An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Caythorpe Gas Storage Project Liaison Committee Meeting 28th September 2009

  2. Agenda • Project Status Report – September 2009 • Archaeological site investigation • Bridge design • Seismic survey • Traffic management plan • Ongoing community liaison • Environmental support fund • Activities on site within coming weeks / months • Questions Caythorpe Liaison Committee 28th September 2009

  3. Health, Safety & Environment • No on or off site complaints (to date) • No on or off environmental impacts (to date) • No accidents, incidents or near misses to report (to date) • Project working under the “Construction Design & Management Regulations” regulated by the Health & Safety Executive • Site visit by HSE Construction Division 27th August. No issues of concern raised • Baseline noise survey completed August 2009 and issued to ERYC • Noise, Vibration, Dust Management and Monitoring Scheme submitted to ERYC (in accordance with planning conditions) Caythorpe Liaison Committee 28th September 2009

  4. Current Status • Demolition of existing equipment completed in June • Archaeological site investigation ongoing • Geotechnical site investigations Caythorpe Liaison Committee 28th September 2009

  5. Archaeological Site Investigation • Located on the margins of a settlement occupied in the late Iron Age, Roman and early Anglo-Saxon periods (about 200BC to AD700) Caythorpe Liaison Committee 28th September 2009

  6. Archaeological Site Investigation Caythorpe Liaison Committee 28th September 2009

  7. Archaeological Site Investigation Caythorpe Liaison Committee 28th September 2009

  8. Invitation to an Archaeological Site Visit • Liaison Committee Saturday 10th October • Boynton School w/c 12th October Caythorpe Liaison Committee 28th September 2009

  9. Bridge Crossing of Gypsey Race • Would like to install October/November 2009 but may delay until Spring 2010 • Design approved by the Environment Agency • Ecological surveys on river ongoing Caythorpe Liaison Committee 28th September 2009

  10. Bridge Crossing of Gypsey Race – Existing View Caythorpe Liaison Committee 28th September 2009

  11. Bridge Crossing of Gypsey Race – Proposed View Caythorpe Liaison Committee 28th September 2009

  12. Water Vole is a protected species and present on the Gypsey Race including location of bridge crossing Ongoing daily surveys on the river Habitat management to encourage voles to move along the river Fallback option is to move the voles under licence from Natural England Ecological Mitigation & Monitoring Strategy submitted to ERYC (in accordance with planning condition) Water Voles Caythorpe Liaison Committee 28th September 2009

  13. Seismic survey underway, due to complete mid November 7 day/week operation. Mitigation measures in place to avoid damage to land and protect archaeology and ecology Vibration monitoring at residential properties Seismic Survey Caythorpe Liaison Committee 28th September 2009

  14. Seismic Survey – Notification to Residents Caythorpe Liaison Committee 28th September 2009

  15. Seismic Survey – Notification to Residents Caythorpe Liaison Committee 28th September 2009

  16. Construction Traffic Management Plan Caythorpe Liaison Committee 28th September 2009

  17. Construction Traffic Management Plan Caythorpe Liaison Committee 28th September 2009

  18. Environmental Support Fund The Fund will be structured into two elements: • An initial one-off sum of £150,000 which is available up until the completion of construction of the project (2012); and • An ongoing annual budget of £5,000 as per the Warwick Energy agreement with ERYC (over the 24 year lifespan of the planning permission this equates to £120,000) • The allocation of monies will be subject to applications to the Liaison Committee in accordance with published guidelines Caythorpe Liaison Committee 28th September 2009

  19. Future Activity October-December 2009 • Completion of seismic survey by mid November • Completion of archaeological site works for this season (with remainder of work to be done in spring) • Moving of water voles if habitat management unsuccessful • Construction of bridge and access road (although may be delayed until spring) Caythorpe Liaison Committee 28th September 2009

  20. Point of contact for seismic survey IMC Geophysics International Ltd c/o Garland Total Vehicle Solutions Lancaster Road Carnaby Industrial Estate Carnaby Bridlington YO15 3QY Tel: 07810 855318 Caythorpe Liaison Committee 28th September 2009

  21. Paul Dacombe Consents & Licencing Manager Caythorpe Gas Storage Project Centrica plc Millstream West Maidenhead Road Windsor Berkshire SL4 5GD Mobile 07789 570416 paul.dacombe@centrica.com Points of contact for project Justin Kenyon Site HSE Manager Caythorpe Gas Storage Limited Caythorpe Well Site Rudston Driffield YO25 4JD Site Office 01262 420177 Mobile 07904200995 justin.kenyon@centrica.com • Project Website Caythorpe Liaison Committee 28th September 2009

  22. Questions? Caythorpe Liaison Committee 28th September 2009