1 / 14

Upcoming Dates Accumulator Ring:

Upcoming Dates Accumulator Ring:. ASAC Review September 22-24 DOE Review October 2003 Extraction magnets being assembled Injection DC Magnets and Kickers ( Complete ) in House. HEBT and RTBT Collimators Delivered Ring 1 and 2 Collimator Chambers Coated Design complete July 2003

tobias
Télécharger la présentation

Upcoming Dates Accumulator Ring:

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Upcoming Dates Accumulator Ring: • ASAC Review September 22-24 • DOE Review October 2003 • Extraction magnets being assembled • Injection DC Magnets and Kickers (Complete) in House. • HEBT and RTBT Collimators Delivered • Ring 1 and 2 Collimator Chambers Coated • Design complete July 2003 • More ½ cells delivered • First doublet cell assembled • RF Cavities delivered – scheduled for late September. • First quarter cell assembled

  2. Hot Topics • New ½ cell Lifting fixture design sent to ORNL for review. • Magnet heat load verification/water flow verification. Hemmer/Lambiase • Lambertson coil re- design - Complete bid package • Lower pressure available. Need cable information. • List of Central Shops Work yet to • be done. • FY 2004 Budget • Commit FY 2003 Funding

  3. Hot Topics ORNL Wednesday Morning Phone Conference • Magnet water flow and resistance measurements. • Water system pressure lowered to 100 psi or less delta P. • 36Q85 must define installation configuration (they are doing drawings). New engineer at ORNL for this area – visit in three/four weeks. • Here is the estimate for pressure drop to the Ext. Septum and Collimator Doublet: •              Ext. Septum Magnet                  6.3 psid             assume 10 psid •              Collimator Doublet Magnet          9.2psid              assume 14 psid •  We would like to run at 120 psig therefore 110 psid at the inlet of the Lambertson.  The ideal return pressure would be 30 psig therefore the return pressure at the magnet would be 40 psig.  Therefore, the available delta-P would be 70 psid.  We could go as high as 150 psig supply yielding 100 psid.  Likewise with the Doublet 105 psig inlet, 45 psig return and 60 psid.  OR 135 psig inlet, 45 psig outlet and 90 psid. •  If so, what is the highest temperature the doublets can run at? •                                                  Let me know,  Jim

  4. Hot Topics ORNL Wednesday Morning Phone Conference -----Original Message-----From: Jim Schubert [mailto:schubertjp@ornl.gov]Sent: Monday, June 30, 2003 4:11 PMHere is the actual cooling parameters for the ring magnets.  Please note I was quoting the inlet temperature for the collimator loop and not the magnet loop.  Sorry.Magnet DI Water Cooling Loop        Inlet temperature (set point)                   87 F                    30.56 C        Design Return Temp                              112 F                   44.44 C        Total system flow (available)                   1067 gpm                4033.26 lpm        Total Heat Removal      (HX)                    13.2 MM Btu/hr  3887 kW         Pump discharge Pressure                 275 Ft-head             120 psid        Design Supply Pressure                                                  150 psig        Design Return Pressure                                                  30 psig         13 psig (min)

  5. HEBT Magnets HEBT Dipole, 12Q45 Quadrupole, & 16CD20 Correctors Installed. HEBT/RTBT 27CD30 Corrector (BNL participation complete other than payment). • NETC – 7 verticals + 2 horizontals at ORNL . HEBT/RTBT 21Q40 Quadrupole – Phase II • 8 Magnets to be shipped from BNL. • ORNL received 8 magnets and 5 frames to ORNL. • Third shipment dispatched end of July? Final shipment dispatched end of August?.

