An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Google Data Center Video Tour Spring 2009

  2. Google Data Center A This One!

  3. Data Center Vitals • Capacity: 10 MW IT load • Area: 75000 sq ft total under roof • Overall power density: 133W/sq ft • Prototype container delivered January 2005 • Data center built 2004-2005 • Construction completed September, 2005 • Went live November 21, 2005

  4. Pictorial History • Brainstorming – Circa 2003

  5. Pictorial History • VERY rough scale model – Note yellow sticky note chillers and towers

  6. Pictorial History • Prototype arriving at Google, Jan 2005

  7. Pictorial History • The first crane was too small -- Take 2

  8. Pictorial History • Google prototypes first airborne data center

  9. Pictorial History • And into the parking garage we go…

  10. Plan View - Orientation Equipment Yard Cooling Plant Container Hangar

  11. Equipment Yard Tour

  12. Equipment Yard Recap • Use free cooling • Economize (water, air, oil, etc) • Optimize power distribution • Use high-efficiency transformers

  13. PUE Constituents and Cooling Plant Breakdown (TTM) 85%

  14. Plant Tour

  15. Cooling Plant Recap • Use free cooling • Limit chiller hours

  16. Additional Vitals • 45 containers, approx. 40000 servers • Single and 2-story on facing sides of hangar • Bridge crane for container handling

  17. Hangar Tour

  18. Container Details • Standard 1AAA shipping container modified for Google use • 1160 servers per container • Approx. 250KW total power • Container power density approx. 780 W/ sq ft • 27°C (81°F)cold aisle

  19. Container Tour

  20. Container Recap • High-efficiency UPS • Eliminate hot/cold mixing • Blanking plates • Tightly controlled air flow paths • Raised temperature cold aisle • Close-coupled cooling

  21. More Container Details

  22. Container Cross-Section

  23. Google Data Center A This One!

  24. Thank you!

  25. Best Practices Panelists Kenneth G. Brill Founder, Executive Director, Uptime Institute James Hamilton VP & Distinguished Engineer, Amazon Web Services Olivier Sanche Senior Director Data Center Services, eBay William Tschudi PI, Applications Team, Environmental Energy Technologies Division, LBNL Luiz Barroso, (moderator) Distinguished Engineer, Google