 1161 – Portland Cement Kilns as needing RACT update • 75 ppb RACT SIP update will add Rule 1157 – Boilers and Process Heaters • Many of these will be minor updates, but 1157, 1160 and 1161 may not be minor

  6. Rule 1160 Draft Update • MDAQMD currently has 1014 engine permits (455,420 horsepower) • Current rule covers 7500 square miles (federal ozone non-attainment area) with 500 hp applicability, controlling 17 engine permits (58,832 hp) – 1990s RACT • Preliminary draft rule covers 20,000 square miles with 50 hp applicability, affecting 122 permits (177,629 hp) – 10 of which will control (29,954 hp) – presumptive 2014 Federal RACT • ~1854 tons per year of ultimate NOx reductions (by 75 ppb plan attainment year) • Public draft soon

  7. Air Monitoring • TEOM and Hi-Vol conversion to BAMs (one co-located Hi-Vol retained in Victorville) • Panoramic site cameras coming – one in testing • Contracting for ozone mapping • Expanding air quality forecasting and air quality data availability on MDAQMD website • Developing increased granularity burn/no-burn forecast tool (current forecast is monolithic for entire air basin)

  8. In addition • Strong community outreach and education effort, including support of Mojave Environmental Education Consortium (MEEC), science fairs, poster contest, solar cook-off, Exemplar awards, health advisories (high winds and wildfires) • Continue to make progress on carbon-neutral building (now four electric vehicle charging stations and considering expanding pv system to car shades)