  6. Ring Magnets • 902 ½ Cell Assembly Area • Production on hold for magnet acceptance/inspection • Lifting fixture for ORNL ring crane. • 17D120 Dipole – complete, 12 of 33 at ORNL • 21Q40 Quadrupole – complete, 11 of 29 at ORNL • 26Q Quadrupole – complete, ready to install

  7. Ring Magnets • 30Q Quadrupole Requisition (1st article measurement 30Q44 complete) • Shipment #1, #2 in house • Shipment #3, #4 in house, inspection • Shipment #5 in customs • High multipole component on 30Q44 and 30Q58. • 21S26 High Field Sextupole (production measurements priority 2) • Production, 9 of 13 in house and accepted. • 6 magnets measured • One shorted magnet returned to Alpha for repair? • 26S26 High Field Sextupole • 1st article approved 5/15/03 – In production. • 27CDM30 Corrector - complete, 11 of 29 at ORNL

  8. Ring Magnets • 21CO26 Corrector – 8 at ORNL – one spare at BNL • 21CS26 Corrector – complete, 3 of 9 at ORNL • 41CDM30 Corrector (production measurements underway) • 7 of in house. • #5 failed high pot – returned to the vendor. • #1 and #2 returned to the vendor. • 36CDM30 Corrector(production measurements complete) • Ready for installation.

  9. Special Injection Magnets Injection Vacuum Chambers • In the shops – vacuum group to leak check. Injection Septum Magnet - magnet measurements in 902. Injection dump septum magnet (delivery date?) - SDMS vacuum chamber Chicane Magnet #2 (magnet meaurements), Chicane Magnet #3 (delivered – next first article magnetic measurement), Chicane Magnet #4 (returned to NETC) – Z Bumps IV in the works? Chicane Magnet #1 Alpha Magnetics delivery date ?? Magnet Stands – Complete Thin Foil Mechanism – D. Gassner motor control design. Thick (Injection Dump) foil fabrication underway Injection Kicker Magnets • Production Assembly #2 long pair complete, #1 short magnet pair complete. • Shipping container magnet • Ceramic Chamber Coating Continuing

  10. Magnet Measurement Schedule First Articles • 26S26 – Done • 30Q44 – Done • 30Q58 – Done, high multipole component! • Chicane #2 • Chicane #3 • Chicane #4 • Chicane #1 • Chicane #2 and #3 together • Injection septum • Dump septum • 36Q85 • 36CDR30 • Lambertson Magnet Production Measurements LARGE APERTURE COIL SMALL APERTURE COIL • 26Q40 – Done • 36CDM30 - Done 21S26 • 41CDM4026S26 • 30Q58 • 30Q44 • 36Q85/36CDR30 with 26 cm coil?

  11. Special Extraction And RTBT Magnets Extraction Kicker Magnets • Ferrite being delivered • All drawings approved • Shops RFQ for downstream kicker assembly Lambertson Magnet • Drawings being checked. • Specification and SOW complete. • ORNL Design Review Completed/Minutes Sent. 36Q85 - Fifth production coil winding complete 36CDR30 – All Coils Wound

  12. Collimators - HEBT Friday 11:00 Weekly Meeting in the EAG Conference Room • HEBT Collimator Beam Line Stand - RFQ approved • HEBT collimators at ORNL • HEBT Strippers 919B ready for assembly. • HEBT Momentum Collimator shielding contract with Oak Ridge Machine Shop • HEBT Momentum Collimator Shops RFQ. Remaining Work: Assemble and drive HEBT Strippers

  13. Collimators - Ring Friday 11:00 Weekly Meeting in the EAG Conference Room • Procurement STATUS SDMS – ring 1 (primary) collimator ordered • Moveable and Primary Shielding Layout must be revised for remote clamp. • Vacuum Chambers for Ring 2 and 3 received at BNL for TiN coating. • Estimated Delivery for Ring 2 and 3 4/04. Remaining Work: Primary/Moveable Collimator Stand and Shielding, Assemble and drive moveable scrapers, Ring 1 and 2 shielding order

  14. Collimators - RTBT Friday 11:00 Weekly Meeting in the EAG Conference Room • RTBT #1 received at ORNL 49,750 lbs. • New RTBT #2 top lifting plate change order. Remaining Work: RTBT 1 and 2 shielding, stands, and jacks.

More Related