1 / 17

Linac 4 High Power RF

Linac 4 High Power RF. O. Brunner & N. Schwerg. Summary. Installation Phase adjustment campaign High power equipment Procurement of “auxiliaries” New 2.8 MW klystrons LEP klystrons. Installation (1). Klystron hall: WG Phase 1 completed Circulators, RF loads Water distribution

vance
Télécharger la présentation

Linac 4 High Power RF

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Linac 4High Power RF O. Brunner & N. Schwerg

  2. Summary • Installation • Phase adjustment campaign • High power equipment • Procurement of “auxiliaries” • New 2.8 MW klystrons • LEP klystrons

  3. Installation (1) • Klystron hall: • WG Phase 1 completed • Circulators, RF loads • Water distribution • Klystron racks

  4. Installation (2) • tunnel: • WG Phase 2 completed • In process: phase adjustment

  5. Phase adjustment (1) • The distance between the cavities (time of flight of particles) defines the phase difference required between the two RF channels • Adjustment procedure • Measure the actual ΔΦ (i.e. WG electrical length) • Modify WG distribution such to get ΔΦ ≈ 20˚ • Insert a phase shifter(0 - 60˚) in one arm for fine adjustments • Precision of measurements: ≈ 100 ps (≈ 10˚) (circulator comp.: ≈ 100 ps(≈ 10˚)) cavities WG klystron magic T circulators

  6. Phase adjustment (2) => All circulators to be moved (except for PIMS B C & PIMS C D) • ”heavy procedure” • less posts in WG system -> reduces the risk of arcing

  7. High Power equipment: "auxiliaries“(1) • New circulators: contract in preparation (ATF (DE)) (≈ 500kEuros) • RF loads: second batch delivered. On time. • Klystron garages: LEP garages to be refurbished (not started) • RF drive amplifiers: proto under test • Focusing power supplies: Israeli contribution – ok • Arc detectors: proto validated • Blowers: not started • Circulator control units: to be built • Magic Tees: prototype @ CERN. Order placed • Phase shifters: proto validated

  8. High Power equipment: "auxiliaries“(2) • Gun tanks: in production/assembly • Gun tank equipment: resistors, heater transformer & power supplies (TE/EPC)

  9. New 2.8 MW klystrons (1) • Orders were placed in 2011 with CPI and Thales • 4 klystrons each • CPI:first klystron delivered in July. Successfully tested and validated in September. • Thales: first klystron presently under tests at the factory (expected delivery: end of Oct.) • Delivery schedule • CPI & Thales: • second klystron in January’13, • all four klystrons before Fall ‘13

  10. New 2.8 MW klystrons (1) • CPI klystron

  11. LEP klystrons: what de we have? EEV (12) 19 “eligible” LEP klystrons Philips (4) Thomson (3)

  12. LEP klystrons: what do we need for L4? output power 1.3 MW • we need klystrons that can produce > 1.3 MW • we need klystrons that can be run at different working points • The LEP klystron were designed and tuned to reach optimum efficiency (>65%) when operated at well defined operating working points (HV, Icat, drive power, impedance seen by klystron, etc) • The klystrons suffer from instabilities when operated under different conditions

  13. How do we test the LEP klystrons ? PfwdPrfl • DC power settings: 108 kV, 22 A • Increase klystron power as a function of: • Circulator compensation current (impedance change) • Phase variation (to mimic the beam passage) • Detect at which output power the instabilities occur RF load (Cu cavity) circulator klystron Phase shifter RF load

  14. LEP klystrons performance results Joanne: 1300 kW Emily: 1010 kW Alison: 1145 kW Julie: 1050 kW (now dead) Lynda: 1100 kW (3 MeV) Elia: < 1000 kW (SM18)

  15. LEP klystrons: what can we expect? • 5/12 EEV tubes tested: • one is very good :1300kW • others are limited to about 1100 kW or less (one died after the test) • Phillips & Thomson tubes are known to be even more prone to oscillations than EEV klystrons • 1/7 tested: < 1000 kW Question: can one dream of getting significantly more than about 1 MW per LEP klystron ? (in the required operating mode) NO !

  16. Conclusions (1) • Installation: • In progress • Phase adjustments in progress – heavy duty, crucial for future reliability • Adjustments: ≈ 10˚ • High power equipment & auxiliaries • Preparation is ongoing • All “big contracts” placed (new circulators: in preparation) • 3 operational test places (B112, 3MeV, SM18) • New 2.8 MW klystrons • Some delays • First CPI klystron successfully tested and validated at CERN • All klystrons shall be delivered before Q3 2013

  17. Conclusions (2) • LEP klystrons • Preparation and test in progress (slow down to be expected with the departure of Nikolai!) • 1/3rd of the LEP klystrons have been tested: • All are capable of more than 1.3 MW peak power (for well defined WP, as expected!) • All (except one) are unstable in the region 1 – 1.3 MW (as expected!) • Despite all efforts made instabilities could not be suppressed/reduced • One tube died after 6 months of testing: vacuum leak in RF input connector Stability maps (measured according to the L4 mode of operation) show that the LEP klystrons modified for Linac4 are limited to 1 – 1.1 MW • We need clear instructions from Project Leader: • Do we continue spending CERN resources on this effort? • What is the strategy for klystron installation (Do we install them? Which klystron at which position? Is there a power limit?) • How many additional 2.8 MW klystrons that must be ordered ?

More Related